Recognition of Government Approved Test Centre
5. Recognition of Government Approved Test Centre.- (1) Any person desirous of obtaining
recognition under these rules for carrying out verification of weights or measures, shall make an
632 ( 8)
application to the Director, Legal Metrology in the form as specified in the Second Schedule. The
qualifications and experience require shall be as under :-
(i) Qualifications- The qualification of the principal officer or any of the employees of
the Government Approved Test Centre shall be equivalent to the qualification as
specified in the Legal Metrology (General Rules), 2011 for a Legal Metrology
Officer;
(ii) Experience- The Principal Officer or any of the employees of the Government
Approved Test Centre shall have working experience of at least three years in the
field of legal metrology.
(2) The application shall be made only by the Principal Officer of the said laboratory.
(3) While making recommendation for approval of a Government Approved Test Centre, the
Director, Legal Metrology shall consider the following:-
(a) Availability and accessibility of land and building;
(b) Adequacy of measuring equipments, testing facilities and other infrastructure;
(c) Availability of technically qualified man power;
(d) Capacity for efficient and timely service to customers;
(e) Whether equipments are periodically verified by secondary standard laboratory or
any other agency determinable by Director, Legal Metrology;
(f) Employees are trained in an institution nominated by Director, Legal Metrology;
(g) Any other factor, which in the opinion of Director, Legal Metrology will affect
proper functioning of Government Approved Test Centre.
(4) The Joint Secretary, Department of Consumer Affairs, Government of India shall be the
Competent Authority to approve the Government Approved Test Centre who shall give such
approval on the recommendation of the Director, Legal Metrology.
(5) The Competent Authority shall grant approval under sub-rule (4), for one year and there after
the same shall be renewed for a period not exceeding five years at a time on the Controller’s
recommendation.
(6) The Director, Legal Metrology will issue a specific code number to each Government
Approved Test Centre for easy identification and records.
(7) In case of non-fulfilling of eligibility conditions, the Director, Legal Metrology shall reject the
application and send a written communication to the applicant and to Controller also.
(8) Any person aggrieved by orders under sub-rule (7) may appeal to Secretary of the Department
of Consumer Affairs, whose decision shall be final.
(9) Certificate of approval granted to any Government Approved Test Centre may be suspended
by Director, Legal Metrology in case the Government Approved Test Centre fails to comply
with any terms or conditions specified in these rules:
Provided that no such suspension shall be made except after giving to the
Government Approved Test Centre an opportunity of show cause against the proposed action:
Provided further that the suspension shall be revoked on compliance of terms and
conditions.
(10) The Director or his Authorized Officer may visit the Government Approved Test Centre as
and when required and the Principal Officer shall permit inspections and render all assistance
for the purpose including the production of records with regard to verification of weights and
measures.
(11) The Principal Officer shall submit a quarterly report to the Director, Legal Metrology and
Controller in respect of the weights and measures verified by them, the fee collected, time
taken for each testing and such other relevant information, as required.
(12) The Principal Officer, while verifying the weights and measures shall adopt the procedure laid
down in the Legal Metrology (General) Rules, 2011.
632 (9)
(13) The certificate of approval granted may be cancelled by the Director, Legal Metrology on the
recommendation of the Controller if the circumstances are such that it cannot be reasonably
expected to function properly as a Government Approved Test Centre:
Provided that no certificate of recognition shall be cancelled except after giving an
opportunity of being heard.
(14) Where the certificate of approval has been granted under sub-rule (4) or suspended under sub-
rule (9) or cancelled under sub-rule (13), the Director of Legal Metrology shall ensure that the
information of such action has been given to the concerned Controller of Legal Metrology of
the State immediately.
(15) The Competent Authority may require Government Approved Test Centre to take out third
party liability insurance sufficient to cover any claim for damage due to any lapses or
violation of government instructions by such Government approved Test Centre.
(16) All the Regional Reference Standard Laboratories working under the administrative control of
the Department of Consumer Affairs shall start functioning as deemed Government Approved
Test Centre on the date of publication of these rules in the Official Gazette and the provisions
of these rules shall apply to such Regional Reference Standard Laboratory as if they were
Government Approved Test Centre.
Previous and next
← Rule 4General provisions relating to Government Approved Test CentreRule 6 →Duties of the Principal Officer and Government Approved Test Centre
All provisions of The Chhattisgarh Legal Metrology (Government Approved Test Centre) Rules, 2018
Questions people ask
Is rule 5 of the Chhattisgarh Legal Metrology (Government Approved Test Centre) Rules, 2018 still in force?
No repeal of the Chhattisgarh Legal Metrology (Government Approved Test Centre) Rules, 2018 is recorded.