Regulation 7, The Himachal Pradesh Electricity Distribution Code, 2009: Stages involved in network expansion planning
The Himachal Pradesh Electricity Distribution Code, 2009 - Regulation 7
Text of regulation 7
Stages involved in network expansion planning
7. Stages involved in network expansion planning:-
(a) Defining the task
(b) Commencement the planning task which consists of:-
(i) recording of the status of the existing distribution network and analysis of
its operational situation,
(ii) load forecast and analysis–Compilation of data on the characteristic
features of the loads that will be incident in the near future and that of the
existing loads,
(iii) estimation of load development,
(iv) examination of the alternative options,
(v) checking the issues involved in the above options and also the feasibility
of introducing a new transformer, enhancement of existing transformer
capacity etc.
(vi) establishment of site location and new sub-station design,
(vii) modification/Redesign of sub-transmission and distribution networks and
its protective arrangement including protective relay setting and
coordination.
(viii) study on alternatives for least cost investment and also on environmental
impact,
40 Compendium of HPERC Regulations, March 2021
(ix) assessment of operational advantages and disadvantages and anticipated
supply reliability levels of various options.
(x) investment planning, and
(xi) procurement of the required network components.
Annexure-2
(See para 3.5.2(a) and 3.6.2)
LOAD DATA FOR DEMANDS OF 500 KW AND ABOVE TO BE FURNISHED BY THE
USER/CONSUMER
Name and Address of User/Consumer:
S.
No
Description Details
1 Type of Load (State whether: - steel melting furnace
loads, rolling mills, traction loads,
other industrial loads, pumping loads,
etc.)
2 Maximum Demand (kVA) and Annual
Energy Requirement in kWh
3 Year/Years by which full/part Supply is
required
4 Location of Load (Furnish location map to scale, indicate
details of Consumer category/capacity,
nearest Railway Station, and nearest
EHV sub-station)
5 Rated Voltage at which supply is
required. Whether Single phase or
Three-phase supply required
6 Type of supply Normal/Alternate/Dedicated (specify
details)
7 Description of Equipment
A
Motors
State purpose and number of
installations, voltage and kW rating,
starting current, type of motors, types of
drives and control arrangements.
B Heating
Type and kW Rating
C Furnace
Type of Furnace, Furnace Transformer
details
Capacity and Voltage Ratio
Compendium of HPERC Regulations, March 2021 41
S.
No
Description Details
D Electrolysis
Purpose, kVA capacity
E Lighting
kW Demand
8 Sensitivity of demand to fluctuations in
voltage and frequency of supply at the
time of Peak Demand (Give details)
9 Voltage sensitivity
MVAr/kV
10 Frequency sensitivity MW/Hz
MVAr/Hz
11 Phase unbalance imposed on system
Maximum (%)
Average (%)
12 Maximum harmonic content imposed
(Furnish details of devices included
with the system for the suppression of
harmonics, also furnish the harmonic
currents of different orders drawn by
each device without filters)
13 Details of any loads, which may cause
Demand fluctuations of greater than
500kW at the point of connection,
including Voltage Dips (percentage)
lasting for 5 seconds and more. (Give
details)
42 Compendium of HPERC Regulations, March 2021
EMBEDDED GENERATOR UNIT-WISE DATA
Name and address of Generating Company:
Location of Generating Plants (s):
Generation Volts (kV);
Rated kVA/kW
Maximum and minimum Active Power sent out (kW) Reactive Power
capability (kVAr), if any;
Type of Generating Plant—synchronous, asynchronous, etc.;
Method of voltage control;
Generator transformer details, if applicable;
Requirements for Top-up supplies and/or standby supplies;
Generator kW/kVAr capability chart (at lower voltage terminals);
Type of excitation system;
Inertia constant kW secs/kVA;
Stator Resistance;
Direct-Axis Reactance (Sub-transient, Transient and Synchronous);
Quadrature-Axis Reactance (Sub-transient and Synchronous);
Zero Sequence (Resistance and Reactance);
Negative Sequence (Resistance and Reactance);
Generator Transformer (Resistance, Reactance, kVA Rating, Tap
Arrangement, Vector Group, Grounding, Connection and %
Impedance);
Automatic Voltage Regulator block diagram, including the data on the
gains (forward and feedback), time constants, and voltage control
limits;
Speed governor block diagram detailing the governor fly-ball, if
applicable, and control system and Prime Mover time constants,
together with the turbine rating and maximum power
Standby requirements:
Rated Capacity and Minimum Generation of each Generating Unit and
Power Station in kW for standby capacity requirements.
