LawGrids logoLAWGRIDS.ORG

Form F5, MULTI YEAR TRANSMISSION TARIFF AND SLDC CHARGES REGULATIONS, 2018: Form No:F5

MULTI YEAR TRANSMISSION TARIFF AND SLDC CHARGES REGULATIONS, 2018 - Form F5

Text of form F5

Form No:F5

Form No:F5 Rs Crores Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) 1 Capital Cost Foreign Component Foreign Exchange rate considered for the admitted cost Domestic Component IDC including Financing Charges Capital cost admitted as on------- (Give reference of the BERC relevant Order with Petition No. & Date ) 2 Less : Capital Expenditure(CWIP) 3 Less : User contributions and Grants - - - 4 Total Capital Cost admitted 5 Increase /Decrease due to FERV 6 Capital Cost for Purposes of ARR* *Must be in agreement with the figures shown in Form No: F5 (page-2), otherwise a reconciliation statement must be accompanied. Note 1. Copy of approval letter should be enclosed. Deviation in capital cost and scope of work if any, must be submitted in detailed. 2. Details of IDC & Financing Charges are to be furnished as per FORM- . (g) Financial Package of Capital cost Admitted Rs. Crores Particulars Capital Cost as Approved Capital Cost Incurred Capital cost Admitted Currency Amount Currency Amount Currency Amount Loans Loan-I Loan-II and so on Total Loan Equity Foreign Domestic Total Equity Total Capital cost Debt : Equity Ratio Provide details for True-up period, Current Year and each of ensuing years separately. 55 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee Form No: F5 (h) Capital Cost Estimates and Schedule of commissioning for New Projects Particulars Present Day Cost Completed Cost Date of approval of the Capital cost estimates: Price level of approved estimates As of End of ________ Qtr. Of the year _________ As on Scheduled COD of the Station Foreign Exchange rate considered for the Capital cost estimates Capital Cost excluding IDC, FC, FERC & Hedging Cost Foreign Component, if any (In Million US $ or the relevant Currency) Domestic Component (Rs. crores) Capital cost excluding IDC, FC, FERC & Hedging Cost (Rs. crores) IDC, FC, FERC & Hedging Cost Foreign Component, if any (In Million US $ or the relevant Currency) Domestic Component (Rs. crores) Total IDC, FC, FERC & Hedging Cost (Rs. crores) Rates, taxes & duties considered Capital cost Including IDC, FC, FERC & Hedging Cost Foreign Component, if any (In Million US $ or the relevant Currency) Domestic Component (Rs. crores) Capital cost Including IDC, FC, FERC & Hedging Cost (Rs. crores) Schedule of Commissioning ((Scheduled DOC elementwise)) ------------------------- ------------------------- --------------------------- COD of last Unit/ Block Note: 1. Copy of approval letter should be enclosed. 2. Details of Capital cost are to be furnished as per Form F5-5 or Form 14(Additional Capitalization) as applicable. 3. Details of IDC & Financing Charges are to be furnished as per Form 20 Signature of Petitioner 56 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee (i) Break-up of Project Cost for Transmission System Form No: F5 Rs. Crores No Break Down As per original estimates Actual capital expenditure ( Opening ) Variation (B-C) Reasons for Variation A B C D E A Transmission Line 1 Preliminary works 1.1 Design & Engineering 1.2 Priliminary investigation,Right of way, forest clearance, PTCC , general civil works etc. Total Preliminary works - - 2 Transmission Lines material 2.1 Towers Steel 2.2 Conductor 2.3 Earth Wire 2.4 Insulators 2.5 Hardware Fittings 2.6 Conductor & Earthwire accessories 2.7 Spares 2.8 Erection, Stringing & Civil works including foundation Total Transmission Line Materials - - 3 Taxes and Duties 3.1 Custom Duty 3.2 Other Taxes & Duties * Pertaining to Transmission Business Only, SLDC shall file separately - - Total -Transmission lines - - B. Substations 4 Preliminary works & land 4.1 Design & Engineering 4.2 Land 4.3 Site preparation Total Preliminary works & land - - 5 Civil Works 5.1 Control Room & Office Building including HVAC 5.2 Township & Colony 5.3 Roads and Drainage 5.4 Foundation for structures 5.5 Misc. civil works Total Civil Works - - 6 Substation Equipments 6.1 Switchgear (CT,PT, Circuit Breaker, Isolator etc) 57 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 6.2 Transformers 6.3 Compensating Equipment (Reactor, SVCs etc) 6.4 Control , Relay & Protection Panel 6.5 PLCC 6.6 HVDC package 6.7 Bus Bars/ conductors/Insulators 6.8 Outdoor lighting 6.9 Emergency D.G. Set 6.1 Grounding System 6.1 Structure for switchyard Total Substation Equipments - - - 7 Spares 8 Taxes and Duties 8.1 Custom Duty 