Form II, Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008: Form-II
Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 - Form II
Text of form II
Form-II
Form-II
[See rule 26 and 44 (b) (i) (a), Schedule-II]
CERTIFICATE OF INITIAL AND PERIODICAL TEST AND
EXAMINATION OF WINCHES, DERRICKS AND
THEIR ACCESSORY GEAR
Test Certificate No……………………. Date………………
(a) In case of construction site, name of the construction site where
lifting appliances are fitted/installed/located.
___________________________________________________________
Distinguishing
No. or mark
Description of
gear annealed
No. of the
certificate
of
test and
examination
Remarks
(to
be
signed
and
dated)
I certify that on
the date on which I
appended my signature, the
gear described in
Cols. 1 & 2, was effectually
annealed under my
supervision, that after
being so annealed, every
article was carefully
inspected and that no
defects affecting its safe
working condition were
found other than those,
shown in Col. 7
Date and
signature
with seal
Date and
signature
with seal
Date and
signature
with seal
1 2 3 4 5 6 7
Situation and Description
of lifting appliances and
gear with distinguishing
number of marks (if any)
which have been tested,
thoroughly examined
Angle to the
horizontal of
derrick boom
at which test
load applied
Test load
applied
Safe working load at the
angle shown in column
(2)
1 2 3 4
Degrees (Tonnes) (Tonnes)
156
Name and address of public service,
association, company or firm or
testing establishment making the test
and examination
5 6
I certify that on the ______________ day of 20________ the lifting
appliances shown in column (1) together with its necessary gear was tested in
the manner set forth overleaf in my presence; that a careful examination of the
said lifting appliances after the test showed that it had withstood the test load
without injury or permanent deformation; and that the safe working load of the
said lifting appliance and accessory gear is, as shown in column (4).
Signature and Seal of the Competent Person
Registration/Authority number
of the Competent Person.
Previous and next
Questions people ask
Is form II of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.