Regulation 7, The Himachal Pradesh Electricity Distribution Code, 2009: Stages involved in network expansion planning

The Himachal Pradesh Electricity Distribution Code, 2009 - Regulation 7

Text of regulation 7

Stages involved in network expansion planning

7. Stages involved in network expansion planning:- (a) Defining the task (b) Commencement the planning task which consists of:- (i) recording of the status of the existing distribution network and analysis of its operational situation, (ii) load forecast and analysis–Compilation of data on the characteristic features of the loads that will be incident in the near future and that of the existing loads, (iii) estimation of load development, (iv) examination of the alternative options, (v) checking the issues involved in the above options and also the feasibility of introducing a new transformer, enhancement of existing transformer capacity etc. (vi) establishment of site location and new sub-station design, (vii) modification/Redesign of sub-transmission and distribution networks and its protective arrangement including protective relay setting and coordination. (viii) study on alternatives for least cost investment and also on environmental impact, 40 Compendium of HPERC Regulations, March 2021 (ix) assessment of operational advantages and disadvantages and anticipated supply reliability levels of various options. (x) investment planning, and (xi) procurement of the required network components. Annexure-2 (See para 3.5.2(a) and 3.6.2) LOAD DATA FOR DEMANDS OF 500 KW AND ABOVE TO BE FURNISHED BY THE USER/CONSUMER Name and Address of User/Consumer: S. No Description Details 1 Type of Load (State whether: - steel melting furnace loads, rolling mills, traction loads, other industrial loads, pumping loads, etc.) 2 Maximum Demand (kVA) and Annual Energy Requirement in kWh 3 Year/Years by which full/part Supply is required 4 Location of Load (Furnish location map to scale, indicate details of Consumer category/capacity, nearest Railway Station, and nearest EHV sub-station) 5 Rated Voltage at which supply is required. Whether Single phase or Three-phase supply required 6 Type of supply Normal/Alternate/Dedicated (specify details) 7 Description of Equipment A Motors State purpose and number of installations, voltage and kW rating, starting current, type of motors, types of drives and control arrangements. B Heating Type and kW Rating C Furnace Type of Furnace, Furnace Transformer details Capacity and Voltage Ratio Compendium of HPERC Regulations, March 2021 41 S. No Description Details D Electrolysis Purpose, kVA capacity E Lighting kW Demand 8 Sensitivity of demand to fluctuations in voltage and frequency of supply at the time of Peak Demand (Give details) 9 Voltage sensitivity MVAr/kV 10 Frequency sensitivity MW/Hz MVAr/Hz 11 Phase unbalance imposed on system Maximum (%) Average (%) 12 Maximum harmonic content imposed (Furnish details of devices included with the system for the suppression of harmonics, also furnish the harmonic currents of different orders drawn by each device without filters) 13 Details of any loads, which may cause Demand fluctuations of greater than 500kW at the point of connection, including Voltage Dips (percentage) lasting for 5 seconds and more. (Give details) 42 Compendium of HPERC Regulations, March 2021 EMBEDDED GENERATOR UNIT-WISE DATA Name and address of Generating Company: Location of Generating Plants (s): Generation Volts (kV); Rated kVA/kW Maximum and minimum Active Power sent out (kW) Reactive Power capability (kVAr), if any; Type of Generating Plant—synchronous, asynchronous, etc.; Method of voltage control; Generator transformer details, if applicable; Requirements for Top-up supplies and/or standby supplies; Generator kW/kVAr capability chart (at lower voltage terminals); Type of excitation system; Inertia constant kW secs/kVA; Stator Resistance; Direct-Axis Reactance (Sub-transient, Transient and Synchronous); Quadrature-Axis Reactance (Sub-transient and Synchronous); Zero Sequence (Resistance and Reactance); Negative Sequence (Resistance and Reactance); Generator Transformer (Resistance, Reactance, kVA Rating, Tap Arrangement, Vector Group, Grounding, Connection and % Impedance); Automatic Voltage Regulator block diagram, including the data on the gains (forward and feedback), time constants, and voltage control limits; Speed governor block diagram detailing the governor fly-ball, if applicable, and control system and Prime Mover time constants, together with the turbine rating and maximum power Standby requirements: Rated Capacity and Minimum Generation of each Generating Unit and Power Station in kW for standby capacity requirements. Generating Unit and Power Station auxiliary Demand (Active Power and Reactive Power) in kW and kVAr, at rated capacity conditions. Interface Arrangements the means of synchronization between the distributors and User; Details of arrangements for connecting to ground that part of the Generator’s System directly connected to the distribution system; The means of connection and disconnection which are to be employed Precautions to be taken to ensure the continuance of safe conditions should any grounded neutral point of the Generating unit become disconnected from ground. Details of Protection System of the Generating Unit Annexure 3 (See para 3.5.2.