Rule 101, The Explosives Rules, 2008: Prior approval before construction
The Explosives Rules, 2008 - Rule 101
Text of rule 101
Prior approval before construction
101. Prior approval before construction .—(1) A
person desiring to obtain a licence for manufacture,
possession for sale, use, transport of explosives, under
these rules, shall obtain prior approval from the authority
empowered to grant such licence, by submitting documents
mentioned in rule 113.
(2) The District Magistrate while granting the prior
approval, shall return to the applicant one set of approval
together with plans and Form DE-2, if required, showing
distances required to be kept clear in and around the
premises.
(3) The Chief Controller or Controller while granting
the prior approval, shall return to the applicant one set of
approval together with plans and a Form DE-2 if required,
showing distances required to be kept clear in and around
the premises and an additional set of the said documents
to enable the applicant to submit the same to the authority
authorised to issue no objection certificate under rules 102
and 103.
(4) Prior approval under sub-rule (1) shall not be
necessary in case of licences for manufacture of Adivertus,
transport of explosives in tractor compressor, possession
in shops, public display of fireworks and import and export
of explosives.
Previous and next
Questions people ask
Is rule 101 of the Explosives Rules, 2008 still in force?
No repeal of the Explosives Rules, 2008 is recorded.