Regulation 3, Central Electricity Authority (Grid Standards) Regulations, 2010: Standards for Operation and Maintenance of Transmission Lines
Central Electricity Authority (Grid Standards) Regulations, 2010 - Regulation 3
Text of regulation 3
Standards for Operation and Maintenance of Transmission Lines
3. Standards for Operation and Maintenance of Transmission Lines.- (1) All
Entities, Appropriate Load Despatch Centres and Regional Power Committees, for
the purpose of maintaining the Grid Standards for operation and maintenance of
transmission lines, shall,-
(a) make all efforts to operate at a frequency close to 50 Hz and shall not allow it
to go beyond the range 49.2 to 50.3 Hz or a narrower frequency band specified in
the Grid Code, except during the transient period following tripping.
(b) maintain the steady state voltage within the limits specified below in Table 1:
Table 1
S.
No.
Nominal System Voltage
(kV rms)
Maximum
(kV rms)
Minimum
(kV rms)
1 765 800 728
2 400 420 380
3 220 245 198
4 132 145 122
5 110 121 99
6 66 72 60
7 33 36 30
Page 4 of 19
( c) ensure that the temporary over voltage due to sudden load rejection
remains within the limits specified in Table 2,-
Table 2
S. No. Nominal System Voltage
(kV rms)
Phase to Neutral Voltage
(kV peak)
1 765 914
2 400 514
3 220 283
4 132 170
Provided that for the voltage level below 132 kV, the temporary over
voltage limits as given in Table 2 shall be decided by the State Commission in
the respective State Grid Code.
(d) ensure that the maximum permissible values of voltage unbalance shall be as
specified in Table 3 below:-
Table 3
S.No. Nominal System Voltage
(kV rms)
Voltage Unbalance
(%)
1 765 and 400 1.5%
2 220 2%
3 33 to132 3%
Provided that Bulk consumers shall avoid unbalanced load during
operation:
Provided further that the distribution licensees shall ensure that their
loads are not unbalanced.
Page 5 of 19
(e) provide standard protection systems having the reliability, selectivity, speed and
sensitivity to isolate the faulty equipment and protect all components from any
type of faults, within the specified fault clearance time and shall provide
protection coordination as specified by the Regional Power Committee.
Explanation.- For the purpose of this regulation “fault clearance time” means the
maximum fault clearance times are as specified in the Table 4 below,-
Table 4
S.No. Nominal System
Voltage
(kV rms)
Maximum Time
( in milliseconds)
1 765 and 400 100
2 220 and 132 160
Provided that in the event of non clearance of the fault by a circuit
breaker within the time limit specified in Table 4, the breaker fail protection
shall initiate tripping of all other breakers in the concerned bus-section to clear
the fault in the next 200 milliseconds.
(f) operate the system in a such a way that the Grid System is capable of
withstanding one of the following contingencies without experiencing loss of
stability:-
(1) outage of one single largest generating unit of the system or
(2) outage of a 132 kV Double circuit line or
(3) outage of a 220 kV Double circuit line or
(4) outage of a 400 kV Single circuit line or
(5) outage of a 400 kV Single circuit line with series compensation or
(6) outage of 765 kV Single circuit line without series compensation or
(7) outage of one pole of HVDC Bipolar line or
(8) outage of an Interconnecting Transformer
Page 6 of 19
(g) operate the system in a such a way that under any one of the following
contingencies, the system remains stable and sustains integrity so that no
generator loses synchronism and no part gets isolated from the rest of the
system:
(1) tripping of a single largest generating unit; or
(2) transient ground fault in one phase of a 765 kV Single Circuit Line
close to the bus; or
(3) a permanent single phase to ground fault in 400 kV single circuit line
followed by 3 pole opening of the faulted line; or
(4) a permanent fault in one circuit of a 400 kV Double Circuit Line when
both circuits were in service in the pre-contingency period; or
(5) a transient single phase to ground fault in one circuit of a 400 kV
Double Circuit Line when the second circuit is already under outage;
or
(6) a three-phase permanent fault in a 220 kV or 132 kV line; or
(7) a permanent fault in one pole of HVDC bipolar in a HVDC Converter
Station.
(h) observe the following permissible limits of voltage fluctuation :-
(i) the permissible limit of voltage fluctuation for step changes which may
occur repetitively is 1.5 percent:
(ii) for occasional fluctuations other than step changes the maximum
permissible limit is 3 percent:
Provided that the standard on voltage fluctuations shall come into
force concurrently with clause 4 of Part IV of the Schedule to the Central
Electricity Authority (Technical Standards for Connectivity to the Grid)
Regulations, 2007.
(2) The transmission licensee shall ensure that the voltage wave-form quality is
maintained at all points in the Grid by observing the limits given in Table 5
below,-
Page 7 of 19
Table 5
S.No. System Voltage
(kV rms)
Total Harmonic
Distortion
(%)
Individual
Harmonic of any
particular
Frequency
(%)
1 765 1.5 1.0
2 400 2.0 1.5
3 220 2.5 2.0
4 33 to 132 5.0 3.0
Provided that the standard on Harmonic Distortion shall come into force
concurrently with clause 3 of Part IV of the Schedule to the Central Electricity
Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007.
Explanation : For the purpose of this regulation, Total Harmonic Distortion
(VTHD) expressed as percentage, shall be calculated as under,-
100
40
2
2
1
2
X
V
V
V
n
n
n
THD ∑
=
=
=
‘1’ refers to fundamental frequency (50 Hz)
‘n’ refers to the harmonic of nth order (corresponding frequency is 50 x
n Hz)
Previous and next
All provisions of Central Electricity Authority (Grid Standards) Regulations, 2010
Questions people ask
Is regulation 3 of Central Electricity Authority (Grid Standards) Regulations, 2010 still in force?
No repeal of Central Electricity Authority (Grid Standards) Regulations, 2010 is recorded.