Rule 20, Bihar Electricity Duty Rules, 2020: Provision of meters
Bihar Electricity Duty Rules, 2020 - Rule 20
Text of rule 20
Provision of meters
20. Provision of meters.— Every assessee shall install and maintain separate, suitable and
correct meters or sub-meters to register the quantities of energy generated, distributed, sold or
consumed by him and shall likewise, cause meters to be installed and maintained in the premises of
consumers for the correct registration of the quantities of energy consumed by such consumers:
Provided that where there is a combined meter for registering the quantities of
energy, part of which is dutiable at any rate or at different rates and part is exempt, the
assessee shall cause separate meters to be installed for registering the quantities of the
different types of consumption separately:
Provided further that if any assessee satisfies the inspecting authority that the
installation and maintenance of such separate meters or sub-meters involve costs
disproportionate to the amount of the duty leviable from him and furnishes to the
inspecting authority such data as, are in the opinion of the inspecting authority necessary
for the assessment of the said duty he may assess the duty payable and exempt such
assessee from the requirement of this rule. An assessee exempted under this proviso
shall communicate to the inspecting authority, within 30 days any change in the data on
the basis of which the duty payable by him was assessed.
Previous and next
Questions people ask
Is rule 20 of Bihar Electricity Duty Rules, 2020 still in force?
No repeal of Bihar Electricity Duty Rules, 2020 is recorded.