Rule 12, THE UTTAR PRADESH GROUND WATER (MANAGEMENT AND REGULATION RULES, 2020: Application Fee
THE UTTAR PRADESH GROUND WATER (MANAGEMENT AND REGULATION RULES, 2020 - Rule 12
Text of rule 12
Application Fee
12. Application Fee. -
(1). Any applicant under sub rule (1), sub rule (2) or sub rule (6) of
rule 11 shall deposit such amount of fee as decided by State
Ground Water Management and Regulatory Authority.
8
(2) The application fee referred to in sub-rule (1) shall be paid online
and shall be deposited in Ground Water fund, created by State
Government.
CHAPTER – IV
Grant of Authorization/No-objection
Procedure, time
limits, format,
fee and other
provisions,
terms and
conditions for
the grant of
Authorization/
No-objection
certificate for
users in Non-
notified areas.
13 (1) Any future or existing user, under sub clause (1) of rule 6,
who does not have No Objection Certificate issued by Central
Ground Water Authority or by Ground Water Department, Uttar
Pradesh shall make, in Form 8(A), an application to the District
Ground Water Management Council for issuance of grant of
Authorization/ No-objection certificate.
(2) Form 8(A) shall be downloaded free of cost from the online
web portal www.upgwdonline.in.
(3) Such forms as are not duly filled or not enclosed with
documents specified in Form 8(A) shall be liable to be rejected.
Procedure for
renewal of No-
objection
Certificate.
14 (1) Any existing Commercial or Industrial or Infrastructural or bulk
user, who has sunk a well for extracting or using ground water in
notified or non-notified area, and have valid No Objection
Certificate issued by the Central Ground Water Authority or the
Ground Water Department before the date of commencement of
the Act, and desires to continue extraction of ground water, shall
make an application in Form 8(B).
(2) A user, having pre-existing right of ground water, shall apply for
renewal of No-objection after one year from the date of
commencement of the Act or on the expiry of the validity of
existing No-objection Certificate, whichever is earlier.
Disposal of
application for
grant of
Authorization/
No-objection
certificate by
District Ground
Water
Management
Council
15 (1) On receipt of the application under rule, 13, if, the District
Ground Water Management Council considers that the application
is for issuance of grant of Authorization/ No-objection certificate
under section 14, it may grant Authorization/ No-objection
certificate in Form 8(C) to the user and if the concerned District
Ground Water Management Council is not satisfied with the case,
it shall refuse to issue certificate of grant of Authorization/ No-
objection and shall intimate accordingly to the user in Form 8(D).
(2) Application as received above shall be disposed by District
Council in accordance to the provisions of rules within thirty days
of receiving of application, otherwise it shall deemed to be issued.
In case it is found that the NOC issued as above in not in
accordance to the provisions of Rule/ Act, State Ground Water
Management and Regulatory Authority shall take appropriate
action by fixing the responsibility of the person found guilty.
(3) Authorization/ No-objection certificate, issued under sub
rule(1) shall be valid for a period of five years. In case of violation
9
of any of the condition of the No objection certificate or change in
ground water status of the area, State Ground Water Management
and Regulatory Authority shall have the right to either cancel the
NOC or impose restrictions as the Authority find appropriate.
(4) On receipt of the application under rule, 14, District Ground
Water Management Council shall forward the application to
Ground Water Department for technical comments. On
recommendation of Ground Water Department, District Ground
Water Management Council, may renew Authorization/ No-
objection certificate in Form 8(E) for such period as may be
recommended by Ground Water Department.
(5) Users, whose application for grant of Authorization/ No-
objection have been rejected under sub rule (1), may prefer an
appeal to State Ground Water Management and Regulatory
Authority within thirty days from the date of receiving of the order.
(6) Any decision taken by the concerned District Ground Water
Management Council, under this rule regarding grant or refusal of
certificate of Authorization/No-objection Certificate shall be
intimated to the user by registered post with due
acknowledgement and electronically, within a period of thirty days
from the date of the receipt of such application.
Provided that the user may receive the copy of the
intimation by hand from the office of the concerned District
Ground Water Management Council
Registers for
certificate of
Authorization/
No-objection
Certificate.
16. Every District Ground Water Management council shall maintain
separate register for issuing certificate of Authorization/No-objection
Certificate.
