Form C (CHB (U) Rule 11.2.2), The Chandigarh Energy Conservation Building Code Rules, 2024.: FORM C (CHB (U) Rule 11.2.2)
The Chandigarh Energy Conservation Building Code Rules, 2024. - Form C (CHB (U) Rule 11.2.2)
Text of form C (CHB (U) Rule 11.2.2)
FORM C (CHB (U) Rule 11.2.2)
FORM C (CHB (U) Rule 11.2.2)
Specifications of material
The materials to be used in the construction to be clearly specified under the following heads: -
Items Specification
a) Foundations
b) Walls
c) Damp-Proof Course
d) Floors
e) Roofs
f) Windows and Doors and other Woodwork
g) Steel work
h) Internal Finish
i) External Finish.
Energy Efficiency Parameters of following as mentioned in CHECBC 2024:
(a) Light (wattage/Lumens/LPD)
(b) Air Conditioning (ISSER Value)
(c) Fan (wattage/swapping value)
(d) Heating Equtrialt
(e) Pumps (Star Rating)
(f) Energy Efficient Motors (I.E. value)
(g) Transformer (Star Rating)
(h) Diesel Generators (Star Rating)
(i) Renewable Energy Systems
Signature of Applicant
Signature of Third-Party Assessor Signature of Architect
*Strike out whichever is not applicable
CHD. ADMN. GAZ., MARCH 20, 2024 (PHGN. 30, 1945 SAKA) 615
This is Digitally Signed Gazette. To verify, visit :
https://egazette.chd.gov.in
Application Form-D (Rule 11.3.4 CBR-2017)
Notice of Completion/ Permission to Occupy and for grant of permission for Sewer Connection
(above 2 Kanal for all categories).
To
The Chief Administrator,
Chandigarh Administration,
UT, Chandigarh.
Subject: For Completion/ Permission to Occupy through Self Certification for House/Plot No.
________, Sector/ Industrial Area__________, Chandigarh. (File No...................... )
Sir / Madam,
We hereby give you notice that the building described below and a part of the building
House/Plot No.______________, Sector/Industrial Area, Chandigarh, sanctioned under self-certification scheme
has been completed on________________________in all respects according to the sanctioned plans and as
per building Rule-11.3.4 of CBR-2017.
1. Completion certificate from the Architect who supervised the sanitary installation works of the
building/Third Party Accessor who supervised the CHECBC 2024 norms throughout
construction process. is submitted herewith (in form E Rule 11.3.4 of CBR 2017).
2. The detail of sanctionable violations from the approved plan has been shown in the completion/ as
built drawings and photographs of front, side, rear setbacks, front and rear elevation and essential
areas like cut-outs and shafts from the roof top of the building as required has been uploaded.
3. The debris and rubbish consequent upon the construction has been cleared from the site and its
surrounding.
Signature
Name & address of the owner/(s)
Phone No.
Signature Signature Signature
Third Party Accessor
(Chandigarh ECBC) Structure Engineer Architect
Name Name Name
Address Address Address
Phone No. Phone No. Phone No.
*Strike out whichever is not applicable
616 CHD. ADMN. GAZ., MARCH 20, 2024 (PHGN. 30, 1945 SAKA)
This is Digitally Signed Gazette. To verify, visit :
https://egazette.chd.gov.in
Previous and next
All provisions of The Chandigarh Energy Conservation Building Code Rules, 2024.
Questions people ask
Is form C (CHB (U) Rule 11.2.2) of the Chandigarh Energy Conservation Building Code Rules, 2024. still in force?