LawGrids logoLAWGRIDS.ORG

Regulation 3, The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006: Cross subsidy surcharge

The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 - Regulation 3

Text of regulation 3

Cross subsidy surcharge

3. Cross subsidy surcharge.- (1) The cross subsidy surcharge as provided under subsection (2) of section 42 of the Act shall be payable by the consumers availing Open Access: Provided that no cross subsidy surcharge shall be payable by a person who has established a captive generating plant for carrying the electricity to the destination of his own use: Provided further that no cross subsidy surcharge on the electricity being— 1 Published in the R H.P. (Extra) dated 7 th September, 2006 at p. 4127-4131. 2 Compendium of HPERC Regulations, March 2021 (a) sold by the generating companies, with the consent of the competent Government under clause (c) of sub-section (1) of section 43 A of the Electricity (Supply) Act,1948 (54 of 1948); or (b) supplied by the distribution licensee, on the authorization by the State Government under section 27 of the Indian Electricity Act, 1910 (9 of 1910); shall be payable during the period such consent or authorization remains in force. (2) 1 [The cross subsidy surcharge shall be determined by the Commission on the methodology and surcharge formula, specified in the revised Tariff Policy, 2016, which is given as under:— Surcharge formula: S= T-[C/(1-L/100)+D+R] (a) “S” is the surcharge; (b) “T” is the tariff payable by the relevant category of consumers, including reflecting the Renewable Purchase Obligation; (c) “C” is the per unit weighted average cost of power purchase by the Licensee, including meeting the Renewable Purchase Obligation; (d) “D” is the aggregate of transmission, distribution and wheeling charges applicable to the relevant voltage level; (e) “L” is the aggregate of transmission, distribution and commercial losses, expressed as a percentage applicable to the relevant voltage level; (f) “R” is the per unit cost of carrying regulatory assets. Provided that the surcharge shall not exceed 20% of the tariff applicable to the respective category of the consumers, seeking open access. Provided further that the Commission, while keeping the overall objectives of the Electricity Act in view, may review and vary the formula, taking into consideration the different circumstances related to power supply, prevailing in the area of Distribution Licensee.]

Previous and next

All provisions of The Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006

Questions people ask

Is regulation 3 of the Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 still in force?

No repeal of the Himachal Pradesh Electricity Regulatory Commission (Cross Subsidy Surcharge, Additional Surcharge and Phasing of Cross Subsidy) Regulations, 2006 is recorded.