Generating Unit and Power Station auxiliary Demand (Active Power
and Reactive Power) in kW and kVAr, at rated capacity conditions.
Interface Arrangements the means of synchronization between the
distributors and User;
Details of arrangements for connecting to ground that part of the
Generator’s System directly connected to the distribution system;
The means of connection and disconnection which are to be employed
Precautions to be taken to ensure the continuance of safe conditions
should any grounded neutral point of the Generating unit become
disconnected from ground.
Details of Protection System of the Generating Unit
Annexure 3
(See para 3.5.2.(b))
Compendium of HPERC Regulations, March 2021 43
Annexure-4
(See para 3.5.2(c))
SYSTEM DATA TO BE PROVIDED BY LICENSEES TO THE INTENDING USERS
(1) 33 kV and above distribution line data relevant to the location where
connection has been applied/feasible to provide.
(2) Details of metering system and protection system proposed.
(3) Fault levels at which the consumer should design his equipment.
(4) Fault clearance time for consumer's switch gear and
(5) Sub-station fault level.
Annexure- 5
(See para 3.5.2(d))
SYSTEM DATA OF WHOLE LICENSEE SYSTEM
1. Topological map of Himachal Pradesh marking boundaries of area of supply of the
licensee.
2. Distribution map of the licensee drawn to scale of not less than 1 Cm to 2.5 Km
showing the existing 11 kV and 33 kV lines and sub-stations within the area of
supply. Lines and sub-stations under construction or planned for the next five years
shall be shown in dotted lines.
3. Single line diagram of the distribution system showing line length, conductor sizes,
sub-station capacity, capacitor sizes with locations of auto-reclosures
/Kiosks/Breakers etc.
4. Details of Metering and relaying at 33/11, 22/0.4,11/0.4 kV sub-stations.
5. Details of Grid sub-stations at the point of interconnections as follows:
(i) MVA Capacity and voltage.
(ii) Number of transformers, capacity of each transformer, voltage ranges of taps.
(iii) Fault level at sub-station bus bars,
(iv) Bus impendence
(v) Sub-station layout diagram.
6. Drawl at interconnection points: Maximum and Minimum MW drawn during last six
months from each interconnection with the transmission system or with other
distribution licensees.
44 Compendium of HPERC Regulations, March 2021
Annexure-6
(see para 3.6.3)
Load Research PROGRAM
1. The licensee shall implement an appropriate load research program for the
systematic collection of data describing consumers' energy usage patterns and
analysis of the data for energy and demand forecast.
2. The pattern of energy consumed by each sector and the load demand, the
period of peak demand etc., shall be determined on the basis of sample
surveys taking representative samples from each sector for its different
seasonal requirements. A suitable questionnaire shall be prepared for the
sample surveys and the data obtained shall be analysed using suitable
statistical models. Based on this, load profiles shall be drawn implementing
demand side management techniques to match the availability from time to
time.
3. The load research program shall assess the following:-
(a) demand at the time of system peak, daily, monthly, seasonal or
annual,
(b) hourly demand for the day of the system peak, monthly, seasonally or
annually,
(c ) hourly end use demand for the average day of the system peak,
monthly, seasonal or annually;
(d) total energy consumption for each category by month, season or year.
(e) category wise diverse or coincidence factors and load factors
(f) category wise non-coincident peak demands.
