Regulation 6, Power Purchase and Procurement Process of Licensee Regulations, 2018: Power Procurement Plan
Power Purchase and Procurement Process of Licensee Regulations, 2018 - Regulation 6
Text of regulation 6
Power Procurement Plan
6. Power Procurement Plan.—On the basis of demand/energy forecast
and availability projections in accordance with provisions of these
Regulations, the Distribution Licensee shall prepare a Power
Procurement Plan for procuring balance power and energy under short
term power procurement plan and long term power procurement plan.
6.1 Long Term Power Procurement Plan
6.1.1 The long-term Power Procurement Plan shall be prepared by
the Distribution Licensee(s) on the basis of the rolling plan
for ten years. The plan shall be prepared on monthly basis as
per the principles laid down earlier in the Regulations. The
procurement of power through Long term should be at least
equal to the base load assessed under Regulation 4 of these
Regulations.
6.1.2 The long-term Power Procurement Plan shall be strictly as
per merit order principle and it should be the least cost plan
[least financial cost to the Distribution Licensee(s)], the
ultimate objective being to make available secure and reliable
power supply at economically viable tariffs to all consumers
while satisfying power supply planning and security
standards;
Provided that the must run Plants/generators shall be
exempted from merit order principle.
6.1.3 The licensee(s) shall have to submit the following details for
the past three years along with long-term power procurement
plan:-
a) Month wise details (with year-wise totals) indicating
power produced by generating stations owned or
operated by the Distribution Licensee(s)/State, Central
sector generating stations and other sources of power
with whom long-term power purchase agreements have
been entered into, short-term purchases of electricity in
MU and expenses along with per unit cost;
b) Month-wise, category-wise energy sales to consumers
and losses in its area of operation.
6.1.4 The rolling plan shall be integral part of the ARR to be filed
every year. The first long term Power Procurement Plan shall
be submitted by the licensee(s) along with the ARR for the
financial year 2019-20.
6.2 Short-Term Power Procurement Plan
6.2.1 The short-term Power Procurement Plan presents assessment
of availability and requirement of electricity for a period of
one year on a monthly basis.
6.2.2 The short-term Power Procurement Plan shall cover different
periods of the day (peak, off peak and seasonal) and take into
account the following:-
6 BIHAR GAZETTE (EXTRA) 3RD APRIL 2018
a) Availability and Requirement worked out as per
Regulation 4&5 both on Peak Demand (MW) and
Energy (MUs) basis;
b) Impact of the power purchase cost on the ARR for the
ensuing year;
c) The power banking transactions;
d) Renewable purchase obligation;
e) Weather forecast and seasonal variations;
f) Transmission constraints, if any
6.2.3 The short-term Power Procurement Plan for purchase of
power shall be the least cost plan [least financial cost to the
Distribution Licensee(s)], the ultimate objective being to make
available secure and reliable power supply at economically
viable tariffs to all consumers while satisfying power supply
planning and security standards;
6.2.4 Short-term power procurement plan shall be submitted on or
before 15th September each year in accordance with sub-
Regulation 6.8 of these Regulations.
7. Need for Additional Power
7.1 In case, additional procurement of power beyond the quantum
approved in the plan is necessitated, the Distribution Licensee(s)
shall demonstrate to the Commission’s satisfaction that there is a
need for such additional power which it intends to procure and shall
seek the prior approval of the Commission. It may do this by
referring to its most recent Power Purchase Plan approved by the
Commission. The Distribution Licensee(s) shall also specify any
areas in which its fresh proposal departs from its most recent Power
Purchase Plan and shall justify the departure.
7.2 The Commission may call for such additional information or
particulars or documents as the Commission may consider
necessary for approving the power Procurement Plan;
7.3 The Commission may, at its discretion, direct the licensee(s) to
publish the main details of the demand forecasted and power
procurement plan with such particulars and in such manner as the
Commission may direct, so as to enable any member of the public
who desires to file objections, comments or suggestions, to do so, in
the manner indicated in the Conduct of Business Regulations of the
Commission. The Commission shall consider such representations
before approval of the plan;
7.4 The Commission shall decide on the quantum of additional power
requirement within 60 days of receiving request complete in all
respect.
7.5 In case of special circumstances, Commission may issue interim
orders in overall public interest.
8. Approval of Power Procurement Plan
8.1 Short- Term Power Procurement Plan
8.1.1 The Distribution Licensee(s) shall submit the short term
Power Procurement Plan including the assessment of
availability and requirement of electricity on monthly basis
for the ensuing year to the Commission on or before 15th
September each year.
7
BIHAR GAZETTE (EXTRA), 3RD APRIL 2018
8.1.2 The Commission may call for such additional information
or particulars or documents as the Commission may
consider necessary for approving the power Procurement
Plan;
8.1.3 The Commission may, at its discretion, direct the licensee(s)
to publish the main details of the demand forecasted and
power procurement plan with such particulars and in such
manner as the Commission may direct, so as to enable any
member of the public who desires to file objections,
comments or suggestions, to do so, in the manner indicated
in the Conduct of Business Regulations of the Commission.
