Rule 4, Assam Public Procurement Rules, 2020: Matters to be included in Procurement Plan
Assam Public Procurement Rules, 2020 - Rule 4
Text of rule 4
Matters to be included in Procurement Plan
4. Matters to be included in Procurement Plan :-
(1) The procurement plan shall, in addition to the provisions contained in sub-clause
(vi) of clause (b) of sub-section (4) of section 5 of the Act, also set forth and clearly
indicate the following:-
(a) Nature of Procurement – Goods, Works or Services;
(b) Purpose and objective of the Procurement;
(c) Its essentiality for public purposes;
(d) Major Specifications– Quantity, Type, Quality, configuration, scope, etc.;
(e) Estimated value;
(f) Details of source of Funds;
(g) Procurement method, with specific reasons, if other than Open Competitive
Bidding;
(h) The specific limitation on participation of bidder, if Limited Bidding is
proposed;
(i) The time-frame for Bid Process; and
(j) In case of works (including software development), the time-frame for
completion to assess requirement of fund in subsequent financial years or, in
case of goods or services, the time-frame for delivery.
(2) The concerned procuring entity shall update its procurement plan as per the approved
budget allocations and submit it to the concerned Administrative Department
5
immediately on receipt of Budget Communication from Finance Department as per
the clause (a) of sub-section (4) of section 5 of the Act. The plan, after approval of
the Administrative Department, shall be uploaded in the State Public Procurement
Portal and the Departmental website by the procuring entity within seven days from
the date of such approval. The Finance Department may, however, relax this
condition, if deemed necessary, in case of lack of capacity at the level of procuring
entities:
Provided that the Finance Department may issue guidelines regarding the
institutional mechanism for preparation and approval of procurement plans at various
levels from time to time.
(3) The Budget Communication of Finance Department shall be deemed to have been
received on the day on which it is uploaded in the website of Finance Department, if
not received earlier otherwise.
(4) Any further update of the procurement plan, made with the approval of the
Administrative Department pursuant to sub-clause (c) of sub-section (4) of section 5
of the Act, shall also be uploaded in the State Public Procurement Portal and the
Departmental portal within seven days from the date of such approval by the
Administrative Department.
(5) Notwithstanding anything contained in these rules, approvals of procurement plans
by the other competent authorities like Governing Bodies, Boards, etc. shall be
obtained as due under existing rules, Articles, Bye laws, due procedure, etc. in cases
of procurement entities under clauses (b) to (f) of sub-section (2) of section 3 of the
Act.