Rule 5, GUWAHATI BUILDING BYELAWS: Procedure regarding construction of buildings and subdivision/ transfer of private land 5.1 Notice
GUWAHATI BUILDING BYELAWS - Rule 5
Text of rule 5
Procedure regarding construction of buildings and subdivision/ transfer of private land 5.1 Notice
5. Procedure regarding construction of buildings and subdivision/ transfer of
private land
5.1 Notice: - Every person who intends to erect or re-erect or make material
alteration in any place in a building or part thereof, within the
jurisdiction of Guwahati Metropolitan Development Authority, shall
give notice in writing to the Chief Executive Officer of the Authority,
his said intention in the form prescribed from time to time by the
Authority and such notice shall be accompanied by the plans and
conforming to the requirements of Section 25 and 29 of Act, 1985 in
triplicate on blue or white prints. One copy shall be retained in the office
of the Authority for record after issue of permission and the other two
shall be returned to the applicant. (One copy for submission to Local
body). In the event of Authority returning the plans after some
observations they will have to comply with, in accordance with the
Building Byelaws while no permission fees is required to be paid.
Note: Format of notice to erect or re-erect or make material alteration
in a building as required under Clause 5.1 of Building Byelaws along
with a checklist to ensure complete submission of documents to facilitate
early disposal of cases shall be framed (i) for building upto G+2nd floor
and (ii) for buildings G+3rd floor and above.
5.2 Exempted to Government: - All Government (Central and State) or Semi
Government Departments except the Defense Department shall also
forward copies of their plans to the Authority complying with all the
provisions of the Byelaws.
5.3 Plans accompanying notice: - The following plans shall accompany the
notice.
(a) Site Plan:- The site plan drawn to a minimum scale of 1:200 and
shall show-
(i) the boundaries of the site with dimensions and of any
contiguous land belonging to the owner;
(ii) the position of the site in relation to neighboring streets
with name of the street on which the building is situated;
(iii) the position of the building and all other buildings (if
any) which the applicant intends to erect upon his land in
relation to-
(1) The boundaries of the site and in case where the site
has been partitioned, the boundaries of the portion
owned by the applicant and also of the portions
owned by other owners of that compact plot;
(2) The means of access from an existing street to the
building;
NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006
Guwahati Metropolitan Dev. Authority Page No. [14]
(3) Space to be left around the building to secure free
circulation of air, admission of light and access for
scavenging purpose etc.
(iv) scale with north line;
(v) plot area, plinth area, each floor area;
(vi) location, name and width of each adjacent road or lane;
(vii) such other particulars as may be prescribed by the
Authority.
5.3 (b) Building Plan:- The detailed plans of the building and elevation
and sections sent with the notice shall be accurately drawn to
scale of 1:100. Adequate arrangement for proper drainage shall
also be made. The plan shall include-
(i) Complete layout plan of the area or areas showing
location and width of all streets dimensions, sizes and
uses of all the plots.
(ii) Plans of all floors, accessory buildings and basement
plan. Such drawings shall fairly indicate the size of
rooms, size of windows and ventilators, size of door
opening and stair runs.
(iii) Location of drains, sewers, public utility, electric lines,
services, transformers.
(iv) Exact location of essential services such as W.C. sink,
bath etc.
(v) Proposed and existing works should be clearly indicated
in different colours (other than red) or in marking.
(vi) Sectional drawings showing clearly the sizes of footings,
thickness of basement walls if any, all roof slabs and
floor slabs, ceiling heights and parapet height with their
materials. The section shall indicate the drainage and
slope off the roof. At least one section shall be taken
through the staircase.
(vii) Details of served privies (if any).
(viii) All street elevation.
(ix) Dimensions of the projected portions beyond the
permissible building line i.e. chajja line.
(x) Scale with north line.
(XI) The existing ground level of the plot and proposed ground
level in relation to abutting road level to be clearly mentioned
in drawing.
(XII) For multistoreyed buildings an undertaking stating that debris
or construction materials will not be stacked in public places
leading to public nuisance. If the Authority finds that the
applicant caused nuisance to public while executing
construction necessary fine be compelled as per provisions in
the byelaw.
(XIII) Detailed parking plan.
(XIV) Space used for storing construction materials during the time
of construction.
(XV) The owner shall file an undertaking stating that he shall leave
and surrender land for road widening, if required free of cost
and he will not violate any rules, building byelaws, and that in
case of violations the Authority shall be at liberty to
NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006
Guwahati Metropolitan Dev. Authority Page No. [15]
summarily remove such deviations as per GMC/GMDA Act.
(The form of undertaking shall be as at Appendix-VI)
5.3 (c) Service Plan- Details of private water Supply, sewerage disposal
system and details of building services, where required by
Authority, shall be made available on a scale not less than 1:200.
5.3 (d) Specification- General specification of the proposed
constructions including a detail calculation sheet of FAR in the
proposal showing detail as given in CL. 58.10.1 and 58.10.2
giving type of grade of materials to be used in the prescribed
form duly signed by the R.T.P. of Architect/ Engineer/ Structural
Engineer as the case may be and countersigned by applicant shall
accompany the notice.
5.3 (e) Supervision- The notice shall be further accompanied by a
certificate of supervision in the prescribed form by the R.T.P. In
the event of the said R.T.P. ceasing to be employed for the work,
the further development work shall stand suspended till a new
R.T.P. is appointed and his certificate of supervision along with a
certificate for the work already done (either from the previous
one or the present) accepted by the Authority. Additional
documents, NOC that may be required other than those specified
herein are given in subsequent chapters for various types of
buildings.
5.3 (f) Any other statement as may be required by the Authority.
5.3 (g) Ownership Document-
Titleship document to justify the ownership of land. In case land
is not owned by applicant, lease deed or a NOC for allowing
applicant for construction in the form of affidavit.
5.3 (h) Every person who intends to subdivide any plot of land or
transfer any plot of land within Guwahati Metropolitan Area
shall give notice in writing to the Authority of his said intention
and such notice shall be accompanied by the plans and
statements together with a development fees as prescribed in the
Byelaw and with necessary document as prescribed in Section 2
of GMDA Act.
Note: (a) Subdivision of a residential building with proportionate
share of land is subject to requirement of minimum plot
size of land for residential use and a maximum of 6
(six) residential units.
(b) However for building falling under Assam Apartment
(construction and transfer of ownership) Act, the
provision of this Act will be followed.
5.3 (i) In addition to the requirement as prescribed above following
additional-document-is-required.
(1) Land sale permission from Deputy Commissioner.
(2) All layout plans before submission to Authority shall be
signed by owner(s) and by one of the following-
NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006
Guwahati Metropolitan Dev. Authority Page No. [16]
(i) Architect holding a valid registration of the Council of
Architect/ R.T.P of GMDA for layout plan of plots of
measuring more than 0.5 HA and below 2.5 HA.
(ii) Town Planner qualified to be a member with Institute of
Town Planners, India for plots measuring 2.5 HA and above.
(iii)In all layout plan a minimum of 5% of the land is to be
reserved for parks/ playgrounds. This land has to be handed
over to GMDA for its development as parks/ playgrounds
free of cost.
(iv) The party should submit an affidavit along with the
application form declaring the following: (a) Particulars of
land, (b) Ownership of land, (c) That they have not applied
for permission of the same building before any other
authority and same is not rejected, (d) That they will
construct the building as per approved plan, (e) They will
submit completion certificate prior to obtaining electric
connection, (f) That applicant will not occupy the building
without obtaining the occupancy certificate.
(v) The property tax should be submitted by the applicant during
submission of application form to ensuring up-to-date
payment of tax to GMC.