Text of regulation 5
Nodal Agency and its functions
5. Nodal Agency and its functions.—(1) The Himachal Pradesh State Load Despatch
Centre (HPSLDC) shall be the Nodal Agency for all intents and purposes and the overall
coordination of the various activities under these Regulations.
Compendium of HPERC Regulations, March 2021 3
(2) The Functions of the Nodal Agency.—(i) functions related to the preparation of
detailed guidelines for:—
(a) submission of DPRs by the Project Entity(ies) to Nodal Agency and by the
Nodal Agency to the Commission;
(b) processing of appraisal of the schemes;
(c) disbursement and release of funds subject to the provisions of these
regulations;
(d) monitoring of scheme(s) at the execution and operation stage;
(e) cost/time overrun in the execution of scheme(s) and remedial measures to
curb and mitigate the same ;
(f) submission of schemes to the Commission for sanction and submission of
progress reports etc. to the Commission; and
(g) any other item required to complete the intend of the regulations to ensure the
proper implementation of the provisions of these regulations;
(ii) functions related to the scrutiny of the draft schemes:—
(a) the Nodal Agency shall initially scrutinize the proposals received from the
concerned Project Entity(ies) in each quarter for technical suitability duly
keeping in view the eligibility conditions as per regulation 3 of these
regulations;
(b) all the proposals received by it at the end of a quarter shall be scrutinized as
per the prudent practices and submitted, within one month, to the Appraisal
Committee for its suitable directions/recommendations; and
(c) all the proposals received by the Nodal Agency in a quarter shall be
processed in a single lot;
(iii) functions related to submission of the draft schemes to the Commission.—The Nodal
Agency shall submit the self contained draft scheme(s), duly scrutinized and
processed as per clause (ii) above, alongwith the recommendations of the Appraisal
Committee, to the Commission for sanction, soon after the availability of the
recommendations of the Appraisal Committee;
(iv) functions related to monitoring the progress of sanctioned schemes during the
execution stage:—
(a) the Nodal Agency shall monitor the progress of the implementation of the
scheme(s), sanctioned by the Commission as per regulation 7 of these
regulations, on monthly basis based on the progress report to be submitted to
it by the concerned Project Entity implementing the scheme;
(b) to submit the status report, along with the proposed remedial measures if any,
to the Monitoring Committee on a quarterly basis;
(c) to submit to the Commission the progress reports, along with the
recommendations of the Monitoring Committee under sub-regulation (2) of
regulation 8, to the Commission on a monthly basis;
4 Compendium of HPERC Regulations, March 2021
(d) to submit the proposals for revision of the scope of work, sanctioned cost or
the completion targets, along with the recommendations of the Monitoring
Committee under clause (iii) of sub-regulation (2) of regulation 8, to the
Commission; and
(e) to submit proposals, along with the recommendations of Monitoring
Committee, For the release of funds against the sanctioned cost of the
scheme(s) to the Commission;
(v) functions related to monitoring the progress of sanctioned schemes during
operation stage:—
(a) the Nodal Agency shall submit the progress report on a quarterly basis
about the functioning of the schemes during the operation stage to the
Monitoring Committee; and
(b) the Nodal Agency shall also submit, to the Commission, half yearly
progress reports about the functioning of the schemes during
operation stage, along with the details of recommendations, if any,
made by the Monitoring Committee for improving the performance of
such schemes and action taken in this regard; and
(vi) other functions:—
(a) function as Secretariat to the Monitoring Committee and the Appraisal
Committee;
(b) keep the Record of Business transacted at each meeting of the
Appraisal Committee and the Monitoring Committee;
(c) to submit, to the Commission the proposals received by it in a
quarter, along with complete details as well as the recommendations
of the Appraisal Committee, within 15 days from the receipt of
recommendations from the Appraisal Committee;
(d) prepare Annual Report of PSDF; and
(e) perform such other functions as may be assigned by the Commission,
Monitoring Committee and the Appraisal Committee.
Previous and next
Questions people ask
Is regulation 5 of the Himachal Pradesh Electricity Regulatory Commission (Power System Development Fund) Regulations, 2020 still in force?
No repeal of the Himachal Pradesh Electricity Regulatory Commission (Power System Development Fund) Regulations, 2020 is recorded.