28. Interim Orders. - (1) Where the Commission is satisfied that a licensee
is contravening, or is likely to contravene any relevant conditions or requirement
of its licence, it shall be final order under Section 29 and, if it thinks it appropriate
in accordance with Sub-section (2) by interim order under this Section issue
such directions as it deems proper for securing compliance.
(2) In determining whether it is appropriate that an interim order be made,
the Commission shall have regard in particular to-
(a) the extent to which the contravention or likely contravention by
the licensee will affect the achievement of the objects and
purposes of this Act;
(b) the extent to which any person is likely to sustain loss or damage
in consequence of anything is likely to be done or omitted to be
done in contravention of the relevant condition or requirement,
before a final order can be made; and
(c) the extent to which there is any other available remedy in respect
of the alleged contravention of a relevant condition or requirement.
(3) If the Commission proposes to make an interim order, it shall give
notice to the licensee.
(a) stating that it proposes to make the order;
(b) setting out;
(i) the relevant conditions or requirement with which the proposed
order is intended to secure compliance;
(ii) the acts or omissions which, in its opinion, constitute
contravention of that condition or requirement;
(iii) the other facts which in its opinion, justify the making of the
proposed order; and
(iv) the effects of the proposed order;
(c) specifying the period not being less than five days from the date
of notice within which the licensee may make representations or
objections to the proposed order.
(4) Subject to Sub-section (5), having considered any representations or
25
objections from the licensee pursuant to Clause (c) of Sub-section (3), the
Commission may make an interim order at any time after expiry of the period
referred to in Clause (c) of the said Sub-section, if -
(a) the Commission has reason to believe that the licensee to whom
the order relates has contravened or is contravening or is likely
to contravene any relevant condition or requirement; and
(b) the provisions made by the order, are requisite tor the purpose of
securing compliance with that condition or requirement.
(5) The Commission may not make an interim order if it is satisfied that
the licensee has agreed to take and is taking all such steps as the Commission
considers that the licensee should take to secure compliance with the condition
or requirement in question.
(6) An interim order -
(a) shall require the licensee to whom it relates to do, or to abstain
from doing such things as are specified in the order;
(b) shall take effect from such time as is specified in the order; and
(c) may be revoked, modified or rescinded at any time by the
Commission, but in any event shall cease to have effect at the
end of such period as in stated in the order, unless the
Commission is at that time following the procedure set out in
Section 29 to declare the interim order to be a final order.
(7) As soon as practicable, after making an interim order, the Commissioner
shall -
(a) serve a copy of the order on the licensee to whom the order
relates.
(b) publish the order in such manner as it considers-appropriate for
the purpose of bringing it to the attention of persons likely to be
affected by it; and
(c) commence proceedings to declare the interim orders to be a
final order in accordance with Section 29;