89. Completion of acquisition not compulsory, but compensation to be awarded when not
completed.
(1) The Government shall be at liberty to withdraw from the acquisition of any land of which possession
has not been taken.
(2) Whenever the Government withdraws from any such acquisition, the Collector shall determine the
amount of compensation due for the damage suffered by the owner in consequence of the notice or
of any proceedings thereunder, and shall pay such amount to the person interested, together with all
costs reasonably incurred by him in the prosecution of the proceedings under this Act relating to the
said land.
Previous and next
All sections of THE MIZORAM (LAND ACQUISITION, REHABILITATION AND RESETTLEMENT) ACT, 2016.
Questions people ask
Is section 89 of THE MIZORAM (LAND ACQUISITION, REHABILITATION AND RESETTLEMENT) ACT, 2016. still in force?
No repeal of the MIZORAM (LAND ACQUISITION, REHABILITATION AND RESETTLEMENT) ACT, 2016. is recorded.