Rule 12, Jammu and Kashmir Control of Building Operations Act: Authentication of Orders and Instruments
Jammu and Kashmir Control of Building Operations Act - Rule 12
Text of rule 12
Authentication of Orders and Instruments
12. Authentication of Orders and Instruments.–– Any order or instrument
requiring authentication by the Authority shall be signed by the Chairman or any
other officer authorised by him in this behalf.
–––––––
8
FORM ‘A’
(See rule 4(1))
Application under sub-section (1) of section 5 for permission
for erection or re-erection of building.
To
The Chairman of the
Building Operations Controlling Authority.
I hereby submit an application for permission to undertake:––
the development of the site
construction of a building
repair of a building
in accordance with the plans submitted herewith. I attach the following documents:–
8 copies of the Building Plans showing the site plan, key location plan, section
and elevations of each floor and specifications.
An attested copy of sale deed/lease deed/gift deed/Court decree/mutation
order in suppport of ownership.
Yours faithfully,
Name_______________________
Postal Address________________
Telephone No._________________
Enclosures attached:
Copies of Building Plan showing site plan,
Key location plan, section, elevation and
Specifications.
Attested copy of _________________in support of ownership of land.
–––––––
9
1[FORM “A-1”
(See Rule 4 (1))
An application under sub-section (1) of section 5 for permission or erection or re-
erection of Building
To
The Chairman,
Building Operations Controlling Authority,
Patnitop Development Authority Area,
Kud, Distt. Udhampur, J&K.
Sir,
I hereby submit an application for permission to undertake:––
(a) The Development of the site.
(b) Construction of Building.
(c) Repair of a Building.
In accordance with the plans submitted herewith I attach the following
documents:––
(1) 8 copies of the Building Plans showing the site plan, key location plan,
section and elevations of each floor and specifications.
(2) An attested copy of sale deed/lease deed/ gift deed /court decree/
mutation order in support of ownership of the land was endorsed by
the Deputy Commissioner Udhampur/Doda.
(3) No objection certificate from the Forest Department.
(4) No objection certificate from the Public Health Engineering Depart-
ment.
(5) No objection certificate from the Power Development Department.
(6) No objection certificate from Sewerage and Drainage Department.
(7) No objection certificate from the Officer Commanding Beacon, Batote
(If construction is falling on National Highway (NH1A).
Form A-1 inserted vide SRO-249 dated 12-07-2001.
10
(8) No objection certificate from the Executive Engineer PWD (R&B)
concerned (if construction is falling on the PWD records).
(9) No objection certificate from the Fire Services Department (In case of
Hotel/Commercial Building).
(10) No objection certificate from the Pollution Control Board in case of
Hotel/Commercial Establishment.
(11) Building for which permission is sought is proposed at Kh. No.
______________ Khewat No. –––––––––––––––– Khata No. –––––
Land measuring ––––––––––– at Village –––––––––– Tehsil ––––––
––––––––––– Distt. Udhampur/Doda.
(12) Measures proposed for disposal of liquid/solid waste of the proposed
construction.
(13) Purpose for which the construction of Building is proposed.
(14) The construction of the building will be supervised by:
(15) Estimated cost of the proposed Building in case of Hotel/Commercial
Building is :
Rs. in Lakh :
(16) Application Form charges have been paid vide G. R. No. _________.
Dated: ___________
Yours faithfully,
Name :–––––––––––––––––––––––––
S/O :––––––––––––––––––––––––––
Postal Address :––––––––––––––––––
Village :––––––––––––––––––––––––
Tehsil :–––––––––––––––––––––––––
District :––––––––––––––––––––––––
Telephone No : __________________
11
FORM ‘B’
(See Rule 4 (3))
Report of the Inspecting Officer
1. Name and address of the Applicant –––––––––––––––––––––––––––––––
2. Date of Application –––––––––––––––––––––––––––––––
3. Date and Time of Inspection –––––––––––––––––––––––––––––––
4. Whether the applicant or his authorised Yes/No
representative was present at the time of
inspection.
5. Whether the site has access Yes/No
6. If yes, width of the road or lane –––––––––––––––––––––––––––––––
having access to the site
7. Whether drinking water facility is available Yes/No
at the locality.
8. Whether the electricity supply is available Yes/No
at the locality.
9. Whether the site is falling under high Yes/No
tension power line.
10. Whether the site is flood prone. Yes/No
11. Whether the site encroaches on the State Yes/No
land or public utility area.