Application
Fee for grant
of
Authorization/
No-objection
17. (1). A Commercial or Industrial or Infrastructural or bulk user
shall deposit such amount of fee as may be decided by the State
Ground Water Management and Regulatory Authority for filing
application for obtaining certificate of Authorization/No-objection
Certificate for sinking a new well referred to in sub-rule (1) of rule 13.
The State Ground Water Management and Regulatory Authority
10
Certificate and
Fee for ground
water
extraction/dra
wl.
may review the amount of fee for different category of users of
ground water time to time.
(2). After grant of authorization on an application referred to in sub-
rule (1) of rule 13, an annual amount of fee for ground water
extraction, as provided under section 16 of the Act shall be
deposited annually by such user. Amount of fee for ground water
extraction shall be determined by the State Ground Water
Management and Regulatory Authority. The State Ground Water
Management and Regulatory Authority may review the amount of
fee of extraction for different category of users of ground water, time
to time.
(3) The fee referred to in sub-rule (1) and sub rule (2) shall be paidin
such manner as prescribed in form 8(A) and shall be deposited in
Ground Water fund.
CHAPTER – V
Identification and Demarcation of Notified areas
Procedure for
Demarcation of
Notified Areas
and Issuance of
Notification for
the purpose of
Act
18. Identification and demarcation of areas to be declared as
Notified Areas, - in the manner -
(1) Rural Areas: Under the provisions of the Act, for the purpose
of demarcation of the Notified Areas, the over-exploited and critical
blocks shall be considered. The Ground Water Department,
therefore, shall identify and prepare the district wise list of blocks
categorized as over-exploited and critical blocks, based on the
latest ground water resource assessment report.
(2) Urban Areas: In the Urban sector, as provided in the Act, the
stressed areas where ground water levels have depleted to
critical/alarming levels shall be considered for the purpose of
declaring such areas as Notified Areas. The Ground Water
Department shall identify and delineate those urban areas as
stressed, where ground water levels have recorded a significant
decline of more than 20 cm per year during the last five years.
(3) The Ground Water Department shall submit the list of over-
exploited and critical blocks and the stressed urban areas to the
State Ground Water Management and Regulatory Authority for
notifying the said areas, as provided in the Act.
19. Issuance of Notification, -
(1) The State Ground Water Management and Regulatory
Authority shall have necessary consultations on the inputs provided
11
by the Ground Water Department related to Over-exploited and
Critical blocks categorized as per the latest Ground Water
Resource Assessment and the Stressed Urban areas identified by
the Department on the basis of analysis of ground water depletion.
(2) The Authority, thereafter, shall advice the State Government to
declare by Notification such areas as Notified Areas for the purpose
of implementation of different provisions of the Act. On the basis of
recommendation of Ground Water Department, the State Ground
Water Management and Regulatory Authority shall also advice
State Government to discontinue or redesign such Government
schemes which are directly dependent on ground water extraction.
(3) The State Government shall duly consider the recommendation
and advice of the State Authority for declaration of such areas as
Notified Areas by Notification, in the Gazette.
(4) The notification referred to in sub rule (3)shall be uploaded on
the websites of all concerned departments And shall also be
published in two widely circulated newspapers in the area.
CHAPTER – VI
FIXING LIMIT OF ABSTRACTION OF GROUND WATER FOR COMMERCIAL,
INDUSTRIAL, INFRASTRUCTURAL OR BULK USERS
Process
forfixing of limit
for abstraction
of Ground Water
for Commercial,
Industrial,
Infrastructural
or Bulk users of
ground water
20. (1) For fixing ground water abstraction limit for all the existing
Commercial, Industrial, Infrastructural or Bulk users of ground
water, the Ground Water Department, in consultation with stake
holders, shall submit a proposal to the State Ground Water
Management and Regulatory Authority within one year from the
date of commencement of these rules.
(2) On the basis of proposal submitted by Ground Water
Department, State Ground Water Management and Regulatory
Authority shall fix ground water abstraction limits for all the
Commercial, Industrial, Infrastructural or Bulk users of ground
water.
(3) Ground water abstraction limits fixed under sub rule (2) shall be
written in the registration or authorization certificate/ No-objection
certificate for wells of existing Commercial, Industrial,
12
Infrastructural or Bulk users of ground water in Notified as well as
Non-notified areas and for all the new Commercial, Industrial,
Infrastructural or Bulk users of ground water in Non-notified areas,
as the case may be, for the purpose of Section 15.
CHAPTER – VII
Demarcation and Declaration of Ground Water Quality Sensitive Zones
Process for
Demarcation
and Declaration
of Ground
WaterQuality
Sensitive Zones.