4. Based on the results of the above analysis, the load forecast shall be made
using the appropriate modern forecasting tools wherever applicable.
5. The optimum circuit loading and the maximum number of circuits at any
electrical interface between the Distribution and Transmission Systems shall
conform to the Distribution System Planning and Security Standards.
6. The loads shall be arranged as far as possible in discrete load blocks to
facilitate load management during emergency operations.
7. Load flow and other system studies shall be conducted to locate the position
of outlets from sub-stations, capacitor installations, distribution transformers,
and to contain voltage variation and energy losses within reasonable limits.
8. The following parameters of equipments and system designs shall be
standardised to facilitate easy replacement and reduction of inventories of
spares in stores:
(a) Capacities of power transformers,
(b) Capacities and designs of distribution transformers,
(c) 33kV/22kV/ 11kV sub-station layout.
(d) Pole mounted sub-stations,
Compendium of HPERC Regulations, March 2021 45
(e) Sizes of bus bars,
(f) Capacities and ratings of circuit breakers and instrument transformers,
(g) Earthing,
(h) Lightning arresters,
(i) Control panels,
(j) Station batteries,
(k) Fire extinguishers.
(l) Maintenance tools
(m) Safety equipments
(n) Energy meters
(o) Wires and cables
(p) Clamps and connectors
9. The planning of the Distribution System shall always keep in view the cost
effectiveness and reduction in energy losses without sacrificing the
requirements of Security Standards and Safety Standards for the Distribution
System.
10. The distribution licensee shall plan the distribution system expansion and
reinforcement keeping the following in view alongwith all other measures to
accommodate the advancement in technology prevailing at the time:-
(a) Optimising the ratio of single, two and three phase LT Lines.
(b) Optimising the ratio of single to three phase transformers;
(c ) Economic ratio of HT and LT line lengths,
(d) Use of aerial bunched conductors,
(e) Underground cables,
(f) Optimizing the number of distribution transformers and their location
at the electrical load centres,
(g) Replacement of long PVC lines with conductors/ 3 phase service line.
46 Compendium of HPERC Regulations, March 2021
Annexure-7
(see para 3.7.11)
Methodology of Load Estimation/Assessment:
1 Domestic and Commercial Loads:- The consumption in domestic and
commercial sectors shall be estimated on the basis of the number of
consumers and their specific consumption. The past growth rate in the
number of consumers in the area shall be studied. In cases where power
shortages have been experienced in the recent past, the growth rate to be
adopted shall take into consideration the appropriate demand making due
allowance in the growth rate to account for increased tempo of household
electrification envisaged in the future. The higher level of electrification
planned in the area should be kept in view. Energy consumption per
consumer shall be estimated after studying the past trends and taking into
account the anticipated improvements in the standard of living.
2 Public Lighting and Water Works: The estimates of electricity consumption
in public lighting and water works shall be based on the average consumption
per kilowatt of connected load, projected on the basis of trends, keeping in
mind the likely increase in public lighting and water supply facilities. The
number of hours of operation shall be estimated taking into account the past
trends and the power cuts if any effected in the area.
3 Agricultural Loads: The power requirement for irrigation pump sets shall be
based on the program of energisation of pump sets in the plan period,
available resources and the ultimate ground water potential. The average
capacity of pump sets shall be worked out considering the mid-year figures
for connected load and the numbers of pump sets.
4 Industrial Loads: The power requirements for industrial sector shall be
estimated under following three categories, namely:-
(a) L.T. Industries ;
(b) H.T. Industries with a demand of less than 5 MW;
(c) H.T. Industries with a demand of 5 MW and above.
(d) EHT Industries
The consumption in category (a) and (b) shall be on the basis of historical
data duly considering the developments in future. In case of category (c),
projection shall be made separately for each industrial unit on the basis of the
information furnished by the industrialists and the Department of Industries
of the State Government.
5. Non-industrial Bulk Supply: The available data regarding the consumption of
bulk supply to non-industrial consumers such as research establishments,
military engineering services, supply to power projects etc., and the probable
future developments in these areas, shall be considered for the forecast.
