Rule 20, Tamil Nadu Combined Development and Building Rules, 2019: Application for Completion Certificate
Tamil Nadu Combined Development and Building Rules, 2019 - Rule 20
Text of rule 20
Application for Completion Certificate
20. Application for Completion Certificate.— (1) For all buildings except residential
building upto 12m in height not exceeding 3 dwelling units or 750 sq.m and all type of
Industrial buildings, the Applicant or Owner or Power of Attorney Holder or Registered
Developer and any other Person who is acquiring interest shall submit a completion
TAMIL NADU GOVERNMENT GAZETTE EXTRAORDINARY 25
report in Form 5 along with Form 6, 7 and 8 in Annexure - XIV, to obtain Completion
Certificate, certifying that the building has been completed as per the approved plan,
from the competent authority that has issued Planning Permit before getting service
connections such as electric power connection, water supply sewerage connection. These
service connections shall be given by the service provider to these buildings only after
the production of the Completion Certificate.
(2) The owner or developer shall submit an application to the competent authority in
the first stage after completion of work upto plinth level requesting for issue of order
for continuance of work.
(3) The owner or developer through the registered professional shall submit to the
designated officer of the competent authority a progress certificate in the given
format at the stage of Plinth and last storey level along with structural inspection
report as provided for under sub-rule (2) of rule 9 of these rules.
(4) On receipt of the progress certificate from the owner or registered developer through
the registered professional, the competent authority shall check for any deviation
from the approved plan and convey decision within 7 working days to the owner or
developer for compliance.
(5) If the order of continuance is not issued within 15 days of receipt of the respective
application, it will be taken as deemed to be issued and the owner or developer may
proceed with the construction without any deviation to the approved plan.
(6) The owner or Power of Attorney holder or registered developer or any other person
who has acquired interest shall submit application in complete shape for issue of
completion certificate according to the norms prescribed in Annexure - XXIII to
these Rules.
(7) The competent authority may on its own or through a subordinate official or a
qualified professional inspect or cause to be inspected the work atleast the two
stages of construction viz, plinth level and completion of construction and such
inspection shall include confirmation that,—
(a) the work was executed and the building was completed as per the approved
plan as stated in these rules along with the norms prescribed for issuing the
completion certificate;
(b) it shall be obligatory on the part of the applicant to confirm that certificate of
Lift Inspector has been obtained regarding satisfactory erection of lift; and
(c) it shall also be obligatory on the part of the applicant to confirm the certificate
to the Directorate of Fire & Rescue Services for completion of fire safety
requirements as applicable for the type of building has also been obtained.
(8) If any project consists of more than one detached or semi detached building or
buildings in a building unit and any building or buildings thereof is completed as
per approved plan (such as parking, internal roads, height of the building,
infrastructure facilities, lift and fire safety measures), the competent authority may
issue completion certificate for such detached or semidetached building or buildings
in a building unit.
(9) The completion certificate shall not be issued unless the information is supplied by
the owner, developer, the registered professionals concerned in the schedule as
prescribed by the competent authority from time to time.
(10) The competent authority shall within 30 days from the date of receipt of application
for completion report inform, communicate its decision after necessary inspection
about grant of completion certificate.
26 TAMIL NADU GOVERNMENT GAZETTE EXTRAORDINARY
(11) Connection to the sewer or water mains or electricity:
(a) Temporary connection for water, electricity or sewer, permitted for the purpose
of facilitating the construction, shall not be allowed to continue in the premises
after completion of the building construction.
(b) No connection to the water mains or sewer line or electricity distribution line
with a building shall be made without the prior permission of the authority and
without obtaining completion certificate.
(c) In case the use is changed or unauthorised construction is made, the authority
is authorised to discontinue such services or cause discontinuance of such
service.
Previous and next
All provisions of Tamil Nadu Combined Development and Building Rules, 2019
Questions people ask
Is rule 20 of Tamil Nadu Combined Development and Building Rules, 2019 still in force?
No repeal of Tamil Nadu Combined Development and Building Rules, 2019 is recorded.