Regulation 8, The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010: Fulfillment of RPPOs
The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 - Regulation 8
Text of regulation 8
Fulfillment of RPPOs
[8. Fulfillment of RPPOs.- (1) The quantum of RPPO inclusive of transmission and
distribution losses mentioned in sub-regulation (2) of regulation 4 shall be applicable to
captive and open access user(s)/ consumer(s) from the date made by the Commission in the
Official Gazette.
(2) The obligated entities shall meet the RPPOs on quarterly and yearly basis as per
provisions specified in regulations 4 and 5 of these regulations.
(3) The shortfall, if any, in the compliance of RPPOs in any year shall, unless such
shortfall occurred due to non-availability of Renewable Energy Certificates (RECs) in the
year in which such shortfall occurred, not be allowed to be carried forward to, or subsequent
yearly adjustment against the surpluses of any subsequent year(s).
(4) Failure on the part of any obligated entity to meet its RPPO in any year shall be
dealt in accordance with the provisions contained in regulation 9 of these regulations.]
Previous and next
Questions people ask
Is regulation 8 of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 is recorded.