7. (1) No piece of land shall be used as a site for the
Building construction of a building, and no building shall be
permissions.
constructed or reconstructed, and no addition or alteration
shall be made to an existing building without the self
certification based declarations or the required approval in
the manner prescribed, relating to the use of building sites
or the construction or reconstruction of buildings:
Provided that the Government may exempt certain
buildings from taking building permission under this section,
in the manner prescribed.
(2) For plot size upto 75 square yards (63 square
meters), and the construction of ground or ground plus one
floor, will not require any permission. The applicant however
need to register online with a token amount of Rs.1 and duly
self certifying his title, the size of the plot and floors, it shall
also not require a completion certificate or occupancy
certificate. Any plot bigger than 75 sq yards cannot be split
for this purpose or this provision cannot be misused for
taking up constructions in government or prohibited or
disputed land and action as prescribed shall be initiated for
violations noticed.
(3) Plot size upto 500 square meters and height upto 10
meters: The permission applications for all the individual
residential buildings having plot area of 500 square meters
and less and building height of 10 meters as specified, shall
be processed through an online based Self-Certification
System in accordance with the Master Plan or Detailed
Planning Scheme or Local Area Plan and the building rules
and in the manner prescribed, and upon furnishing all
required information details shall get instant online approval.
[Act No.12 of 2020] 13
(4) The onus to ensure authenticity of self-certification
and compliance with the self-certification lies with the
applicant, who shall be held personally accountable and
liable in case of false declaration and action shall be initiated
against the said person, as prescribed.
(5) The owner or developer shall along with the building
application form, submit an undertaking that in case of any
actual construction made by him or her in violation of
sanctioned plan, the Government or the Commissioner or
the Agency authorized by him or her shall take-up the
demolition without issuance of any notice. Further, the
District level committee may verify the documents so
submitted, and in case of any misrepresentation or false
statement, the action shall be taken as prescribed.
(6) Citizens shall be encouraged to bring to the notice of
Municipality and District Collector cases where unauthorized
construction or construction in violation of or in excess of
permissions, in the manner prescribed. The identity of such
informers shall be kept confidential. All such cases shall be
examined within a week from such information and
appropriate action initiated. The informant shall be
incentivized in all such cases where the information
furnished by him is found to be correct.
(7) Plot size above 500 square meters and height above
10 meters: There shall be a single window system in case of
applications for building permission in plots of area above
500 square meters and height above 10 meters and all
Commercial Buildings, High Rise Buildings, Group
Development Schemes, Group Housing, Apartment
Complexes, Multiplexes, Non Residential Buildings and
other such constructions, which require multiple NOCs, one
common application form shall be submitted through web
based online system as prescribed.
14 [Act No.12 of 2020]
(8) The online application has to be submitted with all
requisite documents as may be prescribed. The online
system shall not accept the application unless all such
documents are submitted. Such documents upon
submission shall be examined by the single window
committee set up for this purpose and shortfalls or
incompleteness or cases where further information or
clarification is needed shall be communicated to the
applicant within 10 days from the date of applying, in such
manner, as may be prescribed.
(9) In all other cases, the applications for building
permissions accompanied by all valid and required
documents, as required and prescribed, shall be sanctioned
within 21 days and in such manner, as may be prescribed.
(10) If no order is issued on the building application
within the time prescribed, then the approval will be deemed
to have been issued, as may be prescribed. The official
concerned shall be liable for disciplinary action, if there has
been a delay in arriving at a decision within the time period.
(11) The permission issued under deemed clause can
be revoked by the commissioner within 21 days from the
date of deemed approval if it is found that deemed approval
has been obtained by mis-representation of the facts or
false statements, and/or against the building rules,
regulations and Master Plan land use provisions.
Occupancy
Previous and next
Questions people ask
Is section 7 of the Telangana State Building Permission Approval and Self Certification System (TS-bPASS) Act, 2020. still in force?
No repeal of the Telangana State Building Permission Approval and Self Certification System (TS-bPASS) Act, 2020. is recorded.