29. (Compliance of directions): --- (1) The Regional Load Despatch
Centre may give such directions and exercise such supervision and control as
may be required for ensuring stability of grid operations and for achieving the
maximum economy and efficiency in the operation of the power system in the
region under its control.
- 28 -
The Electricity Act, 2003
________________________________________________________________________
(2) Every licensee, generating company, generating station, sub-station and
any other person connected with the operation of the power system shall comply
with the directions issued by the Regional Load Despatch Centres under sub-
section (1).
(3) All directions issued by the Regional Load Despatch Centres to any
transmission licensee of State transmission lines or any other licensee of the
State or generating company (other than those connected to inter State
transmission system) or sub-station in the State shall be issued through the State
Load Despatch Centre and the State Load Despatch Centres shall ensure that
such directions are duly complied with the licensee or generating company or
sub-station.
(4) The Regional Power Committee in the region may, from time to time,
agree on matters concerning the stability and smooth operation of the integrated
grid and economy and efficiency in the operation of the power system in that
region.
(5) If any dispute arises with reference to the quality of electricity or safe,
secure and integrated operation of the regional grid or in relation to any
direction given under sub-section (1), it shall be referred to the Central
Commission for decision :
Provided that pending the decision of the Central Commission, the
directions of the Regional Load Despatch Centre shall be complied with by the
State Load Despatch Centre or the licensee or the generating company, as the
case may be.
(6) If any licensee, generating company or any other person fails to comply
with the directions issued under sub-section (2) or sub-section (3), he shall be
liable to a penalty not exceeding rupees fifteen lacs.
Intra-State transmission