LawGrids logoLAWGRIDS.ORG

Regulation 41, Indian Boiler Regulations, 1950: Additional test before rejection

Indian Boiler Regulations, 1950 - Regulation 41

Text of regulation 41

Additional test before rejection

41. Additional test before rejection.—(a) Should a tube seleoted for testing purposes show definile signs of failure in any one or moro of the testa speoified in Regulations 38, 39 and 40, two further tests of the same kind may be made at the option of the manufacturer from two additional tubes selooted from tho same batch. (b) If the ropeat tests tire satisfactory the tubes shall be accepted provided that in all other respects they fulfil the conditions of this Standard. Should either of tho tubes fail in any test, the biitch of tubes represented may be re-heat-treated in accordance with. Rogulation 36(b) and then retested in accordance with Regulations 38,31) and 40 but employing twico the number of tost pieces. If these seoond repeat tests are satisfactory, the tubes shall be accepted provided that in all other respects they fulfil the conditions of this Standard; but if definite defects are again shown, the batch of tubes which tho test pieces represent shall be rejocted.

Previous and next

All provisions of Indian Boiler Regulations, 1950

Questions people ask

Is regulation 41 of Indian Boiler Regulations, 1950 still in force?

No repeal of Indian Boiler Regulations, 1950 is recorded.