Rule 11, Acquisition of Right of User in Land Rules, 2018: Right of entering for inspection etc

Acquisition of Right of User in Land Rules, 2018 - Rule 11

Text of rule 11

Right of entering for inspection etc

11. Right of entering for inspection etc.- (1) After handing over the possession of land to the land owner / occupier, the Corporation who laid the Water, Gas or Drainage Pipelines the persons authorized by the Corporation shall have the power to enter in the land and do the work as found necessary for inspection, maintenance, repair, replacement or removal of the Water, Gas or Drainage Pipelines. (2) If the land owner or occupier refuses to sign any form, which he or she is required to sign under these rules, the same shall be signed by the Completent Authority, provided the procedure under these rules has been followed. 12. Cost of acquisition of right of user by requisitioning body (1) The establishment charge and contingency cost for the right of user by requisitioning body / corporation shall be 5 percent of the total value of compensation assessed under rule 7. (2) The requisitioning body / corporation shall deposit the establishment charge and the contingency cost, as calculated under rule 12 (1) by way of bank draft to the Collector and the Collector shall deposit the cost of user land in the Deposit account in the district treasury or in a scheduled bank account maintained separately for this purpose to be jointly operated by Competent Authority and Deputy Commissioner.

Previous and next

All provisions of Acquisition of Right of User in Land Rules, 2018

Questions people ask

Is rule 11 of Acquisition of Right of User in Land Rules, 2018 still in force?

No repeal of Acquisition of Right of User in Land Rules, 2018 is recorded.