35.4 Payment security shall be valid for the duration of the transactions or 18 months from the
month in which transaction commences, whichever is earlier. The validity may be extended for
subsequent transaction suitably at the instruction of SLDC in case the customer opts for
another transaction. Payment security shall be released after confirmation of full payments
made by the customer.
36. Fee for Approaching the Commission–
36.1 The fee payable for approaching the Commission for redressal of issues relating to Open
Access shall be as per Uttar Pradesh Electricity Regulatory Commission (Fee and fines)
Regulations, 2018, as amended from time to time. No fee shall be payable to the Commission
in case the matter is referred to the Commission by the State Power Committee/ Grievance
Redressal Committee.
37. Power to Amend–
37.1 The Commission may, at any time add, vary, alter, modify or amend any provision of these
Regulations.
38. Power to Remove Difficulties–
38.1 If any difficulty arises in giving effect to the provision of these regulations, the Commission
may, by general or specific order, make such provisions not inconsistent with the provisions of
the Act, as may appear to be necessary for removing the difficulty.
39. Repeal and Savings–
39.1 Save as otherwise provided in these Regulations, the Uttar Pradesh Electricity Regulatory
Commission (Terms and Conditions for Open Access) Regulations, 2004, and respective
amendments shall stand repealed from the date of notification of these Regulations.
39.2 Notwithstanding such repeal, anything done or purported to have been done under the repealed
Regulations shall be deemed to have been done or purported to have been done under these
Regulations.
mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0 55
Schedule-A
Procedure for Long-Term and Medium-Term Open Access
1. OUTLINE–
1.1 This procedure shall apply to the application made for long- and medium-term open access for
use of intra-State transmission system and/or distribution system with associated facilities for
transmission and/or wheeling of electricity, with or without inter-State transmission system.
1.2 Provided that procedure made hereunder shall be in addition to and not in derogation of open
access regulations or any procedure made thereunder by the Central Electricity Regulatory
Commission for use of inter-State transmission system.
1.3 It aims at easy and pragmatic disposal of applications made for long-term and medium
termopen access. However, some problems may still be experienced. This procedure shall be
reviewed or revised by the Commission by an order suo-moto or on an application moved by
the Nodal Agency citing the reasons and/or cases requiring such consideration.
1.4 All correspondences shall be addressed to the following Officer of State Transmission
Utility (STU):
Chief Engineer (Transmission),
11th Floor, Shakti Bhawan Extension, 14-Ashok Marg,
Lucknow-226 001
Tel: (STU to specify on its website)
Fax: (STU to specify on its website)
E-mail: (STU to specify on its website)
2. SUBMISSION OF APPLICATION–
2.1 The long-term and medium-term open access customer (hereinafter referred to as “customer”)
intending to avail open access shall make an application on format [FORMAT- LT1] with STU
in a cover marked “Application for Long-Term or Medium-Term Open Access”.
2.2 Time Duration of Application:
(i) When System strengthening is involved–The customer shall apply for long-term access
3 years in advance.
(ii) When System strengthening is not involved–An application can be made by the
customer six months in advance.
NOTE: ‘System strengthening’ shall mean to include augmentation or renovation or
modernization or expansion of any equipment or substation and/or electric line and
construction of new substation and/or electric line.
2.3 Application Fee:
(i) When System strengthening is involved- non-refundable application fee of
Rs. 1,50,000/- (or as determined by the Commission from time to time in its order) shall
be levied.
(ii) When System strengthening is not involved- non-refundable application fee of
Rs. 50,000/- (or as determined by the Commission from time to time by an order) shall be
levied.
56 mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0
This fee will be deposited by demand draft in favor of the officer as notified by STU
payable at Lucknow. STU shall acknowledge receipt of the application by indicating time
and date on an “ACKNOWLEDGEMENT” to the customer. The application may be
submitted by post or in person.
3. PROCESSING OF APPLICATION–
3.1 The application shall be taken up for consideration immediately and not later than seven days
by STU on “first come first served basis”. The STU shall seek system feasibility reports from
transmission licensee and/or distribution licensee involved in transaction for permitting open
access. STU shall also make endorsement of the same to SLDC, if considered necessary. The
transmission licensee and/or distribution licensee, as the case may be, shall carry out system
feasibility study, including site drawings, schedule of site responsibility and any other
information necessary for consideration and respond to STU within 30 days.
