Rule 62, The Punjab Canal and Drainage Rules, 2025: No objection certificate before commencing any construction
The Punjab Canal and Drainage Rules, 2025 - Rule 62
Text of rule 62
No objection certificate before commencing any construction
62. No objection certificate before commencing any construction.-
(1) Any person or entity interested in constructing structure or a project
or a building, shall obtain a No Objection Certificate from the department
before the commencement of such construction, if it falls within such
distance as may be notified by the State Government from time to time
from the notified boundary of a river, stream, lake or drain. The authority
responsible for approval of building plans shall be responsible to ensure
the same. The Guidelines to be followed for No Objection Certificate
shall be notified by the State Government.
(2) The State Government shall endeavour to digitalise the data for
notified width of rivers and drains on Geographic Information System
platforms for facilitation of plan sanctioning authorities. Only those projects
which fall within one hundred fifty meter of the notified boundary of a
river, stream, lake or drain shall be required to obtain a No Objection
Certificate. The concerned plan sanctioning authority shall refer only
such cases to the department.
(3) Any application received for No Objection Certificate shall be decided
within twenty one days of receipt provided the same is complete as per
176
Section 32
Section 32
Section 38
PUNJAB GOVT. GAZ., MARCH 28, 2025
(CHTR 7, 1947 SAKA)
such format, as may be notified by the State Government.
(4) The department shall develop online portal for processing such
applications for timely disposal.
Previous and next
Questions people ask
Is rule 62 of the Punjab Canal and Drainage Rules, 2025 still in force?
No repeal of the Punjab Canal and Drainage Rules, 2025 is recorded.