FORM-XI
FORM-XI
(see regulation 11)
To,
ADTCP
..............
Subject: Technical approval for final sanction of Single plot/Layout/Sub-division
Plan for....................purpose in plot(s)bearing
Sy.No(s).............of..............Village...............Hobli, .............Taluk under
The Karnataka Town and Country Planning ( Development of Land in
areas other than Local Planning Areas ) Regulations,2025 .
Reference: Application in Form-X submitted by the applicant
Shri/Smt................. dated:
The application under reference is forwarded herewith along with the the
completion certificates obtained under regulation11(7) and As-built-plan for Final
approval of layout under the KTCP Act, 1961 and The Karnataka Town and
Country Planning (Development of Land in areas other than Local Planning Areas)
Regulations, 2025. The Applicant has carried out all development works in the
layout including all infrastructure facilities and has obtained the certificate of
completion of all development works from the concerned Authority/Agency/
Department which are enclosed herewith. Technical approval for sanction of the
Final Layout is sought under regulation 12 of The Karnataka Town and Country
Planning (Development of Land in areas other than Local Planning Areas)
Regulations, 2025.
Chief Officer ………………TMC/ TP
or
The Panchayath Development Officer
...........Grama Panchayath
¨sÁUÀ 4J , 19 2025 3335
FORM –XII
(see regulation 12(2))
Technical approval for final sanction of the single plot/ layout/Sub-division
Plan.
Sub: Final sanction of the Layout/Sub-division Plan for....................purpose in an
Extent of ________________ Hectares in plot(s) bearing Sy.No(s) .............of..............
Village............... Hobli............. Taluk under The Karnataka Town and Country
Planning (Development of Land in areas other than Local Planning Areas)
Regulations, 2025
Ref: (1) Application dated...........................
(2) Demarcation layout/Subdivision plan in Form-IV Order No: ……….
dated…….
(3) Relinquishment deed in Form-VIII
(4) Application dated..........................
(5)Provisional layout/Subdivision plan for development Order No:……….
dated…….
(6) Application dated..........................
(7) Recommendation of the Chief Officer/PDO of the local authority in Form-XI,
No……………….Dated…..
On receipt of the application cited in reference (1) above, Technical
approval for Sub-division/Layout Plan for....................purpose in plot(s) bearing
Sy.No(s).........of...........Village...........Hobli……..Taluk under The Karnataka
Town and Country Planning (Development of Land in areas other than Local
Planning Areas) Regulations, 2025 was accorded to demarcate and set-it-out on
ground in letter cited in reference (2) above.
The applicant in letter cited in reference (3 ) above, has submitted the
relinquishment deed in Form-VIII, wherein the applicant has relinquished the
installations and fixtures under Roads/Streets, Parks, Civic Amenity sites ,
Public Utility areas, Vehicle Parking, any other infrastructure facility (as the
case may be) to the Local Authority through registered relinquishment deed
free of cost without claiming any compensation, has executed the registered
mortgage deed of all the corner sites and the unreleased intermediate sites in
the layout to the Local authority.
The Sanction of Provisional Single plot/ Layout/Sub-division plan
for................ purpose in plot(s) bearing Sy.No(s).........................
of........Village.........Hobli......Taluk under the Karnataka Town and Country
Planning ( Development of Land in areas other than Local Planning Areas )
Regulations,2025 was accorded to carry out development works in letter cited
in reference (5) above.
3336 , 19 2025 ¨sÁUÀ 4J
The applicant in letter cited in reference (6) above, has submitted that all
development works have been completed. On receipt of the letter cited in
reference (7) above, along with completion certificates and recommendations to
grant technical approval for sanction of Final Single plot /Layout/Subdivision
plan by the…………………Local authority, Technical approval for according
Final sanction of Single plot/Layout/Sub-division plan for ............ purpose in
plot(s) bearing Sy.No(s).............of .............. Village............... Hobli
.............Taluk under The Karnataka Town and Country Planning ( Development
of Land in areas other than Local Planning Areas ) Regulations,2025 is hereby
accorded subject to the following conditions, viz.-
(1)The Landuse Analysis of the layout / subdivision Plan is as shown below.
Sl.no Landuse Area in sqm Percentage
1 Residential/commercial
2 Parks and open spaces
3 Civic amenities
4 parking
5 Utilities
6 Roads
Total
(2) The Residential and Non residential Building sites, as the case may be,
sanctioned finally under this order are fit for allotment/sale/ registration;
Type Dimension
in metre
Building
Site numbers
Total
numbers
1. Residential Building Sites
2.Non-residential Building
Sites
¨sÁUÀ 4J , 19 2025 3337
a. Commercial
b. Industrial
Total
(3) The Parks, Roads/Streets, utilities, Civic amenity site and Installations in
the layout shall vest with the local authority;
(4) No further modification of the plan will be allowed except wherever the
owner(s) of the Building site(s) desires to amalgamate or subdivide the
building sites in the layout/Sub-division Plan as applicable under these
regulations. The applicant shall obtain prior permission for such
Amalgamation or Subdivision by the Director or the sub ordinate officer
authorised by the Director as specified under regulation......