3.2 The feasibility reports may suggest as follows:
(a) System strengthening is not required-
In such case STU shall assess the capacity available and communicate provisional
decision to SLDC with copy to transmission licensee and/or distribution licensee.
(b) System Strengthening is required-
In case there is a constraint in electricity system and system strengthening is necessary,
then:
[i] The licensee shall submit adequate data and drawings in support of suggestion of
system strengthening for consideration of STU.
[ii] STU shall assess requirement of system strengthening and may also cause the
customer to furnish any additional information required for system studies, if
required. On being satisfied, communicate decision to the customer within 15 days
requiring him to pay fee difference of fee for system studies, if not paid earlier.
[iii] The fee shall be paid within fifteen days failing which the application shall be
deemed to be rejected at the discretion of STU.
4. CONFIRMATION OF RESERVATION OF CAPACITY–
4.1 Where electricity system strengthening is not required–
(i) STU shall communicate provisional decision of application processing to SLDC within
seven (7) days along with the customer’s application and licensee’s report(s).
(ii) STU, in consultation with SLDC, shall check transaction for congestion of any element
(electric line and transformer) of transmission and/or distribution system involved in open
access transaction.
(iii) STU shall confirm grant of open access on format [FORMAT-LT2] within sixty days of
receipt of the application with direction to the customer to enter into Bulk Power
Transmission Agreement (BPTA) and/or Bulk Power Wheeling Agreement (BPWA) with
concerned transmission licensee and/or distribution licensee within thirty days.
(iv) In the event of an offer becomes invalid for any reason or rejected by the customer, STU
shall not be required to consider any further application from the same customer within
twelve months from the date of issue of FORMAT-LT2 unless new application
substantially different from the original application is made.
mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0 57
4.2 Where electricity system strengthening is involved–
(i) After processing of application as specified above, STU may require the customer, any
other transmission licensee and/or distribution licensee to furnish additional
information/study/data for further studies within fifteen days. Based on above
information, STU shall prepare preliminary report of system study covering all aspects of
UPEGC and communicate the same to all concerned within next one month:
Provided that if there are more than one application for long-term or medium term
access, STU shall undertake joint studies and prepare one consolidated preliminary
report. STU shall invariably send a copy to SLDC, transmission licensees and/or
distribution licensees, as the case may be.
(ii) The preliminary report shall be communicated along with specific information on
FORMAT- LT2 to all concerned not later than one hundred twenty days from the date of
receipt of application in case of long term and sixty days in case of medium term and
such communication shall be deemed to be grant of open access. However, in case of
more than one application, the condition of one hundred twenty days/ sixty days shall not
apply and STU shall fix such date which shall not be more than one hundred fifty days/
seventy five days in case of long term and medium term respectively. If more than one
application consists of one long term and one medium term application then the outer
time limit of long term application shall be applicable.
(iii) The customer shall enter into Bulk Power Transmission Agreement (BPTA) and/or Bulk
Power Wheeling Agreement (BPWA) with concerned transmission licensee and/or
distribution licensee within sixty days in case of long term and within thirty days in case
of medium term respectively. The copy of such agreements shall be sent to SPC and
SLDC.
(iv) Notwithstanding anything contained in sub clause 4.2 (i), any other transmission licensee
and/or distribution licensee shall also be required by STU to identify system
strengthening requirements at their end and communicate the same to STU with relevant
details in respect to inter-connection, cost estimates, construction milestones/schedule
and site responsibility schedule, drawings and any other information as may be necessary
for consideration of STU within forty five days from the date of receipt of preliminary
report of system study.
(v) The requirement of system strengthening brought out in preliminary report shall be
integrated with the transmission plan (made as per Section 39 of the Act read with the
provisions of UPEGC) prepared by STU. The plan so prepared shall be approved by
CEA.
(vi) Based on approved transmission plan, STU shall finalize strengthening requirements in
transmission and distribution systems, in consultation with SLDC and concerned
transmission and /or distribution licensees or SPC as the need be.
