FORM NO. 11
FORM NO. 11
COMPLETION REPORT
Reference No.
Owner's Name: Location:
Submitted on: Received on:
The
Sir,
The work of erection/re-erection of building as per approved plan is completed
under the Supervision of Architect/Construction Engineer who have given the
completion certificate which is enclosed herewith.
We declare that the work is executed as per the provisions of the Act and
Development Control Regulations / Byelaws and to our satisfaction. We declare that
the construction is to be used for ______________ the purpose as per approved plan
and it shall not be changed without obtaining written permission.
We hereby declare that the plan as per the building erected has been submitted
and approved. We have transferred the area of parking space provided as per approved
plan to an individual/association before for occupancy certificate.
Any subsequent change from the completion drawings will be our responsibility.
Yours faithfully,
(Developer’s / Builder’s Signature) (Owner’s Signature)
Name of Developer / Builder Name of Owner
Date:
Address:
Encl: Completion Certificate
NEW REVISED BUILDING BYELAWS FOR GUWAHATI METROPOLITAN AREA-2006
Guwahati Metropolitan Dev. Authority Page No. [86]
Previous and next
Questions people ask
Is form 11 of GUWAHATI BUILDING BYELAWS still in force?
No repeal of GUWAHATI BUILDING BYELAWS is recorded.