4. Preparation of Social Impact Assessment Study.
(1) Whenever the government intends to acquire land for a public purpose, it shall consult the concerned
Village Council or Local Council or Municipality as the case may be at Village level or Local Council
Ex-121/2016 - 6 -
level in the affected area and carry out a Social Impact Assessment Study in consultation with them,
in such manner and from such date as may be specified by the Government by notification.
(2) The notification issued by the Government for commencement of consultation and of the Social
Impact Assessment Study under sub-section (1) shall be made available in the local language to the
Village Council or Local Council or Municipality, as the case may be, and in the offices of the District
Collector, the Deputy Collector and the Block Development Officer, and shall be published in the
affected areas, in such manner as may be prescribed and uploaded on the website of the Government:
Provided that the Government shall ensure that adequate representation has been given to the
representatives of Village Council or Local Council or Municipality as the case may be at the stage of
carrying out the Social Impact Assessment Study:
Provided further that the Government shall ensure the completion of the Social Impact Assessment
Study within a period of six months from the date of its commencement.
(3) The Social Impact Assessment study report referred to in sub-section (1) shall be made available to
the public in the manner prescribed under Section 6.
(4) The Social Impact Assessment study referred to in sub-section (1) shall amongst other matters
include all the following, namely:-
(a) assessment as to whether the proposed acquisition serves public purpose;
(b) estimation of affected families and the number of families among them likely to be displaced;
(c) extent of lands, public and private, houses, settlements and other common properties likely to
be affected by the proposed acquisition;
(d) whether the extent of land proposed for acquisition is the absolute bare – minimum extent
needed for the project;
(e) whether land acquisition at an alternate place has been considered and found not feasible;
(f) study of social impacts of the project, and the nature and cost of addressing them and the
impact of these costs on the overall costs of the project vis-á-vis the benefits of the project:
Provided that Environmental Impact Assessment study, if any, shall be carried out simultaneously
and shall not be contingent upon the completion of the Social Impact Assessment study.
(5) While undertaking a Social Impact Assessment study under sub-section (1) the Government
shall, among other things, take into consideration the impact that the project is likely to have on
various components such as livelihood of affected families, public and community properties, assets
and infrastructure particularly roads, public transport, drainage, sanitation, sources of drinking water,
sources of water for cattle, community ponds, grazing land, plantations, public utilities such as post
offices, fair price shops, food storage godowns, electricity supply, health care facilities, schools and
educational or training facilities, anganwadis, children parks, places of worship, land for traditional
tribal institutions and burial and cremation grounds.
(6) The Government shall require the authority conducting the Social Impact Assessment study to prepare
a Social Impact Management Plan, listing the ameliorative measures required to be undertaken for
addressing the impact for a specific component referred to in sub-section (5), and such measures
shall not be less than what is provided under a scheme or programme, in operation in that area, of the
State or Central Government, as the case may be, in operation in the affected area.
Previous and next
All sections of THE MIZORAM (LAND ACQUISITION, REHABILITATION AND RESETTLEMENT) ACT, 2016.
Questions people ask
Is section 4 of THE MIZORAM (LAND ACQUISITION, REHABILITATION AND RESETTLEMENT) ACT, 2016. still in force?
No repeal of the MIZORAM (LAND ACQUISITION, REHABILITATION AND RESETTLEMENT) ACT, 2016. is recorded.