Rule 55, Tamil Nadu Combined Development and Building Rules, 2019: Storm Water Drainage
Tamil Nadu Combined Development and Building Rules, 2019 - Rule 55
Text of rule 55
Storm Water Drainage
55. Storm Water Drainage.— (1) Storm water drainage system in a site shall be designed
in such a way to harvest cent percent of it to recharge ground water table below. The
design factors of rain water harvesting structures within a site shall include type of soil
and its absorption capacity, ground slope, intensity and duration of rain fall for the
design period etc. However there shall also be a provision for carrying any excess storm
water which was not absorbed during an exceptional rain fall, to drain or discharge into
the street or public storm water drainage system.
(2) No existing natural or man-made drainage system such as channel, canal, nallah
etc. passing through the site shall be closed. When it is realigned within the site
optimizing the usability of the site, due care shall be taken that its carrying
capacity or velocity of flow is not reduced affecting the upstream and downstream
sites and such a realignment shall be done only with prior approval of
the Competent Authority and concerned agencies
Previous and next
← Rule 53Exit RequirementsRule 56 →Electrical and Allied Installations (Including lightening protection of buildings)
All provisions of Tamil Nadu Combined Development and Building Rules, 2019
Questions people ask
Is rule 55 of Tamil Nadu Combined Development and Building Rules, 2019 still in force?
No repeal of Tamil Nadu Combined Development and Building Rules, 2019 is recorded.