(b)) Compendium of HPERC Regulations, March 2021 43 Annexure-4 (See para 3.5.2(c)) SYSTEM DATA TO BE PROVIDED BY LICENSEES TO THE INTENDING USERS (1) 33 kV and above distribution line data relevant to the location where connection has been applied/feasible to provide. (2) Details of metering system and protection system proposed. (3) Fault levels at which the consumer should design his equipment. (4) Fault clearance time for consumer's switch gear and (5) Sub-station fault level. Annexure- 5 (See para 3.5.2(d)) SYSTEM DATA OF WHOLE LICENSEE SYSTEM 1. Topological map of Himachal Pradesh marking boundaries of area of supply of the licensee. 2. Distribution map of the licensee drawn to scale of not less than 1 Cm to 2.5 Km showing the existing 11 kV and 33 kV lines and sub-stations within the area of supply. Lines and sub-stations under construction or planned for the next five years shall be shown in dotted lines. 3. Single line diagram of the distribution system showing line length, conductor sizes, sub-station capacity, capacitor sizes with locations of auto-reclosures /Kiosks/Breakers etc. 4. Details of Metering and relaying at 33/11, 22/0.4,11/0.4 kV sub-stations. 5. Details of Grid sub-stations at the point of interconnections as follows: (i) MVA Capacity and voltage. (ii) Number of transformers, capacity of each transformer, voltage ranges of taps. (iii) Fault level at sub-station bus bars, (iv) Bus impendence (v) Sub-station layout diagram. 6. Drawl at interconnection points: Maximum and Minimum MW drawn during last six months from each interconnection with the transmission system or with other distribution licensees. 44 Compendium of HPERC Regulations, March 2021 Annexure-6 (see para 3.6.3) Load Research PROGRAM 1. The licensee shall implement an appropriate load research program for the systematic collection of data describing consumers' energy usage patterns and analysis of the data for energy and demand forecast. 2. The pattern of energy consumed by each sector and the load demand, the period of peak demand etc., shall be determined on the basis of sample surveys taking representative samples from each sector for its different seasonal requirements. A suitable questionnaire shall be prepared for the sample surveys and the data obtained shall be analysed using suitable statistical models. Based on this, load profiles shall be drawn implementing demand side management techniques to match the availability from time to time. 3. The load research program shall assess the following:- (a) demand at the time of system peak, daily, monthly, seasonal or annual, (b) hourly demand for the day of the system peak, monthly, seasonally or annually, (c ) hourly end use demand for the average day of the system peak, monthly, seasonal or annually; (d) total energy consumption for each category by month, season or year. (e) category wise diverse or coincidence factors and load factors (f) category wise non-coincident peak demands. 4. Based on the results of the above analysis, the load forecast shall be made using the appropriate modern forecasting tools wherever applicable. 5. The optimum circuit loading and the maximum number of circuits at any electrical interface between the Distribution and Transmission Systems shall conform to the Distribution System Planning and Security Standards. 6. The loads shall be arranged as far as possible in discrete load blocks to facilitate load management during emergency operations. 7. Load flow and other system studies shall be conducted to locate the position of outlets from sub-stations, capacitor installations, distribution transformers, and to contain voltage variation and energy losses within reasonable limits. 8. The following parameters of equipments and system designs shall be standardised to facilitate easy replacement and reduction of inventories of spares in stores: (a) Capacities of power transformers, (b) Capacities and designs of distribution transformers, (c) 33kV/22kV/ 11kV sub-station layout. (d) Pole mounted sub-stations, Compendium of HPERC Regulations, March 2021 45 (e) Sizes of bus bars, (f) Capacities and ratings of circuit breakers and instrument transformers, (g) Earthing, (h) Lightning arresters, (i) Control panels, (j) Station batteries, (k) Fire extinguishers. (l) Maintenance tools (m) Safety equipments (n) Energy meters (o) Wires and cables (p) Clamps and connectors 9. The planning of the Distribution System shall always keep in view the cost effectiveness and reduction in energy losses without sacrificing the requirements of Security Standards and Safety Standards for the Distribution System. 