Regulation 4, Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023: Power Procurement under Section 63 of the Act
Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023 - Regulation 4
Text of regulation 4
Power Procurement under Section 63 of the Act
4. Power Procurement under Section 63 of the Act :–
Tariff for all power procurement under long term, medium term not covered in Regulation 3 and
HP-DAM (High Price Day Ahead Market) shall be discovered through competitive bidding route with
prior approval of the Commission for the requirement of such capacity to be bid in pursuance to
Section 86 (1)(b) of the Act. Further, any deviation from TBCB guidelines shall require prior approval
of the Commission.
PART-B
TRANSMISSION
Previous and next
Questions people ask
Is regulation 4 of Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023 still in force?
No repeal of Uttar Pradesh Electricity Regulatory Commission (Modalities of Tariff Determination) Regulations, 2023 is recorded.