Rule 17, RMMCR 2017 (updated upto 15.04.2025): Grant of quarry licence
RMMCR 2017 (updated upto 15.04.2025) - Rule 17
Text of rule 17
Grant of quarry licence
17. Grant of quarry licence.- (1) Quarry licence shall be granted to a person who offers highest
premium amount through e-auction subject to provisions of 1[clause (vi) of sub-rule (5) of rule 10 or
clause (viii) of] sub-rule (8) of rule 14:
2[Provided that the gap area and strip of land shall be granted as per the provisions of sub-rule (3)
and (4) of rule 8 respectively.]
5[(2) Upon compliance of the sub-rule (10) of rule 14 or sub-rule (8) of rule 17A, as the case may be, the
competent authority shall issue a letter of intent to successful bidder or applicant, as the case may be, to,-
(i) furnish the performance security as specified in rule 20 within six months from date of
issuance of letter of intent;
(ii) submit approved mining plan within six months from date of issuance of letter of intent;
(iii) submit approval under the Forest (Conservation) Act, 1980 or consent under the
Rajasthan Tenancy (Government) Rules, 1955 or prior recommendation of the
Panchayati Raj Institution, concerned within eighteen months from date of issuance of
letter of intent, as the case may be; and
(iv) submit consent from any other Authority under the control of the State Government as
per the condition of notice inviting bid:
Provided that plots auctioned with pre-embedded clearances, the letter of intent shall be
issued for compliance of condition specified in clause (i) only.
Provided further that the above period may be extended by the Mining Engineer or
Assistant Mining Engineer concerned as per the provisions of sub-rule (4), subject to payment
of late fees at the rate of ten percent of annual licence fee for delay of every month or part
thereof.]
___________________________________________________________________________________
1. Substituted vide Notification dated 14.03.2018 2. Added vide Notification dated 16.08.2022
3. Added vide Notification dated 03.01.2025 4. Deleted vide Notification dated 03.01.2025
4. Substituted vide Notification dated 03.01.2025
25
5[(3) If the applicant or successful bidder, as the case may be, complies with the conditions of letter of
intent within the stipulated or extended period of time, the quarry licence shall be granted by the Mining
Engineer or Assistant Mining Engineer concerned with the condition that the licencee shall commence
mining operations after obtaining environment clearance. The grantee shall pay the second installment
being twenty percent of the premium amount before issuance of quarry licence in Form-7 by the Mining
Engineer or Assistant Mining Engineer:
Provided that in the cases where letter of intent has been issued before commencement of the
Rajasthan Minor Mineral Concession (Second Amendment) Rules, 2022 with the condition to submit
environment clearance, quarry licence shall be granted with above condition after deposition of late fees
at the rate of ten percent of annual licence fee for delay of every month or part thereof.
Provided further that if the successful bidder fails to comply with the conditions of letter of intent
within the stipulated or extended period of time, the Mining Engineer or Assistant Mining Engineer
concerned shall reject the bid or application, as the case may be and forfeit the application fees, premium
amount and performance security deposited, after providing an opportunity of being heard by issuing
notice of thirty days.]
6[(4) No quarry licence shall be granted on the expiry of a period of three years from the date of the letter
of intent and the letter of intent shall be invalidated leading to annulment of the entire process of auction:
Provided that the Mining Engineer or Assistant Mining Engineer concerned may allow a further
period of two years for issuance of quarry licence if the reasons for delay were beyond the control of the
holder of letter of intent.
Provided further that where the period of five years has expired or expiring within one year from
the date of commencement of the Rajasthan Minor Mineral Concession (Amendment) Rules, 2025, the
letter of intent shall be invalidated in case quarry licence is not granted within a period of one year from
the date of commencement of the said Rules of 2025.]
Previous and next
Questions people ask
Is rule 17 of RMMCR 2017 (updated upto 15.04.2025) still in force?
No repeal of RMMCR 2017 (updated upto 15.04.2025) is recorded.