6. Other Loads: For other loads, the projections shall be based on the best
judgement.
Compendium of HPERC Regulations, March 2021 47
Annexure- 8
(See para 4.1.2(c) )
SITE RESPONSIBILITY SCHEDULE
Name of Sub-station/Location
Site Owner
Name of co-ordination officer of site
Telephone No.
Fax No.:
Item of Plant/
Apparatus
Plant
Owner
Safety
Responsibility
Control
Responsibility
Operation
Responsibility
Maintenance
Responsibility
Remarks
kV Switchyard
All equipment
including bus-
bars
Feeders
Generating
Units
Other (to be
specified)
Signatures
Plant Owner
Safety Responsibility
Officer
Control Responsibility
Officer
Operation
Responsibility Officer
Maintenance
Responsibility Officer
48 Compendium of HPERC Regulations, March 2021
Annexure-9
(See para 5.4.3.(3) )
ESSENTIAL LOADS AND PRIORITY OF RESTORATION
Priority Type of Load Name of the Sub-station
feeding such loads
1. Hospitals, Water Works,
2. Defense Establishments
3. Radio, Television Stations and telecommunication
Exchanges/Stations
4. Air Port
5. Important cities
6. Police Stations
7. Fire Stations
8. Process Industries and Mining
Annexure –10
(See para 8.4)
OPERATIONAL EVENT REPORTING
Name of the reporting Organization
Date and Time of reporting the /event incident
1 Date and time of incident
2 Location of incident (Name of Sub-station/Line etc.)
3 Description of incident
4 System parameters before the incident (voltage, frequency, flows,
generation, etc.)
5 Failure of protection at EHV GSS if any and relay indications.
6 Damage to equipment
7 Supplies interrupted and duration, if applicable
8 Amount of generation lost, if applicable
9 Possibility of alternate supply arrangement
10 Estimate of time to return service
11 Cause of incident
12 Any other relevant information and remedial action taken
13 Recommendations for future improvement/repeat incident
Compendium of HPERC Regulations, March 2021 49
Annexure-11
(See para 8.5)
RULE NO. 44 A OF THE INDIAN ELECTRICITY RULES, 1956
Rule no. 44 A – Intimation of Accident
If any accident occurs in connection with the generation, transmission, supply or use
of energy in or in connection with any part of electric supply lines or other works of
any person and the accident results in or is likely to have resulted in loss of human or
animal life or in any injury to a human being or an animal, such person or any
authorized person of the distribution licensee not below the rank of Junior Engineer
or equivalent shall send to the Inspector a telegraphic report within 24 hours of the
knowledge of the occurrence of the fatal accident and a written report in a form set
out in Annexure XIII within 48 hours of the knowledge of the occurrence of the fatal
accident and all other accidents. Where practicable a telephonic message should also
be given to the Inspector immediately the accident comes to the knowledge of
authorized officer of distribution licensee or other person concerned.
The Indian Electricity Rules, 1956
Annexure- XIII
FORM FOR REPORTING ELECTRICAL ACCIDENTS (See Rule 44-A)
1 Date and Time of accident
2 Place of accident
(Village/Town, Tehsil /Thana, District and State)
3 System and voltage of supply
(Whether EHV/HV/LV line, sub-station/generating
station/consumer’s installations/service lines/other installations)
4 Designation of the Officer-in-charge (in whose jurisdiction the
accident occurred)
5 Name of owner/user of energy in whose premises the accident
occurred.
6 Details of victim(s)
(a) Human
S.No. Name Father’s
Name
Sex of
victim
Full Postal
Address
Approx.
Age
Fatal / Non-
Fatal
(b) Animal
S.No. Description of
Animals
Number(s) Name(s) of
Owner(s)
Address (es)
of owner(s)
Fatal / Non-
Fatal
7 In case the victim(s) is /are employee(s):
(a) designation of such person(s)
(b) brief description of the job undertaken, if any.