(vii) System strengthening requirements should clearly identify expansion, augmentation,
renovation, modernization of existing sub-stations and/or electric lines and/or
construction of new substations and electric lines. It also includes decision regarding who
will construct, own, maintain and operate different parts of the system strengthening
scheme.
(viii) The final report shall be communicated to all concerned to take up the work of the system
strengthening as per the schedules finalized or decisions taken therein. After final report
is prepared, the customer, STU, any other transmission licensee and distribution licensee
58 mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0
or any other person associated with transaction shall comply with such instructions,
obligations, duties, time schedules or any other matter as may be specified by STU in
final report:
Provided if STU has changed system strengthening requirements, on the basis of
any subsequent study carried out on its own motion or on an application of any other
customer, any other transmission licensee and distribution licensee in such event, the
changes carried out by STU shall be binding on the customer, any other transmission
licensee and distribution licensee or any other person associated with transaction.
5. Bulk Power Transmission Agreement (BPTA) and/or Bulk Power Wheeling Agreement (BPWA)–
5.1 Bulk Power Transmission Agreement (BPTA) and/or Bulk Power Wheeling Agreement
(BPWA) shall be signed by the customer with STU, any other transmission licensee and
distribution licensee, as the case be, agreeing therein to pay transmission and wheeling charges
for use of existing transmission and/or distribution system. These agreements shall be signed
within time communicated to the customer as specified above. The charges as stated above
shall be payable along with other charges, as applicable, associated with open access in
accordance with open access regulations.
5.2 A supplementary BPTA and/or BPWA to the principal agreements signed under clause 5.1
shall also be signed by the customer with STU, any other transmission licensees and
distribution licensees, as the case be, agreeing therein to pay additional transmission and
wheeling charges for use of additional transmission and/or distribution system created due to
system strengthening.
5.3 At the instance of STU, agreements shall include provisions in respect to:
(i) requirement of protection system, metering, operational and safety criteria, data and
communication system;
(ii) conditions of interconnection/connectivity, technical requirements thereof;
(iii) relevant drawings covering all aspects in relation to (i) and (ii) above;
(iv) ‘Site Responsibility Schedule’ in relation to ownership, control, operation and maintenance
of plant and apparatus and safety of persons;
(v) procedure for site access, site operational activities and maintenance standards for
equipment of concerned transmission licensee and/or distribution licensee and/or
customer’s premises;
(vi) premature termination of agreement and its consequences on the contracting parties;
(vii) compliance with the provisions of U.P. Electricity Grid Code, Indian Electricity Grid
Code, regulations/norms/standards/codes specified by CEA/UPERC or any provision of
planning criteria/ any covenants/deeds/regulations by which STU/Transmission licensee /
distribution licensee are bound;
(viii) details of system strengthening requirements including inter-connection, approximate cost
estimates, construction and commissioning milestones/ schedule, schedule of
commissioning and commercial operationalization;
(ix) provisions for payment security, payment, rebate and surcharge as per UPERC (Terms and
condition of transmission tariff) Regulations and UPERC (Terms and condition of
distribution tariff) Regulations and orders of the Commission made thereunder;
5.4 Where electricity system strengthening is involved, the parties should note the following:
(i) System strengthening work shall be taken up after signing of BPTA and/or BPWA.
mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0 59
(ii) The customer and concerned licensees shall furnish progress of system strengthening
works on quarterly basis to each other with a copy to STU.
(iii) The customer and concerned licensees shall inform, in writing, at least ninety days ahead
of scheduled commercial operation date in case of long term and at least thirty days
ahead of scheduled commercial operation date in case of medium term of additional
systems of their part to STU with a copy to concerned/affected persons. Based on
information received, STU shall confirm the customer and concerned licensees at least
sixty days/thirty days ahead of scheduled date of commencement of long/medium-term
transaction respectively and direct the customer to:
(a) establish adequate payment security within thirty days in case of long term and
fifteen days in case of medium term ; and
(b) submit a request for scheduling of transaction to SLDC within thirty days in case of
long term and within fifteen days in case of medium term.