21. Demarcation of Ground Water Quality Sensitive Zone, -
(1)To collect, evaluate and analyze ground water quality data and
related information for the purpose of generating an overview of
the problem, the Ground Water Department shall hold technical
consultations with the expert bodies such as Central Ground Water
Board, Uttar Pradesh Jal Nigam, Central and State Pollution
Control Boards, Indian Institute of Toxicological Research, National
Institute of Hydrology, IITs and also those Institutions, which have
conducted area specific ground water quality studies, for providing
the existing data, reports and information on ground water quality
for both rural and urban segments of Uttar Pradesh.
(2) Based on the evaluation, analysis and mapping of such
available data, the Ground Water Department shall proceed to
generate and develop a comprehensive quality data base for the
entire state. Subsequently, the department shall identify those
areas which are found affected with poor ground water quality
along with risk of pollution hazards on drinking and irrigation water
supplies. Such areas shall be demarcated and mapped as Ground
Water Quality Sensitive Zones.
(3)The department shall prepare a detailed district wise list of
such Ground Water Quality Sensitive Zones with their GPS
locations.
(4) The complete information on ground water quality for the entire
state shall be submitted to the State Ground Water Management
and Regulatory Authority for onward action, with the objective to
ensure protection of ground water quality in such delineated zones
through appropriate measures for prevention and control of
pollution and finding safe quality areas for potable water supplies.
(5) State Ground Water Management and Regulatory Authority
shall take immediate action and will issue directions to concerned
departments to change or redesign their existing policies or
13
schemes to ensure protection of ground water quality in such
delineated zones. All concerned departments shall have to change
or redesign their existing policies or schemes in such delineated
zones.
(6) After issuance of direction in sub rule (5), if District Ground
Water Management Council finds that any particular scheme of any
department is responsible for pollution of ground water in that
district, the Council in such cases shall immediately take action in
consonance with the provision of the Act and also shall submit a
case to State Ground Water Management and Regulatory
Authority.
Issuance of
Notification for
Ground Water
Quality
Sensitive
Zone, -
22 (1) The State Ground Water Management and Regulatory
Authority shall, after having necessary technical consultations on
the information provided by the Ground Water Department
regarding ground water quality of the state, recommend and advice
the State Government to declare by Notification such areas as
Ground Water Quality Sensitive Zones for the purpose of the Act.
(2) The State Government shall duly consider the advice and
recommendation of the State Authority for declaration of Ground
Water Quality Sensitive Zones in the State and issue a Notification,
both in Hindi as well as English language under the sub section (1)
of the section 24. The notification shall also contain the directions
of the State Government for the notified area.
(3) The Notification shall be published in the Gazette and
Subsequently as Public Notice in at least three daily regional
newspapers through the Information Directorate, U.P.
(4) Apart from the publication in the newspapers, the
Notification shall also be uploaded on the websites of all concerned
departments for wide circulation.
CHAPTER – VIII
PROCESS FOR FIXING STANDARDS OF TREATED WASTE WATER
AND
14
PROCEDURE FOR INSTALLATION OF TREATMENT PLANT
Process for
fixing standards
of treated waste
water.
23. (1)On the direction of the State Ground Water Management
and Regulatory Authority, the Ground Water Department, in
consultation with Central Ground Water Board, Central and State
Pollution Control Boards, Uttar Pradesh Jal Nigam shall submit a
proposal to it for approval of standards for treated waste within
such time as may be directed by the said Authority.
(2) On the basis of proposal submitted by Ground Water
Department, State Ground Water Management and Regulatory
Authority shall approve standards for treated waste water.
(3) State Ground Water Management and Regulatory Authority
shall issue direction to each District Ground Water Management
Council for compliance of approved standard while granting No-
objection to user of ground water.
Procedure for
installation of
treatment plant.
24.(1) The State Ground Water Management and Regulatory
Authority shall ensure through District Ground Water Management
Councils that all Commercial, Industrial, Infrastructural or Bulk
users of ground water that pollute ground water or surface water,
will install treatment plants within a period of two years from the
date of commencement of these rules.
(2) Each District Ground Water Management Council shall conduct
physical verification of all Industries in the district thereof, within a
period of one year from the date of commencement of these rules.
(3) On the basis of report of physical verification, the District
Ground Water Management Council shall prepare a list of those
industries, which have not constructed appropriate treatment plant.
