Rule 16, Bihar Electricity Duty Rules, 2020: Review

Bihar Electricity Duty Rules, 2020 - Rule 16

Text of rule 16

Review

16. Review.— (1) When any authority appointed under the Act, reviews under Section 14 any order passed under the Act, it shall record reasons for doing so. (2) Save with the previous sanction of the Commissioner or an authority specially authorized by him in this behalf, no authority appointed under the Act other than the Commissioner, shall review any such order except before the expiry of twenty four months from the date of passing of the order which is sought to be reviewed. (3) Save with the previous sanction of the Commissioner or an authority specially authorized by him in this behalf, no authority appointed under the Act other than the Commissioner, shall review any order, which has been passed by any of its predecessors in office.

Previous and next

All provisions of Bihar Electricity Duty Rules, 2020

Questions people ask

Is rule 16 of Bihar Electricity Duty Rules, 2020 still in force?

No repeal of Bihar Electricity Duty Rules, 2020 is recorded.