5.5 Whenever any equipment and/or drawing are proposed to be changed, the customer or licensee
shall intimate necessary changes to STU and all other concerned. When changes are
implemented, revised single line diagram shall be circulated by the customer or licensee to
STU and all concerned.
6. General–
6.1 STU shall designate an Officer as ‘Nodal Officer’ who shall make correspondence in the
matter of open access and shall be responsible for processing and arranging long- term and
medium-term access. A public notice to above effect shall be made in newspapers and kept on
website within fifteen days of issue of these regulations under intimation to the Commission.
6.2 Any line or transformer or sub-station involved in an open access transaction shall be
exempted from load shedding. SLDC shall be responsible to make proper arrangements in
coordination with transmission/distribution licensee ensuring that the customer remains
unaffected in the event of load shedding. Provided that the consumers with contracted demand
of more than 1 MW if fed through mixed feeder will be allowed open access subject to their
agreeing to the system constraints as well as power cuts imposed on the feeder.
6.3 STU shall maintain up-to-date records of customers, Long-term and Medium-term transactions
and any other relevant information/data and other decisions taken by it on its website and keep
the Commission informed.
6.4 STU may modify formats specified under this procedure as the need be under intimation to the
Commission. These formats shall also be kept on website.
6.5 The customer shall keep STU, SLDC and distribution licensee indemnified at all times and
shall undertake to indemnify, defend and keep STU, SLDC and distribution licensee harmless
from any and all damages, losses, claims and actions including those relating to injury to or
death of any person or damage to property, demands, suits, recoveries, costs and expenses,
court costs, attorney fees, and all other obligations by or to third parties, arising out of or
resulting from open access transaction.
6.6 All complaints regarding unfair practices, delays, discrimination, lack of information, supply
of wrong information or any other matter related to open access in intra-state transmission shall
be directed to the Member Secretary, State Power Committee or Member Secretary, Grievance
Redressal Committee, as the case may be. SPC or GRC, as the case may be, shall investigate
and endeavour to resolve the grievance. The Member Secretary, SPC/ GRC shall forward copy
of its decision to the Commission. In case SPC/ GRC is unable to resolve the matter, it shall be
reported to the Commission for a decision.
6.7 An application involving inter-state transaction shall be governed by the regulations issued by
the Central Electricity Regulatory Commission.
60 mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0
Schedule-B
Procedure for Short-Term Open Access
1. Outline
1.1 This procedure shall apply to the application made for short-term open access for use of intra-
state transmission system and/or distribution system with associated facilities for transmission
and/or wheeling of electricity, with or without inter-state transmission system:
Provided that procedure made hereunder shall be in addition to and not in derogation to
open access regulations or any procedure made thereunder by the Central Electricity
Regulatory Commission for use of inter-State transmission system.
1.2 It aims at easy and pragmatic disposal of applications made for short-term access. However,
some problems may still be experienced. This procedure shall be reviewed or revised by the
Commission by an order suo-moto or on an application moved by the Nodal Agency citing the
reasons and/or cases requiring such consideration.
1.3 All correspondences shall be addressed to the following Officer of State Load Despatch Centre
(SLDC):
Chief Engineer (Power System),
SLDC Campus, Vibhuti Khand-II, Gomti Nagar,
(near Mantri Awas),
Lucknow-226 010
Tel: (SLDC to specify on its website),
Fax: (SLDC to specify on its website);
E-mail: (SLDC to specify on its website).
2. Registration–
2.1 The short-term open access customer (hereinafter referred to as “customer”) intending to avail
short-term access shall obtain ‘One-Time Registration’ on format [FORMAT-ST11] with
SLDC. The registration charges will be as specified in SLDC (Fees & Charges) Regulation, as
amended from time to time or as specified in any order of the Commission.
2.2 SLDC shall convey acceptance of registration or to the customer within five working days
from the date of receipt of FORMAT- ST11.
2.3 Any additional power or change in points of injection and/or drawl shall require fresh
registration with SLDC including with or without inter-state network.
2.4 The registration of customer is aimed at recording basic inputs of open access transactions on
the basis of which operational constraints in transmission and/or distribution system shall be
assessed by the SLDC before permitting open access. It should not be mistaken as a
grant/guarantee of open access.
