Rule 145, Madhya Pradesh Municipal Corporation (Accounts and Finance) Rules 2018: Realisation of Deposits
Madhya Pradesh Municipal Corporation (Accounts and Finance) Rules 2018 - Rule 145
Text of rule 145
Realisation of Deposits
145. Realisation of Deposits.-
(1) Whenever a deposit work is to be undertaken, the deposit shall be realised
before any liability is incurred on the work. One percent of the anticipated
project cost shall be realised before preparation of preliminary estimates. In
addition to the outlay on the work in the preliminary estimates, departmental
charges at such percentages as are prescribed by the State Government
from time to time shall also be realised in advance. No interest shall be
allowed on sums deposited from any source, including private contributions.
(2) In the case of deposit works which are financed entirely from Government
grants, and from whom receipt of deposits is assured, 33-1/3% of the
estimated cost of the work, may be deposited in advance. Thereafter, the
expenditure incurred may be reimbursed through monthly bills simultaneously
with rendering of monthly accounts on the progress of work. The deposit of
33-1/3% obtained as the first installment shall be retained for adjustment
against the last portion of the estimated expenditure.
(3) Where delays are experienced in obtaining deposits, and where the
expenditure has to be incurred out of the 33-113% reserve to keep the works
going, the matter shall be brought to the notice of Commissioner promptly for
taking up the matter with the client. No expenditure shall be incurred on
deposit works out of the Municipal Corporation's funds and vice-versa.
l:J~ ~, ~ 13 WR=Q 2018 900 (45)
i~
(4) To. enable the client to provide additional funds in time whenever the
expenditure is anticipated to exceed the preliminary estimate figure, a revised
preliminary estimate shall be submitted to the client well. in time during the
execution of work.
(5) Where a client has defaulted in making the required deposit, or where the
works outlay is predominantly for purchase of capital equipment and
machineries, the entire deposit including departmental charges shall be
realised in advance.
(6) In no case deposits received from a client for its work shall be diverted to
other works.
(7) The client is clearly made to understand that the Municipal Corporation does
not bind itself to complete the work within the amount of the preliminary
estimate, and that they should agree to pay for the excess expenditure that
may occur. An acknowledgement of this clear understanding shall be
obtained from the client before the deposit work is taken in hand.
(8) The Engineer-in-Charge of the work shall ensure that at any time during the
progress of the work, the expenditure is not more than the deposits received
for the work. Where the Engineer-in-Charge is doubtful about the timely
receipt of deposits, he shall notify the client that if further deposit is not
received, the work would be stopped, and any contractual liability arising out
of such stoppage of work will be borne by the client. He should also bring this
to the notice of Commissioner for taking up the matter with the client.
Previous and next
All provisions of Madhya Pradesh Municipal Corporation (Accounts and Finance) Rules 2018
Questions people ask
Is rule 145 of Madhya Pradesh Municipal Corporation (Accounts and Finance) Rules 2018 still in force?
No repeal of Madhya Pradesh Municipal Corporation (Accounts and Finance) Rules 2018 is recorded.