(4) List of each district as prepared under sub rule (3) shall be
submitted to the State Ground Water Management and Regulatory
Authority.
(5) The State Ground Water Management and Regulatory Authority
shall direct the industries referred to in sub rule (4) that the
industries which have not installed appropriate treatment plants
shall install the said plant within a period of six months from the
date issuance of the direction.
(6) After end of six-month period of direction under sub rule (5),
15
each District Ground Water Management Council shall again
conduct physical verification of all Industries in concerning districts
in two months period. On the basis of report of physical verification,
District Ground Water Management Council shall again prepare a
list of those industries, which have not complied to the direction
issued by State Ground Water Management and Regulatory
Authority under sub rule (5).
(7) List of each district as prepared under sub rule (6) shall again
be submitted to State Ground Water Management and Regulatory
Authority.
(8) State Ground Water Management and Regulatory Authority
shall take action against such user of ground water, who still fails to
set up treatment plant within the said period, by:
(i) issue order for construction of necessary treatment plant
at such user’s cost by the agency identified by the State
Ground Water Management and Regulatory Authority;
(ii) direct District Ground Water Management Council of
concerning district to issue order for start of prosecution
under the provisions of sub-section (2) of section 39 of the
Act.
Procedure for
restrictions for
discharging
untreated
effluent into
ground water or
surface water.
25. (1) State Ground Water Management and Regulatory Authority
shall monitor through Appropriate Authorities that,-
(a)no Government department/ undertaking/ Corporation, etc.
discharge untreated effluent into ground water or surface
water.
(b)no untreated nala or sewer. etc are directly discharged into
rivers/ ponds/ lakes or any groundwater or surface water.
(2) Each District Ground Water Management Council shall
conduct physical verification for process of effluent discharge
adopted by such Government bodies as provided under sub rule
(1), within a period of one year from the date of commencement of
these rules.
(3) On the basis of report of physical verification, District Ground
Water Management Council shall prepare a list of the Government
bodies referred to in sub rule (1), which have not adopted
appropriate process for treating effluent and are directly
16
discharging untreated effluent into ground water or surface water.
(4) List of each district as prepared under sub rule (3) shall be
submitted to State Ground Water Management and Regulatory
Authority.
(5) The State Ground Water Management and Regulatory Authority
shall issue such instructions to Government bodies referred to in
sub rule (4), so as to ensure:
(a) the construction of appropriate treatment plants within one
yearfrom the date of issuance of the said instruction, or
(b)to make functional the existing treatment plants within six
monthsfrom the date of issuance of the said instruction.
(6) At the end of period specified under sub rule (5), each District
Ground Water Management Council shall again conduct physical
verification of those Government departments/ undertakings/
Corporations/ bodies, etc. which have not yet adopted appropriate
process for treating effluent and are still directly discharging
untreated effluent into ground water or surface water, within two
months.
(7) List of those Government bodies, who have not complied to the
advisory issued by State Ground Water Management and
Regulatory Authority under sub rule (6) shall be submitted to State
Ground Water Management and Regulatory Authority for action.
CHAPTER – IX
RAIN WATER HARVESTING
Process of
imposing
provisions for
rain water
harvesting.
26. (1) Appropriate Authorities shall ensure that Rain Water
Harvesting Structures have been properly constructed by all users
having plot area of 300 square meters or more. Installation of rain
water harvesting structures shall be made compulsory for different
users in phases, described hereunder.
Provided that-;
Installation of Rain Water Harvesting Structures shall be
compulsory for every such user, who have submersible pump
or any similar ground water extracting device for extraction of
ground water in his or her premises.
(2) In first phase, every Government Department/ Semi-
17
Government Department/ Authorities/ Aided Institutions/ Public
Sector Undertaking (either fully or partially funded by Government),
Private Institutions or Organizations, having plot area of 300
square meters or more, or who are extracting ground water
through submersible pumps or similar devices, shall also ensure
that Rain Water Harvesting Structures have been properly
constructed in their premises within a period of two years from the
date of commencement of the Act.
(3) In second phase (after one year of first phase), every user
other than those mentioned in sub rule (2), having plot area of 300
square meters or more, or who are extracting ground water
through submersible pumps or similar devices, shall also ensure
that Rain Water Harvesting Structures have been properly
constructed in their premises,withinone yearof end of first phase.
(4) After installation of Rain Water Harvesting Structures, every user
shall inform online on web portal www.upgwdonline.in.