10. The distribution licensee shall plan the distribution system expansion and reinforcement keeping the following in view alongwith all other measures to accommodate the advancement in technology prevailing at the time:- (a) Optimising the ratio of single, two and three phase LT Lines. (b) Optimising the ratio of single to three phase transformers; (c ) Economic ratio of HT and LT line lengths, (d) Use of aerial bunched conductors, (e) Underground cables, (f) Optimizing the number of distribution transformers and their location at the electrical load centres, (g) Replacement of long PVC lines with conductors/ 3 phase service line. 46 Compendium of HPERC Regulations, March 2021 Annexure-7 (see para 3.7.11) Methodology of Load Estimation/Assessment: 1 Domestic and Commercial Loads:- The consumption in domestic and commercial sectors shall be estimated on the basis of the number of consumers and their specific consumption. The past growth rate in the number of consumers in the area shall be studied. In cases where power shortages have been experienced in the recent past, the growth rate to be adopted shall take into consideration the appropriate demand making due allowance in the growth rate to account for increased tempo of household electrification envisaged in the future. The higher level of electrification planned in the area should be kept in view. Energy consumption per consumer shall be estimated after studying the past trends and taking into account the anticipated improvements in the standard of living. 2 Public Lighting and Water Works: The estimates of electricity consumption in public lighting and water works shall be based on the average consumption per kilowatt of connected load, projected on the basis of trends, keeping in mind the likely increase in public lighting and water supply facilities. The number of hours of operation shall be estimated taking into account the past trends and the power cuts if any effected in the area. 3 Agricultural Loads: The power requirement for irrigation pump sets shall be based on the program of energisation of pump sets in the plan period, available resources and the ultimate ground water potential. The average capacity of pump sets shall be worked out considering the mid-year figures for connected load and the numbers of pump sets. 4 Industrial Loads: The power requirements for industrial sector shall be estimated under following three categories, namely:- (a) L.T. Industries ; (b) H.T. Industries with a demand of less than 5 MW; (c) H.T. Industries with a demand of 5 MW and above. (d) EHT Industries The consumption in category (a) and (b) shall be on the basis of historical data duly considering the developments in future. In case of category (c), projection shall be made separately for each industrial unit on the basis of the information furnished by the industrialists and the Department of Industries of the State Government. 5. Non-industrial Bulk Supply: The available data regarding the consumption of bulk supply to non-industrial consumers such as research establishments, military engineering services, supply to power projects etc., and the probable future developments in these areas, shall be considered for the forecast. 6. Other Loads: For other loads, the projections shall be based on the best judgement. Compendium of HPERC Regulations, March 2021 47 Annexure- 8 (See para 4.1.2(c) ) SITE RESPONSIBILITY SCHEDULE Name of Sub-station/Location Site Owner Name of co-ordination officer of site Telephone No. Fax No.: Item of Plant/ Apparatus Plant Owner Safety Responsibility Control Responsibility Operation Responsibility Maintenance Responsibility Remarks kV Switchyard All equipment including bus- bars Feeders Generating Units Other (to be specified) Signatures Plant Owner Safety Responsibility Officer Control Responsibility Officer Operation Responsibility Officer Maintenance Responsibility Officer 48 Compendium of HPERC Regulations, March 2021 Annexure-9 (See para 5.4.3.(3) ) ESSENTIAL LOADS AND PRIORITY OF RESTORATION Priority Type of Load Name of the Sub-station feeding such loads 1. Hospitals, Water Works, 2. Defense Establishments 3. Radio, Television Stations and telecommunication Exchanges/Stations 4. Air Port 5. Important cities 6. Police Stations 7. Fire Stations 8. Process Industries and Mining Annexure –10 (See para 8.4) OPERATIONAL EVENT REPORTING Name of the reporting Organization Date and Time of reporting the /event incident 1 Date and time of incident 2 Location of incident (Name of Sub-station/Line etc.) 3 Description of incident 4 System parameters before the incident (voltage, frequency, flows, generation, etc.) 5 Failure of protection at EHV GSS if any and relay indications. 