Regulation 12, Central Electricity Authority (Grid Standards) Regulations, 2010: Reporting of events affecting grid operation
Central Electricity Authority (Grid Standards) Regulations, 2010 - Regulation 12
Text of regulation 12
Reporting of events affecting grid operation
12. Reporting of events affecting grid operation.- (1) Any tripping of
generating unit or transmission element, along with relay indications, shall be
promptly reported by the respective Entity to the Appropriate Load Despatch Centre
in the reporting formats as devised by the Appropriate Load Despatch Centre.
(2) The Appropriate Load Despatch Centre shall promptly intimate the event to the
Regional Load Despatch Centres and State Load Despatch Centres of the affected
regions and States respectively which shall, in turn, take steps to disseminate this
information further to all concerned.
Previous and next
← Regulation 11Categorisation of grid incidents and grid disturbance based on severity of trippingsRegulation 13 →Reporting of grid disturbance
All provisions of Central Electricity Authority (Grid Standards) Regulations, 2010
Questions people ask
Is regulation 12 of Central Electricity Authority (Grid Standards) Regulations, 2010 still in force?
No repeal of Central Electricity Authority (Grid Standards) Regulations, 2010 is recorded.