41. Ropes.—The employer shall ensure at a construction site of a building
or other construction work that,—
(a) no rope is used for building or other construction work unless—
(i) it is of good quality and free from patent defects; and
(ii) in the case of a wire rope, it has been tested and examined
by a competent person in the manner, specified in
Schedule II;
(b) every wire rope of lifting appliance or lifting gears, used for
building or other construction work, is inspected by a
responsible person for such use, at least once in every three
months :
Provided that after any such wire is broken in such a rope, it
shall, thereafter, be inspected at least once in every month by
the responsible person;
(c) no wire rope is used for building or other construction work, if
in any length of eight diameters of such wire, the total number
of visible broken wires exceed ten per cent of the total number
of wires in such rope, or such rope shows sign of excessive
wear, corrosion or other defects, which the person who inspects
it or the Inspector having jurisdiction, declares it as unfit for
use;
(d) eye splices and loops of ropes for the attachment of hooks,
rings and other such parts to wire ropes are made with suitable
thimble; and
(e) a thimble or loop splice made in any wire rope sling conforms
to the following standards, namely :—
(i) wire rope sling shall have at least three tucks with full
strand of rope and two tucks with one-half of the wires
cut out of each of such strand in all cases and such strands
shall be tucked against the layer of the ropes;
(ii) protruding ends of such strands in any splice of wire rope
slings shall be covered or treated so as to leave no sharp
points;
(iii) a fibre rope or a rope sling shall have at least four tucks;
tail of such tuck being whipped in a suitable manner; and
(iv) a synthetic fibre or rope sling shall have at least four tucks
with full strand followed by further tuck with one-half
Section 40 (2) (e)
31
filaments cut out of each of such strands. Any portion of
the splices containing such tucks, with reduced number of
filaments, shall be securely covered with suitable tape or
other materials :
Provided that nothing contained in this sub-clause, shall
apply, where any other form of splice, which may be shown
to be as efficient as the splice with above standards, is
used.
Previous and next
Questions people ask
Is rule 41 of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.