6 Damage to equipment 7 Supplies interrupted and duration, if applicable 8 Amount of generation lost, if applicable 9 Possibility of alternate supply arrangement 10 Estimate of time to return service 11 Cause of incident 12 Any other relevant information and remedial action taken 13 Recommendations for future improvement/repeat incident Compendium of HPERC Regulations, March 2021 49 Annexure-11 (See para 8.5) RULE NO. 44 A OF THE INDIAN ELECTRICITY RULES, 1956 Rule no. 44 A – Intimation of Accident If any accident occurs in connection with the generation, transmission, supply or use of energy in or in connection with any part of electric supply lines or other works of any person and the accident results in or is likely to have resulted in loss of human or animal life or in any injury to a human being or an animal, such person or any authorized person of the distribution licensee not below the rank of Junior Engineer or equivalent shall send to the Inspector a telegraphic report within 24 hours of the knowledge of the occurrence of the fatal accident and a written report in a form set out in Annexure XIII within 48 hours of the knowledge of the occurrence of the fatal accident and all other accidents. Where practicable a telephonic message should also be given to the Inspector immediately the accident comes to the knowledge of authorized officer of distribution licensee or other person concerned. The Indian Electricity Rules, 1956 Annexure- XIII FORM FOR REPORTING ELECTRICAL ACCIDENTS (See Rule 44-A) 1 Date and Time of accident 2 Place of accident (Village/Town, Tehsil /Thana, District and State) 3 System and voltage of supply (Whether EHV/HV/LV line, sub-station/generating station/consumer’s installations/service lines/other installations) 4 Designation of the Officer-in-charge (in whose jurisdiction the accident occurred) 5 Name of owner/user of energy in whose premises the accident occurred. 6 Details of victim(s) (a) Human S.No. Name Father’s Name Sex of victim Full Postal Address Approx. Age Fatal / Non- Fatal (b) Animal S.No. Description of Animals Number(s) Name(s) of Owner(s) Address (es) of owner(s) Fatal / Non- Fatal 7 In case the victim(s) is /are employee(s): (a) designation of such person(s) (b) brief description of the job undertaken, if any. (c) Whether such person/persons was/were allowed to work on the job. 8 In case the victim(s) is/are employee(s) of a licensed contractor (a) Did the victim(s) possess any electric workman’s permits(s), 50 Compendium of HPERC Regulations, March 2021 supervisor’s certificate of competency issued under Rule 45? If yes give number and date of issue and the name of issuing authority. (b) Name and designation of the person who assigned the duties of the victim(s) 9 In case of accident in the Distribution licensee system, was the Permit To Work (PTW) taken? 10 Describe fully the nature and extent of injuries, e.g. fatal /disablement (permanent or temporary) of any portion of the body or burns or other injuries. In case of fatal accident, was the post mortem performed? 11 Detailed causes leading to the accident (To be given in a separate sheet annexed to this form) 12 Action taken regarding first-aid, medical attendance etc. immediately after the occurrence of the accident (give details) 13 Whether the District Magistrate and Police Station concerned have been notified of the accident (if so, give details) 14 Steps taken to preserve the evidence in connection with accident to the extent possible. 15 Names and designation(s) of the person(s) assisting, supervising the person(s) killed or injured. 16 What safety equipments were given to and used by the person(s) who met with this accident (e.g. rubber gloves, rubber mats, safety belts and ladders etc.)? 17 Whether isolating switches and other sectionalizing devices were employed to deaden the section for working on the same? Whether working section was earthed at the site of work? 18 Whether the work on live lines was undertaken by authorized person(s)? If so, the name and the designation of such person(s) may be given. 19 Whether the artificial resuscitation treatment work on live lines was undertaken by authorised person(s)? If yes, how long was it continued before its abandonment? 20 Names and designations of persons present at and witnessed the accident. 