(c) Whether such person/persons was/were allowed to work on the job.
8 In case the victim(s) is/are employee(s) of a licensed contractor
(a) Did the victim(s) possess any electric workman’s permits(s),
50 Compendium of HPERC Regulations, March 2021
supervisor’s certificate of competency issued under Rule 45? If yes give
number and date of issue and the name of issuing authority.
(b) Name and designation of the person who assigned the duties of the
victim(s)
9 In case of accident in the Distribution licensee system, was the Permit
To Work (PTW) taken?
10 Describe fully the nature and extent of injuries, e.g. fatal /disablement
(permanent or temporary) of any portion of the body or burns or other
injuries.
In case of fatal accident, was the post mortem performed?
11 Detailed causes leading to the accident
(To be given in a separate sheet annexed to this form)
12 Action taken regarding first-aid, medical attendance etc. immediately
after the occurrence of the accident (give details)
13 Whether the District Magistrate and Police Station concerned have been
notified of the accident (if so, give details)
14 Steps taken to preserve the evidence in connection with accident to the
extent possible.
15 Names and designation(s) of the person(s) assisting, supervising the
person(s) killed or injured.
16 What safety equipments were given to and used by the person(s) who
met with this accident (e.g. rubber gloves, rubber mats, safety belts and
ladders etc.)?
17 Whether isolating switches and other sectionalizing devices were
employed to deaden the section for working on the same? Whether
working section was earthed at the site of work?
18 Whether the work on live lines was undertaken by authorized
person(s)?
If so, the name and the designation of such person(s) may be given.
19 Whether the artificial resuscitation treatment work on live lines was
undertaken by authorised person(s)?
If yes, how long was it continued before its abandonment?
20 Names and designations of persons present at and witnessed the
accident.
21 Any other information / remarks.
Place
Time
Date
Signature
Name
Designation
Address of the person reporting
Compendium of HPERC Regulations, March 2021 51
Annexure13
(See para 1.3)
LIST OF ABBREWATIONS
1 AAC
All Aluminum Conductor
2 AAAC All Aluminum Alloy Conductor
3 ACSR Aluminum Conductor Steel Reinforced
4 BIS The Bureau of Indian Standards
5 Board The HP State Electricity Board
6 CAIDI Customer Average Interruption Duration Index
7 CAIFI Customer Average Interruption Frequency Index
8 CBIP The Central Board of Irrigation and Power
9 CEA Central Electricity Authority
10 CEI Chief Electrical Inspector
11 CT Current Transformer
12 DCR Distribution Code Review
13 DCRP Distribution Code Review Panel
14 EHV
EHT
Extra High Voltage
Extra High Tension
15 GI Galvanized Iron
16 GSS Gas Sub-station
17 HPERC The Himachal Pradesh Electricity Regulatory Commission
18 HV/
HT
High Voltage/
High Tension
19 Hz Hertz (cycles per seconds)
20 IDMT
Inverse Definite Minimum Time
21 IEEE Institute of Electrical and Electronics Engineers
22 IEC
International Electro Technical Commission
52 Compendium of HPERC Regulations, March 2021
23 IEGC Indian Electrical Grid Code
24 IS Indian Standards
25 IP Irrigation Pump
26 kA Kilo Ampere
27 kW Kilo Watt
28 kWh Kilo Watt hour
29 kVA Kilo Volt Ampere
30 LT Low Tension
31 LV Low Voltage
32 MAIDI Momentary Average Interruption Duration Index
33 MAIFI Momentary Average Interruption Frequency Index
34 MCB Miniature Circuit Breaker
35 MVA Mega Volt Ampere
36 MW Megawatt
37 PAP Project affected person
38 PCC
Prestressed Cement Concrete
39 PT Potential transformer
40 PTW Permit to work
41 RCC Reinforced Cement Concrete
42 REC Rural Electrification Corporation
43 R&R Rehabilitation and Resettlement
44 SAIDI System Average Interruption Duration Index
45 SAIFI System Average Interruption Frequency Index
46 SCADA Supervisory Control and Data Acquisition
47 SLDC State Load Despatch Centre
48 STU State Transmission Utility
Compendium of HPERC Regulations, March 2021 53
Notifications and Orders issued
under
The HP Electricity Regulatory Commission Distribution Code, 2008
1
[The HPERC constitutes the Electricity Review Panel]
NOTIFICATION
Shimla-2, the 15
th
February, 2013
No. HPERC/392- Vol(II).—In exercise of the powers conferred under clause 2.2 of
the Himachal Pradesh Electricity Distribution Code, 2009, the Himachal Pradesh Electricity
Regulatory Commission hereby constitute the Electricity “Distribution Code Review Panel”
comprising of the following:
Sr. No. Name & Designation Representation from
1. The Director (Operation) Distribution Licensee Chairman
HPSEB Ltd. Vidyut Bhawan,
Shimla- 171004.
