FORM - I
FORM - I
[See rule 44(b)]
REGISTER OF PERIODICAL TEST - EXAMINATION OF LIFTING
APPLIANCE AND GEARS ETC.
PART-I
Initial and periodical load test of lifting appliances and their annual
thorough examination.
“Thorough examination” means a visual examination, supplemented, if
necessary, by other means such as a hammer test, carried out as
carefully as the conditions permit, in order to arrive at a reliable
conclusion as to the safety of the parts examined and if necessary, for
152
such examination parts of the lifting appliances and gear shall
be dismantled.
(A)
Initial and periodical load tests of lifting appliance
Situation and No. of I certify that on the date on Remarks (to
description of certificate of which I have appended my be signed
lifting appliances test and signature the lifting appliance and dated)
tested with examination of shown in column (1), was
distinguishing competent tested and no defects,
number of marks, person affecting its safe working
if any conditions, were found other
than those, shown in column (5)
Date and Date and
Signature with Signature
seal with seal
1 2 3 4 5
(B)
Annual thorough examination
I certify that on the date on which I have appended my Remarks to be
signature, the lifting appliance shown in column (1) signed and dated
was thoroughly examined and no defects affecting its
safe working conditions were found, other than those,
shown in column (12)
Date and
signature
with seal
6 7 8 9 10 11 12
1.
2.
Note.— If all the lifting appliances are thoroughly examined on the same date it will be
sufficient to enter in column (1) “All lifting appliances”. If not, the parts,
which have been thoroughly examined on the dates, must be clearly indicated.
Date and
signature
with seal
Date and
signature
with seal
Date and
signature
with seal
Date and
signature
with seal
Date and
signature
with seal
Remarks to
be signed
and dated
153
PART II
Initial and periodical load test of loose gears and annual thorough
examination
List of loose gear :
The following classes of loose gears, namely :—
1. Chains made of malleable cast iron;
2. Plate link chains;
3. Chains, rings, hooks, shackles and swivels made of steel;
4. Pitched chains;
5. Rings, hooks, shackles and swivels permanently attached to pitched
chains, pulley blocks, container spreaders, trays, slings, baskets,
etc. and any other similar gear;
6. Hooks and swivels having screw-threaded parts or ball bearings or
other case hardened part; and
7. Bordeaux connections.
Initial Test and periodical load test of loose gears
1 2 3 4 5
1.
2.
3.
4.
5.
Distinguishing
No. or marks
Description of
loose gear tested
and examined
No. of certificates of
test and examination
of competent person
I certify that on the date on
which I have appended my
signature, the loose gears,
shown in columns (1) and (2),
were tested and no defects
affecting the safe working
condition, were found other
than those, shown in column (6)
Date and
signature
with seal
Date and
signature
with seal
154
Annual thorough examination of loose gears
Remarks (to be I certify that on the date on which I have appended my
signed and dated) signature the loose gear shown in columns (1) and (2)
were thoroughly examined by me and no defects affecting
their safe working condition were found other than those,
shown in column (10)
6 7 8 9 10
1.
2.
3.
4.
5.
PART III
Annealing of Chains, Rings, Hocks, Shackles and Swivels (other than
those exempted )
(See PART II)
12.5 mm and smaller chains, If used with lifting appliance driven by power,
rings, hooks, shackles and must be annealed once at least in every six months.
swivels in general use. Other If used solely with lifting appliance worked by
chains, rings, hooks, shackles hand must be annealed once at least in every
and swivels in general use. twelve months.
If used with lifting appliance driven by power,
must be annealed once at least in twelve months.
If used solely with lifting appliance worked by
hand, must be annealed once at least in every
two years.
Note.— It is recommended though not required by rules that annealing should be
carried out in a suitably constructed furnace heated to temperature
between 1100 degree and 1300 degree Fahrenheit or 600 degree and 700
degree Centigrade, for a period between 30 and 60 minutes.
Date and
signature
with seal
Date and
signature
with seal
Date and
signature
with seal
Date and
signature
with seal
155
Previous and next
Questions people ask
Is form I of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 still in force?
No repeal of Punjab Building and Other Construction Workers ( (Regulation of Employment and Conditions of Service) Rules, 2008.) Rules, 2008 is recorded.