12. Whether the Key plan of the Plan is correct. Yes/No
N.B. If the Key Plan has been shown wrongly in the
Building Plan, the correct rough key plan
showing the identification marks on all the four
sides shall be drawn below or on the opposite
page.
Signature –––––––––––––––––––––––––––––––
Name of Inspecting Officer ––––––––––––––––––
Designation –––––––––––––––––––––––––––––
Date:_________
–––––––
12
1[FORM ‘B – 1’
(See Rule 5 (1))
Report of the Inspecting Officer
1. Name and address of the Applicant –––––––––––––––––––––––––––––
2. Date of Application –––––––––––––––––––––––––––––
3. Construction site –––––––––––––––––––––––––––––
4. Date and Time of Inspection –––––––––––––––––––––––––––––
5. Particulars of the permission sought –––––––––––––––––––––––––––––
6. Whether the applicant or his authorised representative Yes/No
was present at the time of inspection.
7. Whether the site has access Yes/No
8. If yes, width of the road or lane –––––––––––––––––––––––––––––
having access to the site
9. Whether drinking water facility is available at the locality. Yes/No
10. Whether the electricity supply is available at the locality. Yes/No
11. Whether the site is falling under high tension power line. Yes/No
12. Whether the site is flood prone. Yes/No
13. Whether the site encroaches on the State land or public Yes/No
utility area.
14. Whether the Key plan of the Building Plan is correct. Yes/No
Certified that the site and building plans drawn by the approved Architect/
Draftsman have been checked at site and found correct. The observations made at
site are as under:-
N.B. If the Plan has been shown wrongly in the Building Plan, the correct rough
key plan showing the identification marks on all the four sides shall be drawn
below or on the opposite page.
Signature –––––––––––––––––––––––––––––––
Name of Inspecting Officer ––––––––––––––––––
Designation –––––––––––––––––––––––––––––]
–––––––
1. Form B-1 inserted vide Notification No. LSG(J)-94/147 dated 03.12.1998.
13
1.Form B-2 added by Notification LSG(J)94/147 dated 03.12.1998.
1[FORM ‘B-2’
(See Rule 45(1))
Report of the Inspecting Officer
1. Distance of proposed construction from nearest lake fringe/shore-line/ waterway
as indicated on the index plan. –––––––––––––––––––––––––––––––
2. Measures taken for disposal of Liquid/Solid waste as a result of proposed
construction for –––––––––––––––––––––––––––––––––––––––––––––
(a) Waste construction material during construction ––––––––––––––––
(b) Solid waste –––––––––––––––––––––––––––––––––––––––––––
(c) Sullage ––––––––––––––––––––––––––––––––––––––––––––
(d) Sewage ––––––––––––––––––––––––––––––––––––––––––––
(Plan should show septic tank and soakage pit on connection to sewer line.)
3. Measures proposed for drainage of proposed constructed area–––––––––––
4. Whether the applicant proposes to get connected to sewage drainage scheme
of the Jammu and Kashmir LAWDA Yes/No
5. Uitimate occupancy–––––––––––––––––––––––––––––––––––––––––––
Signature –––––––––––––––––––––––––––––––
Name of Inspecting Officer ––––––––––––––––––
Designation –––––––––––––––––––––––––––––
–––––––
14
1[FORM ‘C’
Proxy Form
––––––––––––––––––––––––––– Name of the Department/Organisation
I ––––––––––––––––––––––––––––– of –––––––––––––––––––––––
being a member of the Building Permission Authority of ––––––––––––––––
representing the above Department/Organisation hereby appoint Mr. ––––––––––
––––––––– of ––––––––––––––––––––––– failing him Mr. ––––––––––––––––
––––––– of –––––––––––––––––––––––––––––– as my proxy to attend and
decide upon the issue arrising out of discussions held.
Signed this –––––––––––––––––– day of –––––––––––––––– of the year
–––––––––––––.
Signature –––––––––––––––––––––––––––––––
Name ––––––––––––––––––––––––––––––––––
Designation –––––––––––––––––––––––––]
–––––––
1.Form C inserted by Notification LSG(J)94/147 dated 03.12.1998.
Previous and next
All provisions of Jammu and Kashmir Control of Building Operations Act
Questions people ask
Is rule 12 of Jammu and Kashmir Control of Building Operations Act still in force?
No repeal of Jammu and Kashmir Control of Building Operations Act is recorded.