Provision of information to the commission
8. Provision of information to the commission. - (1) The distribution licensee shall
furnish to the Commission without delay such information, documents and details related
to the licensed business or any other business of the distribution licensee, as the
Commission may require from time to time for its own purposes or for the purposes of the
Government of India, the State Government, the Central Commission, the Central
Electricity Authority, the State Transmission Utility and the State Load Despatch Centre.
(2) The distribution licensee shall duly maintain the information as the Commission
may direct under section 128 of the Act.
(3) The distribution licensee shall notify the Commission as soon as possible the
occurrence of any major incident affecting any part of its distribution system and, in any
event, by not later than two months from the date of such occurrence, -
(a) submit a report to the Commission giving full details of the facts within the
knowledge of the distribution licensee regarding the incident and its cause;
(b) in the event the report under clause (a) is likely to take more than two
months from the date of such incident, the distribution licensee shall, within
one month from such date of the incident, submit a preliminary report with
such details which the distribution licensee can reasonably furnish and state
reasons as to why the distribution licensee requires more than two months
for giving full report of such incident; and
(c) give copies of the report to all parties concerned with the major incident
and to such other persons as the Commission may direct.
Compendium of HPERC Regulations, March 2021 9
(4) The Commission at its discretion may require the submission of a report on the
major incident to be prepared by an independent person at the expense of the distribution
licensee.
(5) The distribution licensee shall also undertake such studies as the Commission
may direct from time to time for the improvement of its distribution system and any other
matter concerning the distribution business that the Commission considers necessary to
avoid the occurrence of any such major incident.
(6) The distribution licensee shall duly inform the Commission about any incident
restricting it from meeting obligations under the licence granted including any act of
omission or commission by others and steps taken by the distribution licensee to mitigate
the effect of such incident.
(7) The Commission may at any time require the distribution licensee to comply
with the provisions of sub-regulations (3) to (6) as to incidents which the Commission may
specifically direct and the distribution licensee shall be obliged to comply with the same
notwithstanding that such incidents are not major incidents; provided that the time limits
specified in sub-regulation (3) shall commence from the date on which the Commission
notifies the distribution licensee of such requirement.
(8) The distribution licensee shall submit a business plan within three months of the
distribution licence coming in force for such period as the Commission may direct and
shall update such plan annually. The business plan shall contain year-wise load growth,
year-wise distribution loss reduction proposal along with specific action plan, metering
plan for metering interface points, investment plan as detailed in regulation 9, treatment of
previous losses, debt restructuring plan, cost reduction plan, projected profit and loss
account, projected balance sheets, projected cash flow statements and projected important
financial parameters.
(9) The Commission may require the distribution licensee to intimate by the end of
the first quarter of each financial year the progress made in implementing the business plan
of the previous financial year with the comparison of actual implementation vis-à-vis the
plan as approved by the Commission.
Previous and next
Questions people ask
Is regulation 8 of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (General Conditions of Distribution Licence) Regulations, 2004 is recorded.