(5) If such user under sub rule (2) and sub rule (3), fails to do so, he
or she or concerning body shall be punished in such manner and
with such punishment as may be determined by the State Ground
Water Management and Regulatory Authority.
(6) Besides punishment referred to in sub rule (5), submersible
pump or any other ground water extracting device shall
immediately be disconnected, sealed and seized by the Municipal
Water Management Committee.
(7) Area-specific design of Rain Water Harvesting Structures and
quantum of recharge shall be decided by State Ground Water
Management and Regulatory Authority. Such designs shall also be
made available online.
(8) Ground Water Department shall also circulate list of competent
technical persons, who shall provide necessary technical
assistance for installation of appropriate Rain Water Harvesting
Structures.
(9) Appropriate Authorities shall organise training programs for
demonstrating rain water harvesting techniques. Appropriate
18
Authorities shall also invite different non-government organisations
to participate in such training programs.
(10) Appropriate Authorities shall also conduct awareness
campaign to sensitize different users for rain water harvesting.
(11) State Ground Water Management and Regulatory Authority
shall also ensure that all concerning Institutions like ‘All India
Council of Technical Institution’, ‘Medical Council of India’,
University Grants Commission, or similar bodies shall include
installation of appropriate rain water harvesting structure into their
building norms while issuing No Objection Certificate.
(12) District Ground Water Management Council shall also issue
direction to concerning implementing department to rejuvenate the
defunct wells for water harvesting work.
(13) Appropriate Authorities shall also issue direction to
concerning implementing department to take appropriate actions
for water harvesting, viz., reuse the surplus drawl water of hand
pumps, etc.in urban and rural areas.
CHAPTER – X
COMPOUNDING OF OFFENCES
Process of
Compounding of
offence.
27. The application for compounding of an offence shall be made in
the form appended as appendix (B) to these rules.
CHAPTER – XI
GRIEVANCE REDRESSAL
Process of
Grievance
Redressal
28.(1) Any aggrieved person may submit his or her grievance with
sufficient justification online at web portal www.upgwdonline.in on
issues referred to in sub-section (2) of section 43 of the Act.
(2) The District Ground Water Grievance Redressal Officer may if
require issue notice to the alleged user to submit his or her
explanation within a period of thirty days from the receipt of
grievance application.
(3) The alleged person shall submit his or her explanation to
District Ground Water Grievance Redressal Officer, within a period
of thirty days of receiving notice.
19
(4) District Groundwater Grievance Redressal Officer shall decide
the grievance and communicate his or her decision to the
aggrieved person within thirty days of receiving of explanation of
alleged user.
(5) The aggrieved person may prefer an appeal against the decision
of the District Ground Water Grievance Redressal Officer to the
State Ground Water Management and Regulation Authority within
thirty days from the date of receipt of the decision of the District
Ground Water Grievance Redressal Officer.
CHAPTER – XII
MISCELLANEOUS
Other
provisions.
29. (1) District Ground Water Management Council shall identity
such existing Government schemes which either encourage
excessive ground water drawl or have adverse impact on water
quality of that area.
(2)District Ground Water Management Council shall submit
proposal for revisiting such schemes to State Ground Water
Management and Regulatory Authority.
(3) State Ground Water Management and Regulatory Authority
shall take immediate action and will issue directions to concerned
departments to change or redesign their existing policies or
schemes. All concerned departments shall have to change or
redesign their existing policies or schemes in such delineated
zones.
30. Anything, which has not been provided in these rules shall be
put before State Ground Water Management and Regulatory
Authority. Decisions, in such cases shall be taken in consonance
with the provisions of Act, and communicated accordingly.
20
(Anurag Srivastava)
Principal Secretary
Appendix (A)
[See rule 4]
(Qualification of non-official members of Appropriate Authorities)
S. No. Members referred to in Rule 3 Qualification
1. Members of Gram Panchayat
Ground Water Sub Committee,
referred to in clause (e) of sub-
section (2) of section 3.
Block Development officer of respective
block shall nominate one representative
from Minor irrigation department and
one representative from Agriculture
Department.
2. Members of Block Panchayat
Ground Water Management
Committee referred to in clause
(e) of sub-section (2) of section
4.
District Magistrate of respective district
shall nominate one representative from
Minor irrigation department and one
representative from Agriculture
Department.
3. I. Two members of
Municipal Water
Management Committee
referred to in sub clause
(c) of sub-section (2) of
section-5.
