Text of rule 3
Application of these rules
3. Application of these rules.--
The following shall be the rules for exemption of any building or class of building
developed on or before the 1st day of July 2007 and deviated from certain
provisions of the Act or any rule or regulation made thereunder:-
(i) The constructions of building should have been completed on or before
the 1st July 2007;
(ii) These rules are applicable for the entire State of Tamil Nadu excepting
the hill areas, falling within the purview of Hill Area conservation Authority;
(iii) The grant of exemption shall be with reference to the Development
Regulations for chennai Metropolitan Area and the Development control
Regulations in cases of areas falling within the purview of the Director of
Town and Country Planning prevailing as on the date of notification of
these rules;
(iv) The requirements for compliance of certain planning parameters viz.,
Road Width, Setbacks, Floor Space Index, Vehicular Parking, Open Space
Reservation (OSR) shall be as per Annexure-IA and IB for chennai
Metropolitan Planning Area and Directorate of Town and country Planning
areas, respectively, for exemption under these rules to the extent indicated
herein. Therefore, similar requirements under the provisions of other
Statutes/Rules like Tamil Nadu District Municipalities Building Rules, 1972,
Tamil Nadu Panchayats Building Rules, 1997 and Multi-Storied and Public
Buildings Rules, 1973, etc., will stand exempted to the extent as provided
under these rules;
(v) The definitions of the Development Regulations or Development Control
Regulations, as the case may be, shall apply;
(vi) In the event of applicant providing offsite parking, the same shall be
provided within a distance of 500 m and produce the ownership or lease
document in his favour for that site having a minimum validity period of 33
years;
(vii) The penalty leviable over and above the fees or charges normally
leviable as per Annexure-II;
(viii) For the purpose of calculation of penalty, the Guideline Value
prevailing on the date of filing of application for regularisation;
(ix) (a) The applicant shall file online application for regularization within 6
months from the date of notification of these rules.
(b) The applicant shall assess the violation in the building, workout the
applicable regularisation fees as prescribed in Annexure-II and submit the
same online for the full assessed amount. If any under assessment in the
self assessment, is detected at any stage, the regularization application
shall be rejected, the amount shall be forfeited and enforcement action
against the violation shall be taken.
(x) In cases where the applicant withdraws his application filed under
Regularisation Scheme under section 113-A of the Act and apply afresh
under section 113-c of the Act, the regularisation fee already paid by him
under section 113-A of the Act will be adjusted;
(xi) In cases where the applications filed under section 113-B of the Act
which are eligible for exemption under section 113-c of the Act shall be
remitted back to competent Authority for processing under Section 113-c
of the Act, the regularisation fee already paid by the applicant under
section 113-B of the Act will be adjusted;
(xii) The Structural Stability Certificate issued by an registered Structural
Engineer in cases of Special Buildings, Group Developments and Multi-
Storied Buildings in consultation with the competent Geo-Technical
Engineer is a pre-requisite for filing the application seeking exemption
under section 113-C of the Act;
(xiii) In case of ordinary building, certification by a Registered Civil
Engineer is sufficient for filing application seeking exemption under section
113-c of the Act;
(xiv) No Objection Certificate and Compliance Certificate from the
Directorate of Fire and Rescue Services for Commercial Special Buildings,
all Multi-Storied Buildings and all public buildings is a prerequisite for filing
the regularization application under section 113-c of the Act;
(xv) The plans accompanying the applications for Ordinary, Special
Buildings, Group Developments and Multi-Storied Buildings irrespective of
usage category of the building have to be signed by the Registered
Architect/Registered civil Engineer/Licenced Surveyor as per requirement;
(xvi) The competent Authority shall scrutinise the applications submitted
for exemption under section 113-c of the Act, along with the structural
stability certificate and other data related to site and building and the
Competent Authority shall decide on the corrective measures, if any, and
communicate the same to the applicant for carrying out the corrections,
within a time period as may be specified by the Competent Authority but
not more than six months, failing which the regularization application shall
be rejected.
(xvii) Rs. 1 per square feet for ordinary buildings applications and Rs. 2 per
sq. ft. for applications other than ordinary buildings will be collected as
scrutiny fee which has to be paid along with the application. The
applications for exemptions under section 113-c of the Act is not applicable
for regularization of vacant site or plot;
(xviii) An affidavit sworn by the applicant in Rs. 100/- non judicial stamp
paper that planning permission issued for exemption under section 113-c
of the Act will not confer any right on the applicant to obliterate acquisition
proceedings and to compensation for the building so permitted contrary to
the provisions contained in the said Land Acquisition Act, 1894 (central Act
I of 1894) or any other land Acquisition Laws.
Previous and next
All provisions of Assessment and Collection of amount for the Exemption of Buildings Rules
Questions people ask
Is rule 3 of Assessment and Collection of amount for the Exemption of Buildings Rules still in force?
No repeal of Assessment and Collection of amount for the Exemption of Buildings Rules is recorded.