6. Application for Planning Permission and Building Permit.— (1) For the purpose of
obtaining planning permission or building permit, the applicant who should be the
owner of the land or leaseholder or power of attorney holder who has right over the land
to develop, shall submit an application on-line in the prescribed Form to the competent
authority.
(2) The following operational constructions and installations of Government, whether
temporary or permanent, which are essential for the operation, maintenance,
development or execution of any of the following services are exempted from
applying under these Rules;-
(i) Railways;
(ii) National Highways;
TAMIL NADU GOVERNMENT GAZETTE EXTRAORDINARY 13
(iii) National Waterways;
(iv) Major ports;
(v) Airways and Aerodromes;
(vi) Posts & Telegraphs, Telephone, Wireless, Broadcasting and other like forms of
communications;
(vii) Regional grid for Electricity;
(viii) Defence;
(ix) Metro Rail and
(x) Minor ports;
(3) The departments or agencies specified in sub-rule (2), which are exempted from
seeking approval, shall send in advance to the competent authority the details of the
development they intend to carry out for information and records of the competent
authority and local body.
(4) When any department of the State government or the Central government other than
those specified in sub-rule (2), intends to carry out development of any land or
building, the officer in charge of the same shall apply in writing in the Form with
necessary documents and plan to the competent authority and obtain clearance for
the intended development complying with these rules.
(5) Government departments are exempted from the payment of scrutiny fee or any
other fee or charge.
(6) The plan submitted under sub-rule (4) shall be prepared by a qualified architect or
engineer and structural aspects of the design shall be certified by a qualified
structural engineer.
(7) An application in Form - A in Annexure - I accompanied by proof of ownership,
plans, specifications, etc., mentioned therein shall be submitted to the competent
authority in case of subdivision or layout or reconstitution or amalgamation of land
for building purposes.
(8) An application in Form - B in Annexure - II accompanied by proof of ownership,
detailed plans, specifications, site plan, key plan and topo plan showing existing
developments to a radius of 100 metres drawn to a scale of 1:500 and such other
details as may be required from time to time shall be submitted to the competent
authority, in the case of development of land and buildings, change of land and
building use and in the case of site approval.
(9) An undertaking in Form - C in Annexure -III by the registered professionals to the
competent authority in the case of developments such as Non High Rise Buildings
and High Rise Buildings and other developments as may be decided by the
competent authority.
(10) The competent authority may seek any additional particulars as deemed fit for
processing the application.
(11) The applicant may address the competent authority for clarification before filing an
application and such clarification shall be issued within 2 months from the date of
receipt of application seeking such clarification.
14 TAMIL NADU GOVERNMENT GAZETTE EXTRAORDINARY
Previous and next
All provisions of Tamil Nadu Combined Development and Building Rules, 2019
Questions people ask
Is rule 6 of Tamil Nadu Combined Development and Building Rules, 2019 still in force?
No repeal of Tamil Nadu Combined Development and Building Rules, 2019 is recorded.