8.2 Other Taxes & Duties Total Taxes & Duties - - Total (Sub-station) - - - 9 Construction and pre- commissioning expenses 9.1 Site supervision & site admn.etc. 9.2 Tools and Plants 9.3 construction Insurance Total Construction and pre commissioning expenses - - - 10 Overheads 10 Establishment 10 Audit & Accounts 10 Contingency Total Overheads - - - 11 Total Cost - - 12 IDC, FC, FERV & Hedging Cost 12 Interest During Construction (IDC) 12 Financing Charges (FC) 12 Foreign Exchange Rate Variation (FERV) 12 Hedging Cost Total of IDC, FC, FERV & Hedging Cost - - 13 Capital Cost incl. IDC, FC, FERV & Hedging Cost - - Note: 1. In case of time & Cost over run, a detailed note giving reasons of such time and cost over run should be submitted clearly bring out the agency responsible and whether such time & cost over run was beyond the control of the transmission licensee. 2. Above statement to be provided separately for each transmission line commissioned during the ARR period 58 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee (j) Break-up of Construction/ Supply/ Service packages Form No: F5 SL. Particulars 1 2 3 4 5 6 ---- 1 Name/ No. of Construction / Supply / Service Package (and Schemes/plan) 2 Scope of works1 (in line with head of cost break-ups as applicable) 3 Whether awarded through ICB/DCB/ Departmentally/ Deposit Work 4 No. of bids received 5 Date of Award 6 Actual Date of Start of work Original Scheduled date of Start of work 7 Actual date of Completion of Work Original Scheduled date of Completion of work 8 Value of Award2 in (Rs. Lakhs) 9 Firm or With Escalation in prices 10 Actual capital expenditure till the completion or up to COD whichever is earlier for work capitalized during the period(Rs.Cr.) - Taxes & Duties and IEDC (included in above) - IDC, FC, FERV & Hedging Cost(included in above) 11 Actual capital expenditure till the end of the period(Rs.Cr.) for Capital work under progress - Taxes & Duties and IEDC (included in above)- IDC, FC, FERV & Hedging Cost(included in above) 12 Actual capital expenditure already capitalized in earlier years(Rs.Cr.) - Taxes & Duties and IEDC (included in above) - IDC, FC, FERV & Hedging Cost(included in above) 13 Sub -total (10+11+12) Note: 1. Above statement to be provided separately for each work commissioned during the period, work under progress and part capitalization done in earlier years. 2. Statement as Per Form F5-6 to be duly reconciled with corresponding Cost Break Up to be provided as per Form F5-5 , for each transmission line commissioned during the True-up, Review and ARR period * Pertaining to Transmission Business Only, SLDC shall file separately Signature of Petitioner 59 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018 Name of Transmission Licensee (k) Statement of Additional Capitalization Form No: F5 Rs. Crores No Year Work/ Equipment proposed to be added after COD up to Cut off Date/ Beyond Cut off Date Amount capitalised and Proposed to be capitalised Justification Regulations under which covered Admitted Cost1 1 2 3 4 5 6 7 8 9 10 11 12 13 Note: 1 Fill the form in chronological order year wise along with detailed justification clearly bring out the necessity and the benefits accruing to the beneficiaries. 2 In case initial spares are purchased alongwith any equipment, then the cost of such spares should be indicated separately. * Pertaining to Transmission Business Only, SLDC shall file separately 60 BIHAR GAZETTE (EXTRA) 17TH JULY 2018 Name of Transmission Licensee (l) Statement of Capital Works in Progress Form No: F5 Rs. Crores Particulars Previous Year Current Year (i. e. RE) Ensuing years (Projection) Approved in MYT/RE Actual FY (n+1) FY (n+2) FY (n+3) A a Opening Capital Expenditure(CWIP) b Amount of IDC, FC, FERV & Hedging cost included in a above B a Addition/Adjustment in Capital Expenditure(CWIP) during the period b Amount of IDC, FC, FERV & Hedging cost included in a above C a Capitalization/Transfer to Gross Fixed asset during the period b Amount of IDC, FC, FERV & Hedging cost included in a above D a Closing Capital Expenditure(CWIP) b Amount of IDC, FC, FERV & Hedging cost included in a above * Pertaining to Transmission Business Only, SLDC shall file separately 61 BIHAR GAZETTE (EXTRA), 28TH AUGUST 2018

Previous and next

All provisions of MULTI YEAR TRANSMISSION TARIFF AND SLDC CHARGES REGULATIONS, 2018

Questions people ask

Is form F5 of MULTI YEAR TRANSMISSION TARIFF AND SLDC CHARGES REGULATIONS, 2018 still in force?

No repeal of MULTI YEAR TRANSMISSION TARIFF AND SLDC CHARGES REGULATIONS, 2018 is recorded.