2. The Executive Director(TA), HPERC Convener
HPERC, Khalini, Shimla-171002.
3. The General Manager, HPPTCL, STU Member
Barowalia House, Khalini, Shimla
4. The Chief Engineer(Commercial), Distribution Licensee Member
HPSEB Ltd. Vidyut Bhawan,
Shimla- 171004.
5. The Convener, HP Small Hydro Generator Member
Power Association, B-99,
Sector-3, New Shimla-171009, H.P.
6. The Vice President and Chairman , Industrial Consumers Member
Power Committee of BBN
Industries Association,
C/O Single Window Clearing Agency
Industrial Area, Baddi-173205
7. The Chief Manager(Electrical), Open Access Consumers Member
C/O ACC Ltd., “Anandvas”, /Bulk Consumers
1st Floor Khalini, Shimla-171002
8. The Convener, Power Panel, CII, Bulk Consumers Member
Himachal Pradesh State Council,
Confederation of Indian Industry (CII)
Sector 31-A, Chandigarh-16003
1
Published in R.H.P. dated 16
th
February, 2013 at p. 6809-6810.
54 Compendium of HPERC Regulations, March 2021
9. The Superintending Engineer, Non Domestic/ Non Member
(P&I)-Unit-II Jal Bhawan Shimla-9 Commercial Consumers
10. The Superintending Engineer, Non Commercial/Non Member
Electrical Circle, HP PWD, Domestic Consumers
Kasumpati, Shimla-9
11. The President, Shimla Hotel & Commercial Consumers Member
Restaurant Association,
Hotel Shivalik Near U.S. Club Gate,
Shimla-171001.
12. The Consumer Representative Domestic Consumers Member
Arcadia,Vill. Ghat-ki-Ber,
P.O. Dharampur,
Dist. Solan(HP) PIN: 173209.
13. The Superintending Engineer, Distribution Licensee Member
HPSEBL (Operation Circle),
Kasumpati, Shimla-171009
14. The Vice President, M/S Ruchira Industrial Consumers Member
Paper Mill, Trilokpur Road,
Kala Amb Distt. Sirmour,
HP-173030
1. The Chairman of the Electricity Distribution Code Review Panel shall hold
office as such for a period of two years and its all other member shall hold office by the
virtue of positions held by them in their respective organisation until changed/replaced by
the respective organisation/ consumer group.
2. A member of the Electricity Distribution Code Review Panel, who is a Govt.
officer or an employee/officer of any Govt. instrumentality or of any Public Sector
undertaking shall draw travelling and daily allowance from his parent department or
organization.
3. A member of Electricity Distribution Code review Panel, other than those referred
to under sub-para(2) shall be paid fee of Rs.500/- per meeting and TA and DA at the rates
admissible, in the State Govt. to its grade-I officers.
By order of the Commission
Sd/-
Secretary,
(H.P. Electricity Regulatory Commission).
Previous and next
All provisions of The Himachal Pradesh Electricity Distribution Code, 2009