3. Submission Of Application And Confirmation Of Reservation Of Capacity For Recurring
Transactions–
3.1 The customer shall seek concurrence of STU and/or transmission licensee and/or distribution
licensee, as the case may be, involved in transaction on formats [FORMAT-ST12(A)&(B)].
mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0 61
3.2 It shall be accompanied by non-refundable application fee of Rs. 5,000/- (or as determined by
the Commission from time to time by an order) by demand draft, RTGS/NEFT/IMPS or
through any other mode of digital payment in favour of the Officer as notified by SLDC
payable at Lucknow.
3.3 STU and/or transmission licensee and/or distribution licensee, as the case may be, shall convey
his concurrence or otherwise on formats [FORMAT- ST13(A)&(B)] to SLDC within fifteen
days from the date of receipt of FORMAT-ST12(A)&(B).
3.4 “Concurrence” shall mean in principle agreement for allowing use of transmission and/or
distribution system during a specified period after due verification of spare capacity, any
operational constraint and availability of infrastructure for operation of ABT including ABT
meters and communication system. This Concurrence shall be provided by SLDC. The
concurrence shall be applicable for stated power, period of transaction and points of injection
and drawl.
3.5 In case of rejection of request for concurrence, STU or transmission licensee or distribution
licensee concerned shall convey reasons to SLDC in writing with a copy to the customer.
SLDC shall seek clarification from concerned licensee and take appropriate decision as
deemed fit.
3.6 In case of acceptance, SLDC shall check transaction for congestion of any element (line and
transformer) of transmission and/or distribution system involved in transaction and accordingly
permit open access.SLDC shall assign specific reasons if open access is denied as specified
above.
3.7 SLDC shall convey grant of open access or otherwise in formats [FORMAT- ST13(A)&(B)]
along with schedule of payments to the customer within fifteen days from the date of receipt of
acceptance by STU and/or transmission licensee and/or distribution licensee as mentioned in
clause 3.3 above.
3.8 In case of extension beyond the period mentioned in the application, if the customer is limiting
its transaction within the earlier concurred capacity then it does not require fresh concurrence
from transmission /distribution licensee however, it will intimate concerned transmission/
distribution licensee about the extension stating that during extension the transaction will be
within the earlier concurred capacity. In such a situation earlier given concurrence shall remain
valid till any objection on such concurrence is raised by the concerned transmission/
distribution licensee. In such a case, there will be no requirement of fresh filing of Format 12A
& B. No application Fee shall also be charged for the extension of transaction:
Provided that any extension at a time shall be for a period of three months only and
extension of such transaction may be carried out for a period of not more than one year from
the date of original application.
4. Submission Of Application (For Day Ahead Transactions And Non-Recurring Transactions):
4.1 The application for grant of open access shall be submitted on format [FORMAT- ST1] for
transaction registered for a specified time period as stated above.
4.2 It shall be accompanied by non-refundable application fee of Rs. 5,000/- (or as determined by
the Commission from time to time by an order) by demand draft, RTGS/NEFT/IMPS or
through any other mode of digital payment in favour of the Officer as notified by SLDC
payable at Lucknow.
62 mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0
4.3 SLDC shall acknowledge receipt of the application with an
“ACKNOWLEDGEMENT” to the customer. In case of default in payment of the application
fee, SLDC shall reject the application.
4.4 The application received by SLDC after 17:00 hrs of a day shall be treated as having been
received on the next day.
5. Confirmation Of Reservation Of Capacity (For Day Ahead Transactions And Non-Recurring
Transactions)–
5.1 Non-Recurring Transaction:
(a) An application for grant of open access for non-recurring transactions commencing in
any month may be submitted up to 15th day of the preceding month.
For example, application for grant of open access commencing in the month of July
shall be received up to 15th day of June.
(b) SLDC shall check transaction for congestion of any element (line and transformer) of
transmission and/or distribution system involved in transaction and accordingly permit
open access.
(c) SLDC shall convey grant of open access or otherwise in format [FORMAT-ST2] along
with schedule of payments to the customer latest by 20th day of such preceding month.
(d) SLDC shall assign specific reasons if open access is denied as specified above.
