Text of regulation 4

Power Procurement under Section 63 of the Act

4. Power Procurement under Section 63 of the Act :– Tariff for all power procurement under long term, medium term not covered in Regulation 3 and HP-DAM (High Price Day Ahead Market) shall be discovered through competitive bidding route with prior approval of the Commission for the requirement of such capacity to be bid in pursuance to Section 86 (1)(b) of the Act. Further, any deviation from TBCB guidelines shall require prior approval of the Commission. PART-B TRANSMISSION

Previous and next

All provisions of Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023

Questions people ask

Is regulation 4 of Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023 still in force?

No repeal of Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023 is recorded.