Regulation 9, The Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004: Investments
The Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 - Regulation 9
Text of regulation 9
Investments
9. Investments.- (1) The distribution licensee shall duly comply with the regulations,
guidelines, directions and orders the Commission may issue from time to time in regard to
the investments to be made in the distribution business.
(2) The distribution licensee shall make the investments in a prudent manner being
guided by the duty to build, maintain and operate an efficient, co-ordinated and economical
distribution system in the State.
(3) The distribution licensee shall submit to the Commission investment plans as a
part of the business plan under sub-regulation (8) of regulation 8 giving details of
investment schemes to be undertaken during the concerned period for the approval of the
Commission. The distribution licensee shall demonstrate to the satisfaction of the
Commission that -
(a) there is a need for such investments in the distribution system contained in
the investment plan;
(b) the distribution licensee has examined the economic, technical, system and
environmental aspects of all viable alternatives to the proposal for investing
in or acquiring new distribution system assets to meet such need.
10 Compendium of HPERC Regulations, March 2021
(4) The distribution licensee shall intimate, by the end of the first quarter of each
financial year, -
(a) the annual investment plan with details of investment schemes to be carried
out during the financial year; and
(b) the progress made in implementing the annual investment plan of the
previous financial year with the comparison of actual implementation vis-à-
vis the plan as approved by the Commission for the concerned period.
(5) The distribution licensee shall not undertake schemes involving major
investments, not covered under the investment plan approved by the Commission under
sub-regulation (3) without the prior approval of the Commission, and for such approval the
distribution licensee shall demonstrate to the satisfaction of the Commission the factors
mentioned in sub-regulation (3).
(6) The distribution licensee shall invite and finalise tenders for procurement of
equipment, material and/or services relating to major investment, in accordance with a
transparent tendering procedure as may be directed by the Commission. The distribution
licensee shall, in consultation with the Commission, -
(i) ensure that material management policy and practices including calendar of
various actions, approvals, tendering, purchase order, delivery schedule and
payments etc. are streamlined so as to provide necessary inputs of right quality
at the right time to facilitate faithful implementation and compliance of the
approved standards and benchmarks.
(ii) lay down bench-mark prices and conclude rate contracts for decentralised
purchases so as to bring about financial discipline and inventory control for
achieving optimal financial ratios in respect of such decentralised purchases.
(7) For the purposes of this regulation, the term "major investment" means any
planned investment in or acquisition of distribution facilities, the cost of which, when
aggregated with all other investments or acquisitions (if any) forming part of the same
overall transaction, equals or exceeds an amount contained in the special conditions
applicable to the distribution licensee or otherwise decided by the Commission from time
to time by a general or special order.
(8) The distribution licensee shall be entitled to make investment in the distribution
business other than those covered under sub-regulations (3) and (5) but for the purposes of
considering such investment while determining the tariff, the distribution licensee shall
satisfy the Commission that the investment was required for the distribution business and
such investment was made in an efficient, co-ordinated and economical manner.
(9) The distribution licensee shall submit to the Commission alongwith the
“Expected Revenue Calculations” filed under section 62 of the Act, the highlights of the
annual investment plan consisting of the schemes approved by the Commission, schemes
submitted before the Commission for approval and all schemes not requiring prior
approval of the Commission planned for the ensuing financial year and shall make
investment in the said financial year in accordance with the said investment plan:
Compendium of HPERC Regulations, March 2021 11
Provided that if any unforeseen contingencies required reallocation of funds within
the schemes listed in the annual investment plan, the distribution licensee may do so to the
extent such reallocation in respect of individual projects does not exceed an amount
decided by the Commission in the special conditions applicable to the distribution licensee
or otherwise by a general or special order. The distribution licensee shall give due
intimation of such reallocation to the Commission within 7 days of making the investment:
Provided also that if on account of unforeseen circumstances the distribution
licensee is required to make investment in a scheme, which does not find a place in the
annual investment plan, the distribution licensee may do so if the same is not a major
investment and subject to the conditions contained in sub-regulation (8).
(10) The distribution licensee shall submit to the Commission the relevant load
flow studies and details of investment requirement to achieve the planned reduction in
losses (both technical and non technical).
Previous and next
Questions people ask
Is regulation 9 of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 is recorded.