LawGrids logoLAWGRIDS.ORG

Regulation 8, The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010: Fulfillment of RPPOs

The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 - Regulation 8

Text of regulation 8

Fulfillment of RPPOs

[8. Fulfillment of RPPOs.- (1) The quantum of RPPO inclusive of transmission and distribution losses mentioned in sub-regulation (2) of regulation 4 shall be applicable to captive and open access user(s)/ consumer(s) from the date made by the Commission in the Official Gazette. (2) The obligated entities shall meet the RPPOs on quarterly and yearly basis as per provisions specified in regulations 4 and 5 of these regulations. (3) The shortfall, if any, in the compliance of RPPOs in any year shall, unless such shortfall occurred due to non-availability of Renewable Energy Certificates (RECs) in the year in which such shortfall occurred, not be allowed to be carried forward to, or subsequent yearly adjustment against the surpluses of any subsequent year(s). (4) Failure on the part of any obligated entity to meet its RPPO in any year shall be dealt in accordance with the provisions contained in regulation 9 of these regulations.]

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010

Questions people ask

Is regulation 8 of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Renewable Power Purchase Obligation and its Compliance) Regulations, 2010 is recorded.