Rule 102, The Explosives Rules, 2008: No objection certificate before construction
The Explosives Rules, 2008 - Rule 102
Text of rule 102
No objection certificate before construction
102. No objection certificate before construction.—
(1) After approval under rule 101, the person desiring to
obtain a licence for manufacture, possession for sale or
use of explosives shall obtain a no objection certificate
from the District Magistrate or Director General of Mines
Safety, as the case may be, before commencing
construction of the premises.
(2) Certificate referred to in sub-rule (1) shall not be
required if—
(a) the premises proposed to be licensed is within
the factory licensed under these rules for
186 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
manufacture of explosives and the required
safety distances are under the control of
applicant;
(b) the premises for which the new licence is
required is situated within the same survey
number, in which the applicant has an existing
premises and a valid licence for the same.
(c) any other amendment in the existing licence is
carried out which does not warrant any fresh
enquiry for grant of no objection certificate.