Regulation 4, The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006: 2[Restriction of Cross Subsidy Surcharge
The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 - Regulation 4
Text of regulation 4
2[Restriction of Cross Subsidy Surcharge
4. 2[Restriction of Cross Subsidy Surcharge.— The Commission may further
restrict the cross subsidy surcharge computed in accordance with Regulation 3, in a
1
Sub. for sub-regulation 2 of regulation 3 vide Not. No. HPERC/391.dated 10
th
November, 2016
published in R.H.P. dated 16
th
November, 2016 at p. 5564-5565. Before substitution sub-regulation (2) read
as under:
-“(2) The cross subsidy surcharge shall be determined by the Commission on a methodology and
surcharge formula specified in the National Tariff Policy, which is given as under:-
S = T – [C (1+L/100) +D]
Explanation.- For the purpose of this regulation. -
(a) “S” is the Surcharge
(b) “T” means Tariff payable by the relevant category of consumers
(c) “C” is the Weighted average cost of power purchase of top 5% at the margin excluding liquid
fuel based generation and renewable power
(d) “D” is the Wheeling Charge
(e) “L” is the system losses for the applicable voltage level, expressed as a percentage”
2 Subs. vide Not. No. HPERC/391dated 10
th
November, 2016 published in the R.H.P. dated 16
th
November, 2016 at p. 5564-5565 and before its substitution it stood as under:-
Compendium of HPERC Regulations, March 2021 3
manner as it may consider appropriate, from time to time for respective categories of
consumers and also for different time of a day.]
Previous and next
Questions people ask
Is regulation 4 of the Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 is recorded.