Regulation 4, Central Electricity Authority (Grid Standards) Regulations, 2010: Operation Planning
Central Electricity Authority (Grid Standards) Regulations, 2010 - Regulation 4
Text of regulation 4
Operation Planning
4. Operation Planning.- The Regional Power Committee shall periodically
review the performance of the grid for the past period and plan stable operation of
the grid for the future, considering various parameters and occurrences such as
frequency profile, voltage profile, line loading, grid incident, grid disturbance,
performance of system protection schemes and protection coordination.
Page 8 of 19
Previous and next
← Regulation 3Standards for Operation and Maintenance of Transmission LinesRegulation 5 →Maintenance Planning
All provisions of Central Electricity Authority (Grid Standards) Regulations, 2010
Questions people ask
Is regulation 4 of Central Electricity Authority (Grid Standards) Regulations, 2010 still in force?
No repeal of Central Electricity Authority (Grid Standards) Regulations, 2010 is recorded.