5.2 Day-ahead Transaction:
(a) Day ahead transaction shall be permitted, in case, SLDC notifies on its website of any
capacity, which has been expressly surrendered, whole or part thereof, or not in use for
more than three days in past.
(b) An application for grant of open access for such capacity may be received by SLDC
within three days prior to the date of scheduling but not later than 1300 Hours of the day
immediately preceding the day of scheduling for day-ahead transaction.
(c) For example, application for day-ahead transaction on 25th day of July shall be received
on 22nd day or 23rd day or up to 1300 hours on 24th day of that month.
(d) SLDC shall check for congestion and inform all concerned, as provided above, of re-
allotment of the capacity. All other provisions of registration, application and
confirmations shall also apply.
6. Bidding Procedure–
6.1 If the capacity sought by the customers is more than the available capacity or SLDC perceives
congestion of any element of transmission and/or distribution system involved in transaction
before allocation, the allocation shall be made through bidding procedure.
6.2 The decision of SLDC in respect of an expected congestion shall be final and binding. SLDC
shall convey information of congestion and decision of invitation of snap bids indicating floor
price on format [FORMAT-ST3] to the customers.
6.3 SLDC may invite bids through fax / e-mail and shall also display bidding information on its
website.
6.4 The floor price comprising of transmission and/or wheeling charges determined on the basis of
relevant order of the Commission shall be indicated in FORMAT-ST3.
mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0 63
6.5 The Bids shall be accepted on format [FORMAT-ST4] up to the “bid closing time” as
indicated in bidding invitation FORMAT- ST3. Modification / amendment to a bid, once
submitted shall not be entertained.
6.6 If any customer does not participate in bidding process, his application shall be deemed to have
been withdrawn and shall not be processed.
6.7 SLDC shall not entertain any request for extension of time/date for submission of bids.
6.8 Bid price and the approval of the capacity for open access shall be determined as follows:
(a) The bidders shall quote price (rounded-off to whole number) in denomination in which
floor price has been determined.
(b) The quoted price shall be arranged in descending order and allocation of available
capacities shall be accorded in such descending until the available capacity is exhausted.
(c) In case of equal price quoted by two or more customers, the allocation from the residual
available capacity at any stage under sub-clause 6.8 (b) shall be made in proportion to
capacity being sought by such customers.
(d) All customers, in favour of whom full capacities have been allotted, shall pay the highest
price obtained from bids.
(e) The customers, who are allotted less capacity, shall pay the price as quoted by them.
6.9 SLDC shall reject bid which are in-complete; vague in any manner or not found in conformity
with bidding.
6.10 The successful bidding customer, in favour of whom the capacities have been allocated, shall
pay transmission charges, wheeling charges, as the case may be, determined by bidding under
sub-clause 6.8 (c) or sub-clause 6.8 (d).These charges shall be payable along with other
charges, as applicable, associated with open access in accordance with open access
Regulations.
7. General–
7.1 SLDC shall designate an Officer as ‘Nodal Officer’ who shall make correspondence in the
matter of open access and be responsible for processing and arranging short-term open access.
Similarly, STU, other transmission licensee and distribution licensee shall each nominate
‘Coordinator’ for necessary co-ordination with SLDC. A public notice to above effect shall be
made in newspapers and kept on websites within fifteen days of issue of these regulations
under intimation to the Commission.
7.2 Separate application shall be made for each open access transaction.
7.3 The mode of communication may be fax or e-mail with post confirmation by post or delivered
personally.
7.4 An application incomplete/vague or not in conformity with the Regulations and procedure shall
be summarily rejected and the decision of SLDC in that regard shall be final.
7.5 The “day” means a day starting at 00:00 hours and ending at 24:00 hours. For example, in case
of application of reservation for time period 22:00 hours to 03:00 hours, reservation of capacity
shall be from 22:00 hours to 24:00 hours in the first day and 00:00 hours to 03:00 hours in next
day.
7.6 In case of the customer/beneficiary being a consumer in the area of supply of a distribution
licensee, a copy of application and subsequent correspondences, as considered appropriate
64 mŸkj izns'k vlk/kkj.k xtV] 10 fnlEcj] 2019 bZ0
shall also be sent to such distribution licensee for the purpose of surcharge and/or additional
surcharge.
