Rule 19, Bangalore Metro Railway (General) Rules, 2011: Working of Signals and points
Bangalore Metro Railway (General) Rules, 2011 - Rule 19
Text of rule 19
Working of Signals and points
19. Working of Signals and points.- (1) Control of signals and points shall be from a route
setting panel or work-station, and complete routes, points and signals, will be cleared
by a single operation under normal conditions.
(2) Any failure of vital equipments shall cause the signaling system to display a more
restrictive indication.
(3) Any route which has been cleared for a train shall not be cancelled until it is cleared by
the train entering the route except,-
(a) in case of emergency; and
(b) in case where operating conditions require that an alternate route be cleared
and in this case, the alternative route shall not be made available for clearance
until the pre-set time, defined under special instructions, has elapsed from the
time the original route was blocked.
(4) In conditions of failure of route setting controls, points can be set individually from
Operations Control Centre, Station Control Room or locally as may be necessary.
16 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II-SEC. 3(i)]
Previous and next
All provisions of Bangalore Metro Railway (General) Rules, 2011
Questions people ask
Is rule 19 of Bangalore Metro Railway (General) Rules, 2011 still in force?
No repeal of Bangalore Metro Railway (General) Rules, 2011 is recorded.