Rule 8B, The Karnataka Industries (Facilitation) (Amendment) Rules, 2020: Procedure for grant of acknowledgement certificate
The Karnataka Industries (Facilitation) (Amendment) Rules, 2020 - Rule 8B
Text of rule 8B
Procedure for grant of acknowledgement certificate
8B. Procedure for grant of acknowledgement certificate.- (1) Every
manufacturing enterprise or manufacturing industry seeking acknowledgement certificate
shall first obtain approval for the project from the State High Level Clearance Committee or
State Level Single Window Clearance Committee or District Single Window Clearance
Committee and then furnish a duly filled Combined Application Form for obtaining
acknowledgment certificate (CAF) in Form IV, along with relevant fees towards services and
self certification in Form V, electronically on the online portal of the State level Nodal
Agency.
(2) On the receipt of self certification in Form V, the acknowledgement certificate
shall be granted in electronic format by the State Level Nodal Agency for the projects
approved by the State High Level Clearance Committee or State Level Single Window
Clearance Committee and by the District Level Nodal Agency for the projects approved by
District level Single Window Clearance Committee in Form VI, stating the date of receipt of
self certification and the period of validity of acknowledgement certificate.”
4. Amendment of rule 9.- In rule 9 of the said rules, the following shall be inserted at
the end, namely:-
“During the period of validity of the acknowledgement certificate, in instances where
inspections are warranted, the inspection shall be carried out by such officers of the
respective departments in consultation with the nodal agency and approval of the head of
the department concerned.”
5. Insertion of new rule 9A and 9B.- After rule 9 of the said rules the following shall
be inserted, namely:-
“9A. Operationalising the manufacturing enterprise or industry.– (1) The
manufacturing enterprise or industry shall make relevant applications for operationalising
the unit under applicable Acts, rules etc. within six months before the expiry of the
acknowledgement certificate. The acknowledgement certificate issued under sub-section (3)
of section 13 shall be the prerequisite document for getting approvals.
(2) If the applicant fails to operationalise the unit within three years from the date of
issue of acknowledgement certificate, the applicant has to obtain necessary clearances for
setting up or establishment of industry, from the respective departments as per regular
procedure.
Previous and next
← Rule 3Insertion of new rule 8A and 8BRule 9B →Functions of the State Level or District Level Nodal Agency
All provisions of The Karnataka Industries (Facilitation) (Amendment) Rules, 2020