7.7 Any line or transformer or sub-station involved in an open access transaction shall be
exempted from load shedding. SLDC shall be responsible to make proper arrangements in
coordination with transmission / distribution licensee ensuring that the customer remains
unaffected in the event of load shedding. Provided that the consumers with contracted demand
of more than 1 MW if fed through mixed feeder will be allowed open access subject to their
agreeing to the system constraints as well as power cuts imposed on the feeder.
7.8 The licensees shall make all reasonable attempts to ensure that operational constraints in
transmission and/or distribution systems, as the case may be, including metering,
communication system, capacity determination, etc. are removed so that, as far as possible, no
eligible customer is denied open access on the ground of operational constraints.
7.9 The customer shall establish communication facilities such as telephone, fax, computer and
internet facilities etc., as specified in the Regulation, before undertaking transmission of
electricity.
7.10 SLDC shall maintain up-to-date records of customers and other decisions taken by it on its
website and keep the Commission informed.
7.11 SLDC may modify formats specified under this procedure as the need be in consultation with
STU and information to the Commission. These formats shall also be kept on website.
7.12 The customer shall keep SLDC indemnified at all times and shall undertake to indemnify,
defend and keep SLDC harmless from any and all damages, losses, claims and actions
including those relating to injury to or death of any person or damage to property, demands,
suits, costs and expenses, court costs, attorney fees, and all other obligations by or to third
parties, arising out of or resulting from open access transaction.
7.13 All complaints regarding unfair practices, delays, discrimination, lack of information, supply
of wrong information or any other matter related to open access in intra-state transmission shall
be directed to the Member Secretary, State Power Committee or Member Secretary, Grievance
Redressal Committee, as the case may be. SPC or GRC, as the case may be, shall investigate
and endeavour to resolve the grievance. The Member Secretary, SPC/ GRC shall forward copy
of its decision to the Commission. In case SPC/ GRC is unable to resolve the matter, it shall be
reported to the Commission for a decision.
By order of the Commission,
SANJAY KUMAR SINGH,
Secretary.
ih0,l0;w0ih0 31 vlk/kkj.k xtV&23-12-2019&150 izfr;ka&¼Mh0Vh0ih0@vkQlsVA
A. Short-term open access customer:
(i) SLDC shall serve a notice on format [FORMAT-ST9] to such customer. SLDC shall make endorsements to all concerned with the transaction.
(ii) The notice period shall be of three days. The notice period shall exclude the day on which notice is served and the day from which such reduction/cancellation is to commence.
(iii) On expiry of notice period, marginal capacity shall stand reduced or cancelled, as the case may be, unless decided otherwise by SLDC and communicated to all concerned, who are connected or affected by such transaction on format [FORMAT-ST10(B)].
(iv) The decision of SLDC shall be final and binding.
(v) In the event of under-utilization of the capacity contracted under Open Access by the customer, the concerned licensee may also file an application with SLDC to reduce or cancel the capacity allocated to the customer after it has served a prior notice of default to the customer. On such application, SLDC may review the allotment capacity and follow the procedure as stated above.
(vi) SLDC may allot the capacity, available as a result of surrender or reduction or cancellation of the marginal capacity to any other customer.
(vii) The customer on its own shall not assign/transfer whole or any part of his marginal capacity to any person or licensee.
(viii) The capacity that becomes available, due to decisions of SLDC, shall be displayed on its website.
B. Medium-term open access customer:
C. Long-Term Access:
CHARGES FOR OPEN ACCESS
Provided that where a transmission system and/or a distribution system has been constructed for exclusive use of an open access customer, the transmission charges and/or wheeling charges for whole of the system, including such additional system for exclusive use, shall be paid by open access customer.
Notwithstanding above, any relaxation regarding transmission and wheeling charges, as granted under the CRE Regulation, shall be applicable with respect to those plants for the use of intra-state network during the period of CRE Regulation, as amended from time to time.
Inter-State Open Access:
Intra-State Open Access:
Previous and next
Questions people ask
Is form AT-ST5 of Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2019 still in force?
No repeal of Uttar Pradesh Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2019 is recorded.