Rule 10, RMMCR 2017 (updated upto 15.04.2025): Period of quarry licence
RMMCR 2017 (updated upto 15.04.2025) - Rule 10
Text of rule 10
Period of quarry licence
10. Period of quarry licence.- (1) On and after the commencement of these rules, all quarry
licence shall be granted for a period not exceeding thirty years:
____________________________________________________________________________________
1. Deleted vide Notification dated 14.03.2018 2. Substituted vide Notification dated 24.10.2024
13
Provided that ending period of quarry licence granted shall be 31st of March.
(2) All quarry licences granted before the commencement of these rules shall be deemed to have been
granted for a period of thirty years:
Provided that ending period of such quarry licence shall be 31st of March.
(3) Notwithstanding anything contained in sub-rule (1) and (2), the period of licence, granted before the
commencement of these rules, shall be extended and be deemed to have been extended upto a period
ending on the 31st March, 2025 with effect from the date of expiry of the period of renewal/extension last
made or till the completion of renewal/extension period, if any, or a period of thirty years from the date
of initial grant of such licence, whichever is later, subject to the condition that all the terms and
conditions of the licence have been complied with.
2[(3A) Notwithstanding anything contained in sub-rule (1), (2) and (3), the period of existing quarry
licences may be further extended upto 31st March, 2040 subject to following conditions:-
(i) An online application for extension of quarry licence period shall be submitted to the
Mining Engineer or Assistant Mining Engineer concerned with a non refundable fee of
rupees three thousand;
(ii) Licencee has not carried out any illegal mining activities 4[] or the case is compounded;
3[(iii) Payment of premium amount at the rate of one third of annual licence fee for each year of
extension or part thereof sought by the licencee in following manner:-
S.
No.
Period of extension Number of
installments
Payment mode
1 2 3 4
1. More than ten years Five (i) first installment along with
application; and
(ii) second and subsequent
installment, as the case may
be, at the beginning of
financial year after issuance
of order of extension.
2. More than five and
upto ten years
Three
3. More than two and
upto five years
Two
4. Upto two years One
]
(iv) The applications for extension of quarry licence period shall be disposed of by Mining
Engineer or Assistant Mining Engineer concerned.]
(4) The Period of quarry licence may be extended upto the period for which the quarry remained close
(dies-non) due to any court order:
Provided that where licence remains closed due to any fault on the part of the licencee or where
part of licence was only closed, the period shall not be extended and annual licence fee shall be
chargeable for such period.
(5) On the expiry of the licence period, the area shall be put up for e-auction. The process of e-auction
shall be started well in advance so that before the expiry of the licence period, new licence may be
granted without any gap:
Provided that the licencee shall have right of first refusal at the time of e-auction held for such
licnce after expiry of the licence period in the following manner:-
(i) to be eligible to exercise the right of first refusal, the licencee shall comply with the
conditions of the quarry licence, the Act and the Rules made thereunder till its expiry;
(ii) 1[]
____________________________________________________________________________________
1. Deleted vide Notification dated 14.03.2018 2. Inserted vide Notification dated 16.08.2022
3. Substituted vide Notification dated 24.10.2024 4. Deleted vide Notification dated 03.01.2025
14
(iii) the notice inviting bid shall specify that the licencee holding the licence prior to expiry of
the quarry licence has the right of first refusal 1[];
(iv) upon conclusion of the 1[] of e-auction as per rule 14, the Mining Engineer or Assistant
Mining Engineer concerned shall issue a notice to the licencee seeking written
confirmation of his willingness to exercise the right of first refusal within a period of
seven days of the conclusion of the 1[] of e-auction;
(v) the notice given under clause (iv) to this sub-rule shall be acknowledged by the licencee
and who shall, within a period of fifteen days of receipt of notice, exercise the right of
first refusal in writing to the Mining Engineer or Assistant Mining Engineer concerned,
failing which it shall be construed that the licencee is not desirous of exercising the right
of first refusal and the successful bidder shall be entitled to a quarry licence in the
manner provided in these rules; and
(vi) if the licencee exercise the right of first refusal and matches the highest final offer price,
the licencee shall be deemed to be the successful bidder in place of the earlier successful
bidder declared after the 1[] of e-auction and shall be entitled to a quarry licence in the
manner provided in these rules.
Previous and next
Questions people ask
Is rule 10 of RMMCR 2017 (updated upto 15.04.2025) still in force?
No repeal of RMMCR 2017 (updated upto 15.04.2025) is recorded.