(5) ............................ (such other conditions)
Three copies of the technically approved Final Single plot /sub-division/layout
plan for final sanction are enclosed with the order.
Director/ Addl director/Joint Director/Assistant Director
Office Seal
To
The Jurisdictional Chief Officer/PDO of the Local Authority
Copy, with a plan, for information and necessary action to:
(1) The Applicant, Address………………………
FORM –XIII
(see regulation 12(2))
Final sanction of the single plot/ layout/Sub-division Plan.
Sub: Final sanction of the Layout/Sub-division Plan for....................purpose in an
Extent of ________________ Hectares in plot(s) bearing Sy.No(s) .............of..............
Village............... Hobli............. Taluk under The Karnataka Town and Country
Planning (Development of Land in areas other than Local Planning Areas)
Regulations, 2025
Ref: (1) Application dated...........................
(2) Demarcation layout/Subdivision plan in Form-IV Order No: ……….
dated…….
(3) Relinquishment deed in Form-VIII
(4)Provisional layout/Subdivision plan for development Order No:……….
dated…….
(5) Application dated..........................
(6) Recommendation of the Chief Officer/PDO of the local authority in Form-XI,
No……………….Dated…..
3338 , 19 2025 ¨sÁUÀ 4J
(7) Technical approval for sanction of single plot/final layout/sub division plan
in Form-XII
On receipt of the application cited in reference (1) above, Technical
approval for of Sub-division/Layout Plan for....................purpose in plot(s)
bearing Sy.No(s).........of...........Village...........Hobli……..Taluk under The
Karnataka Town and Country Planning (Development of Land in areas other
than Local Planning Areas) Regulations, 2025 was accorded to demarcate and
set-it-out on ground in letter cited in reference (2) above.
The applicant in letter cited in reference (3 ) above, has submitted the
relinquishment deed in Form-VIII, wherein the applicant has relinquished the
installations and fixtures under Roads/Streets, Parks, Civic Amenity sites ,
Public Utility areas, Vehicle Parking, any other infrastructure facility (as the
case may be) to the Local Authority through registered relinquishment deed
free of cost without claiming any compensation, has executed the registered
mortgage deed of all the corner sites and the unreleased intermediate sites in
the layout to the Local authority.
The Sanction of Provisional Single plot/ Layout/Sub-division plan
for................ purpose in plot(s) bearing Sy.No(s).........................
of........Village.........Hobli......Taluk under the Karnataka Town and Country
Planning ( Development of Land in areas other than Local Planning Areas )
Regulations,2025 was accorded to carry out development works in letter cited
in reference (4) above.
The applicant in letter cited in reference (5) above, has submitted that all
development works have been completed. On receipt of the letter cited in
reference (6) above, along with completion certificates and recommendations to
grant technical approval for sanction of Final Single plot /Layout/Subdivision
plan by the…………………Local authority, Technical approval in Form-XII for
according Final sanction of Single plot/Layout/Sub-division plan for ............
purpose in plot(s) bearing Sy.No(s).............of .............. Village............... Hobli
.............Taluk under The Karnataka Town and Country Planning ( Development
of Land in areas other than Local Planning Areas ) Regulations,2025 has been
accorded by the Director/ Addl Director/Joint Director/Assistant Director. Final
sanction is hereby accorded subject to the following conditions, viz.-
¨sÁUÀ 4J , 19 2025 3339
(1)The Landuse Analysis of the layout / subdivision Plan is as shown below.
Sl.no Landuse Area in sqm Percentage
1 Residential/commercial
2 Parks and open spaces
3 Civic amenities
4 parking
5 Utilities
6 Roads
Total
(2) The Residential and Non residential Building sites, as the case may be,
sanctioned finally under this order are fit for allotment/sale/ registration;
Type Dimension
in metre
Building
Site numbers
Total
numbers
1. Residential Building Sites
2.Non-residential Building
Sites
a. Commercial
b. Industrial
Total
(3) The Parks, Roads/Streets, utilities, Civic amenity site and Installations in
the layout shall vest with the local authority;
(4) No further modification of the plan will be allowed except wherever the
owner(s) of the Building site(s) desires to amalgamate or subdivide the
building sites in the layout/Sub-division Plan as applicable under these
regulations. The applicant shall obtain prior permission for such
3340 , 19 2025 ¨sÁUÀ 4J
Amalgamation or Subdivision by the Director or the sub ordinate officer
authorised by the Director as specified under regulation......
(5) ............................ (such other conditions)
Three copies of the technically approved Final Single plot /sub-division/layout
plan for final sanction are enclosed with the order.
The Jurisdictional Chief Officer/PDO of the Local Authority
Office Seal
To
Copy, with a plan, for information and necessary action to:
(1) Director/Addl Director/Joint Director/Assistant Director
(2) The Applicant, Address…..
(3) Jurisdictional Sub-Registrar, for registering the released building sites
Previous and next
Questions people ask
Is form XI of the Karnataka Town and Country Planning (Development of Land in areas other than Local Planning Areas) Regulations, 2025. still in force?
No repeal of the Karnataka Town and Country Planning (Development of Land in areas other than Local Planning Areas) Regulations, 2025. is recorded.