21 Any other information / remarks. Place Time Date Signature Name Designation Address of the person reporting Compendium of HPERC Regulations, March 2021 51 Annexure13 (See para 1.3) LIST OF ABBREWATIONS 1 AAC All Aluminum Conductor 2 AAAC All Aluminum Alloy Conductor 3 ACSR Aluminum Conductor Steel Reinforced 4 BIS The Bureau of Indian Standards 5 Board The HP State Electricity Board 6 CAIDI Customer Average Interruption Duration Index 7 CAIFI Customer Average Interruption Frequency Index 8 CBIP The Central Board of Irrigation and Power 9 CEA Central Electricity Authority 10 CEI Chief Electrical Inspector 11 CT Current Transformer 12 DCR Distribution Code Review 13 DCRP Distribution Code Review Panel 14 EHV EHT Extra High Voltage Extra High Tension 15 GI Galvanized Iron 16 GSS Gas Sub-station 17 HPERC The Himachal Pradesh Electricity Regulatory Commission 18 HV/ HT High Voltage/ High Tension 19 Hz Hertz (cycles per seconds) 20 IDMT Inverse Definite Minimum Time 21 IEEE Institute of Electrical and Electronics Engineers 22 IEC International Electro Technical Commission 52 Compendium of HPERC Regulations, March 2021 23 IEGC Indian Electrical Grid Code 24 IS Indian Standards 25 IP Irrigation Pump 26 kA Kilo Ampere 27 kW Kilo Watt 28 kWh Kilo Watt hour 29 kVA Kilo Volt Ampere 30 LT Low Tension 31 LV Low Voltage 32 MAIDI Momentary Average Interruption Duration Index 33 MAIFI Momentary Average Interruption Frequency Index 34 MCB Miniature Circuit Breaker 35 MVA Mega Volt Ampere 36 MW Megawatt 37 PAP Project affected person 38 PCC Prestressed Cement Concrete 39 PT Potential transformer 40 PTW Permit to work 41 RCC Reinforced Cement Concrete 42 REC Rural Electrification Corporation 43 R&R Rehabilitation and Resettlement 44 SAIDI System Average Interruption Duration Index 45 SAIFI System Average Interruption Frequency Index 46 SCADA Supervisory Control and Data Acquisition 47 SLDC State Load Despatch Centre 48 STU State Transmission Utility Compendium of HPERC Regulations, March 2021 53 Notifications and Orders issued under The HP Electricity Regulatory Commission Distribution Code, 2008 1 [The HPERC constitutes the Electricity Review Panel] NOTIFICATION Shimla-2, the 15 th February, 2013 No. HPERC/392- Vol(II).—In exercise of the powers conferred under clause 2.2 of the Himachal Pradesh Electricity Distribution Code, 2009, the Himachal Pradesh Electricity Regulatory Commission hereby constitute the Electricity “Distribution Code Review Panel” comprising of the following: Sr. No. Name & Designation Representation from 1. The Director (Operation) Distribution Licensee Chairman HPSEB Ltd. Vidyut Bhawan, Shimla- 171004. 2. The Executive Director(TA), HPERC Convener HPERC, Khalini, Shimla-171002. 3. The General Manager, HPPTCL, STU Member Barowalia House, Khalini, Shimla 4. The Chief Engineer(Commercial), Distribution Licensee Member HPSEB Ltd. Vidyut Bhawan, Shimla- 171004. 5. The Convener, HP Small Hydro Generator Member Power Association, B-99, Sector-3, New Shimla-171009, H.P. 6. The Vice President and Chairman , Industrial Consumers Member Power Committee of BBN Industries Association, C/O Single Window Clearing Agency Industrial Area, Baddi-173205 7. The Chief Manager(Electrical), Open Access Consumers Member C/O ACC Ltd., “Anandvas”, /Bulk Consumers 1st Floor Khalini, Shimla-171002 8. The Convener, Power Panel, CII, Bulk Consumers Member Himachal Pradesh State Council, Confederation of Indian Industry (CII) Sector 31-A, Chandigarh-16003 1 Published in R.H.P. dated 16 th February, 2013 at p. 6809-6810. 54 Compendium of HPERC Regulations, March 2021 9. The Superintending Engineer, Non Domestic/ Non Member (P&I)-Unit-II Jal Bhawan Shimla-9 Commercial Consumers 10. The Superintending Engineer, Non Commercial/Non Member Electrical Circle, HP PWD, Domestic Consumers Kasumpati, Shimla-9 11. The President, Shimla Hotel & Commercial Consumers Member Restaurant Association, Hotel Shivalik Near U.S. Club Gate, Shimla-171001. 12. The Consumer Representative Domestic Consumers Member Arcadia,Vill. Ghat-ki-Ber, P.O. Dharampur, Dist. Solan(HP) PIN: 173209. 13. The Superintending Engineer, Distribution Licensee Member HPSEBL (Operation Circle), Kasumpati, Shimla-171009 14. The Vice President, M/S Ruchira Industrial Consumers Member Paper Mill, Trilokpur Road, Kala Amb Distt. Sirmour, HP-173030 1. The Chairman of the Electricity Distribution Code Review Panel shall hold office as such for a period of two years and its all other member shall hold office by the virtue of positions held by them in their respective organisation until changed/replaced by the respective organisation/ consumer group. 2. A member of the Electricity Distribution Code Review Panel, who is a Govt. officer or an employee/officer of any Govt. instrumentality or of any Public Sector undertaking shall draw travelling and daily allowance from his parent department or organization. 3. A member of Electricity Distribution Code review Panel, other than those referred to under sub-para(2) shall be paid fee of Rs.500/- per meeting and TA and DA at the rates admissible, in the State Govt. to its grade-I officers. By order of the Commission Sd/- Secretary, (H.P. Electricity Regulatory Commission).

Previous and next

All provisions of The Himachal Pradesh Electricity Distribution Code, 2009

Questions people ask

Is regulation 7 of the Himachal Pradesh Electricity Distribution Code, 2009 still in force?