Rule 1, Reallocation of Generating Capacity to Discoms: No. 2260-F-3-24-2009-XIII
Reallocation of Generating Capacity to Discoms - Rule 1
Text of rule 1
No. 2260-F-3-24-2009-XIII
1. No. 2260-F-3-24-2009-XIII.-State Government has notified M.P. Electricity Reforms Transfer Schemes
Rules 2006 vide notification dated 3rd June 06 whereby the functions, properties, interest rights and obligations of
the Residual Madhya Pradesh State Electricity Board relating to Bulk Purchase and Bulk Supply of Electricity along
with the related agreements and arrangements have been transferred and vested in MP Power Management Company
Limited (MP PMCL), formerly known as MP Power Trading Company Limited (TRADECO).
2. In order to keep the retail tariff uniform in the entire State without sacrificing the incentive for loss reduction
& efficiency gains by Discoms during the transient phase of power sector reforms and since the revenue requirement
are different for all the three Discoms, the State Government reallocated the capacity available as on March 2012
vide Gazette Notification No. 2660-F-3-24-2009-XIII, dated 29th March 2012.
3. With the similar intent, vide this order, the State Government supersedes Gazette Notification No. 26601F
3-24/2009-XIII dated 29th March 2Q12 in order to allocate new capacities and achieve the same "objective of
maintaining uniform retail tariff in the' entire State and hence reallocates the capacity available as on'date to the
three Distribution companies in the manner prescribed below:-
(i) Summary of total installed generation capacity available to the State:-
Table - 1: Total Available Generation Capacity
S. MP's Power Share from
No.
(1) (2)
1 Central sector WR
2 Central sector ER
3 DVC
Installed Capacity (MW)
(3)
9,193.00
1,500.00
500.00
229
MP Share (MW)
(4)
2,lOLOO
75.00
200.00
230 Tf~ ~, ~--.,tcp 19 11Ti'f 2013
(1) (2) (3) (4)
4 Indira Sagar Project 1,015.00 1,015.00
5 Sardar Sarovar Project 1,450.00 827.00
6 Omkareshwar HEP 520.00 520.00
7 InterState Hydel 646.00 379.00
8 GENCO Thermal 2,870.00 2,770.00
9 GENCO Hydro 605.00 605.00
Total ..18,299.00 8,492.00
(ii) The total available generation capacity as shown in Table above is reallocated to the Discoms
as shown below:-
Table - 2: Reallocation of Generating Capacity to Discoms
Discom Generation Capacity Allocation
M.P. Madhya Kshetra Vidyut Vitaran Co. Ltd.
M.P. Paschim Kshetra Vidyut Vitaran Co. Ltd.
M.P. Poorv Kshetra Vidyut Vitaran Co. Ltd.
%
32.56%
39.22%
28.22%
MW
2,765.28
3,330.68
2,396.04
(iii) The plant-wise reallocation of available generation capacities to the Discoms shall be as per
Appendix-I.
(iv) The power generation available from captive power producers, mini/ micro hydel projects or from
non conventional energy sources not included in the above capacity allocation, are deemed to be
assigned to the Discoms in whose geographical location such power project exists.
4. In addition to the above allocation, the specific allocation of 200 MW made available to the State from
the un-allocated power of CGSs of WR for supply to drought prone districts of Bundelkhand Region are assigned
to the MP Poorv Kshetra Vidyut Vitaran Co. Ltd., for the drought prone area Sagar Region exclusively. After
considering the specific allocation for Bundelkhand Region the effective allocation of generating capacity to the
Discoms is detailed in Appendix-2 and shall be as under:
Table -3: Final allocation of Generating Capacity to Discoms
Discom Generation Capacity Allocation
M.P. Madhya Kshetra Vidyut Vitaran Co. Ltd.
M.P. Paschim Kshetra Vidyut Vitaran Co. Ltd.
M.P. Poorv Kshetra Vidyut Vitaran Co. Ltd.
Previous and next
All provisions of Reallocation of Generating Capacity to Discoms
Questions people ask
Is rule 1 of Reallocation of Generating Capacity to Discoms still in force?
No repeal of Reallocation of Generating Capacity to Discoms is recorded.