District Magistrate shall nominate two
members having field knowledge of
water resources in the state of Uttar
Pradesh.
21
II. Two members of
Municipal Water
Management Committee
referred to in sub clause
(d) of sub-section (2) of
section-5.
District Magistrate shall nominate two
members of Resident Welfare
Associations/ Social Groups.
III. Three members of
Municipal Water
Management Committee
referred to in sub clause
(e) of sub-section (2) of
section-5.
District Magistrate of respective district
shall nominate one representative from
Ground Water Department, one
representative from Minor Irrigation
department and one representative from
Agriculture Department.
4. I. One subject expert as
member of District
Ground water
Management Council
mentioned in clause (c)
of sub-section (2) of
section-6.
District Magistrate shall nominate one
subject expert having Masters degree in
Earth Sciences or Graduate in Civil/
Mechanical Engineering as well as
minimum ten years of experience in
ground water management in the state
of Uttar Pradesh.
II. One member referred to
in clause (d) of sub
section (2) of section-6.
District Magistrate shall nominate one
eminent person from Public/Non-
Government Organization/ Social
Sector.
5. I. Three subject experts as
members of State
Ground Water
Management and
Regulatory Authority
referred to in serial
number 16 of sub-
section (2) of section-7.
State Government shall nominate three
subject experts as,-
I. One Environmental Expert,
having Masters degree in Earth
Sciences/ Environmental science
as well as minimum fifteen years
of experience in ground water
management or pollution control;
II. One Ground Water Chemist,
having Masters degree in
Chemistry as well as minimum
22
fifteen years of experience in the
field of testing, analysis and
interpretation of ground water
quality;
III. One Ground Water Expert,
having Masters Degree in Earth
sciences or Graduate Degree in
Civil/ Mechanical Engineering as
well as minimum fifteen years of
experience in the field of ground
water exploration and
management related to different
hydrogeological conditions of
Uttar Pradesh.
II. One eminent person
from Public/Non-
Government
Organization/Social
Sector referred to in
serial number 17 of sub
section (2) of section-7.
State Government shall nominate one
eminent person from Public/Non-
Government Organization/Social Sector.
23
Appendix (B)
[See rule 27]
(Format of Applicationfor Compounding of an Offence)
S.No. Particulars Remarks
1 Name of the applicant
2 Offences committed u/s *
3 Status of case (i.e. whether
contemplated/pending in
Court/convicted/acquitted
4 Particulars of offences along-with
justification for compounding (separate
sheet)
5 Whether the applicant has paid the
amount of penalty and any other sum due
relating to the offence?
6 Whether the applicant undertakes to pay
the compounding charges as shall be
intimated by the compounding officer?
7 Whether similar offences in the case of
the applicant have been compounded
earlier. If yes, how many times?
8 Whether the application is for
compounding of first offence referred to in
Section 41?
9 Whether the applicant was convicted by a
court of law for the offence sought to be
compounded
24
DECLARATION BY THE APPLICANT
I do hereby declare that the particulars furnished herein above are correct and true. I
understand that in case any of the information and particulars is found to be in correct at any
stage of scrutiny and investigation or thereafter, my application is liable to be rejected
Icancelled.
Note:
1. Separate application form should be filled for every offence.
2. The application form should be completed in all respect before submission. Incomplete
applications are liable for rejection. Any correctionIalteration shall be duly authenticated.
3. In case any of the particulars/information is found to be incorrect at any stage of
verificationIscrutiny, the application is liable for rejection.
6. Please attach the following documents along with the application:
(a) Document showing proof of ownership of land;
(b) Photocopy of Aadhaar card / voter IDIration card Iany other proof of identification
(c) Notice issued by District Ground Water Management Council against offence
committed by the applicant.
7. The compounding Officer reserves the right to ask for any other document(s) from the
owner applicant for examination of the merit of the case.
Place
Signature…………………… Date
Current
address………………………
……
* Offence for which compounding is sought
I agree
I agree
25
Previous and next
All provisions of THE UTTAR PRADESH GROUND WATER (MANAGEMENT AND REGULATION RULES, 2020
Questions people ask
Is rule 12 of THE UTTAR PRADESH GROUND WATER (MANAGEMENT AND REGULATION RULES, 2020 still in force?
No repeal of the UTTAR PRADESH GROUND WATER (MANAGEMENT AND REGULATION RULES, 2020 is recorded.