Section 29, THE ODISHA ELECTRICITY REFORM ACT, 1995: Final orders
THE ODISHA ELECTRICITY REFORM ACT, 1995 (2 of 1996) - Section 29
Text of section 29
Final orders
29. Final orders. - (1) If the Commission proposes to make a final order
or to declare an interim order to be a final order, the Commission shall give
notice;
(a) stating that it proposes to make the final order or to declare the
interim order to be a final order;
(b) setting out the information referred to in Clause (b) of Sub-section
(3) of Section 28 in respect of the proposed final order; and
(c) specifying the period, not being less than sixty days from the
date of publication of the notice, within which representations or
objections to the proposed order may be made.
(2) The Commission shall consider any representations or objections that
26
are duly made and not withdrawn and shall publish of such representations or
objections specifying a period, not being less than thirty days from the date of
publication of the notice within further representations or objections may be made.
(3) A notice under Sub-section (1) or (2) shall be given -
(a) by publishing the notice in such manner as the Commission
considers appropriate for the purpose of bringing the matters to
which the notice relates to the attention of persons likely to be
affected by them; and
(b) by serving a copy of the notice, and a copy of the proposed final
order on the licensee to whom the order relates.
(4) The Commission shall not modify the proposed final order as a result
of any representations or objections received following publication of the notice
referred to in Sub-section (1), except.
(a) with the consent to the modification of the licensee to whom the
proposed final order relates; or
(b) after complying with the requirements of Sub-section (5).
(5) The Commission shall, for the purpose of Sub-section (4).
(a) serve on the licensee to whom the proposed final order relates
such notice as appears to the Commission to be requisite, of its
proposal to modify the proposed final order, together with details
of such modifications.
(b) specify in that notice the period not being less than thirty days
from the date of the service of the notice, within the representations
or objections to the proposed modifications can be made; and
(c) consider any representations or objections which are duly made
and not withdrawn within ten days of the receipt thereof.
(6) The provisions of Clauses (a) and (b) of Sub-section (6) of Section 28
shall apply to final orders.
(7) As soon as practicable after making a final order, the Commission
shall with respect to the final order, follow the procedure set out in Clauses (a)
and (b) of Sub-section (7) of Section 28.
(8) The Commission may revoke a final order at any time, but before revoking
a final order the Commission shall give notice.
(a) stating that it proposes to revoke the order and setting out its
effect; and
(b) specifying the period not being less than thirty days from the
date of publication of the notice within which representations or
objections to the proposed revocation may be made, and shall
consider any representations or objections which are duly made
and not withdrawn within ten days of the receipt thereof.
(9) If, after giving a notice under Sub-section (8) above, the Commission
27
decides not to revoke the final order to which the notice relates, it shall give
notice of its decision to the concerned persons.
(10) The procedure provided in Clauses (a) and (b) of Sub-section (7) of
Section 28 shall be followed for giving a notice under Sub-section (8) or (9).