The Commission shall consider such representations before
approval of the plan;
8.1.4 Commission shall approve such short-term power
procurement plan with such modifications or such
conditions as may be specified in that order or reject the
same after giving the Distribution licensee(s) ample
opportunity of being heard by 15th November each year.
8.2 Long Term Power Procurement Plan
8.2.1 The Distribution Licensee(s) shall submit the rolling Long
term power procurement plan including the assessment of
availability and requirement of electricity prepared in
accordance with regulation 6.2 to 6.5 of these Regulations.
The rolling plan of next ten years will be filed to the
Commission along with ARR of each year, duly updating the
preceding Long Term Power Procurement Plan, to take the
latest development into account.
8.2.2 The Commission shall approve such Long Term Power
Procurement Plan with such modifications or such
conditions as may be specified in the order along with the
Tariff order each year.
9. Criterion for Power Purchases
9.1 The Distribution Licensee(s) shall effect power purchase or enter
into long term or short-term power purchase agreements or
arrangements in accordance with the Power Procurement Plan
approved by the Commission;
9.2 While effecting power purchase, the Distribution Licensee(s) shall
adhere to the principle of least cost plan (least financial cost to the
Distribution Licensee), the ultimate objective being to make
available secure and reliable power supply at economically viable
tariffs to all consumers while satisfying power supply planning
and security standards.
9.3 The Commission may, from time to time, specify criterion for
Power Purchase from hydro, co-generation & renewable generating
stations. The criterion shall, inter alia, consider any policy
directive of State Government, Commission directives on power
purchase, allocation including temporary allocation and diversion
of power from different sources, generation from conventional and
renewable energy sources.
9.4 There shall be mechanism of consultation among STU,
Transmission Licensee, generating companies and Distribution
Licensee(s) & SLDC for formulating Power Procurement Plan. The
Distribution Licensee(s) shall make the assessment of availability
8 BIHAR GAZETTE (EXTRA) 3RD APRIL 2018
and requirement of electricity in consultation with the State
Government, all concerned generating companies, Transmission
Licensees, Eastern Regional Power Committee, National/ Regional
Load Despatch Centre(s), Central Electricity Authority and other
concerned entities;
9.5 The Distribution Licensee(s) shall endeavour not to import reactive
power from the Eastern Grid. Requirement of reactive
compensation in the State power system to be provided by
Transmission and Distribution Licensee and generating
Companies will be finalised in Consultation with ERLDC/SLDC.
10. Power procurement procedure
10.1 Short-Term Power Procurement Procedure
10.1.1 After approval of the short term Power Procurement Plan
by the Commission, Distribution Licensee(s) shall
procure required power through transparent open
competitive bidding in accordance with the bidding
Guidelines, as amended from time to time, for short term
procurement of power under section 63 of the Act or
through power exchange or bilateral banking
arrangements.
10.1.2 The Distribution Licensee(s) shall be free to procure
power as per Power Procurement Plan approved by the
Commission from any source for meeting short-term
demand of power by adopting transparent bidding
process as per the bidding guidelines of the Ministry of
Power, Government of India referred above and in such
case the licensee need not approach the Commission for
prior approval but shall intimate about the initiation of
such procurement process. These Guidelines shall be
binding on the procurer [Distribution Licensee(s)].
10.1.3 In case there is any deviation from the bidding
Guidelines, the Distribution licensee(s) shall obtain prior
approval of the Commission and the Commission shall
decide on the modifications to the bid documents within
a reasonable time in accordance with provisions of the
bidding guidelines;
10.1.4 In case of emergency condition arising due to
shortage/non-availability of fuel, unplanned/forced
outage of a generator etc. which necessitates emergency
procurement of power, efforts shall be made to carry out
such emergency purchases through Power Exchange. In
such case, the license(s) need not to approach the
Commission for prior approval.
10.1.5 For cost optimization of power purchase cost, efforts
shall be made to replace long term power having higher
variable rates through purchase from Power Exchange.
In such a case, the license(s) need not to approach the
Commission for prior approval.
10.1.6 For procurement of additional power over and above the
quantum approved by the Commission in the short-term
power procurement plan, licensee (s) shall seek the prior
approval of the Commission.
9
BIHAR GAZETTE (EXTRA), 3RD APRIL 2018
10.1.7 Within 15 days from the date of entering into an
agreement or arrangement of short term procurement,
the Distribution Licensee(s) shall submit to the
Commission providing full details of such agreement or
arrangement including quantum, duration, supplier
detail, procedure adopted for supplier selection,
reasonability of cost and any other detail seeking
adoption of the tariff under Section 63 of the Act.
10.1.8 The Commission shall adopt the tariff subject to
reasonability or reject the same, after giving ample
opportunity to the Distribution licensees of being heard,
within a reasonable time not exceeding 60 days.
10.1.9 Licensee(s) shall submit monthly return to the
Commission in the proforma as may be specified by the
Commission giving all the details of procurement/sale
carried out during the month.
10.2 Long Term Power Procurement Procedure
10.2.1 Tariff Policy issued by Central Govt. shall be basic
guiding principle for any long term power procurement;
10.2.2 Unless otherwise approved by the Commission by a
general or special order, long-term power purchase or
procurement by the Distribution Licensee(s) shall be
done through a competitive procurement process;
10.2.3 The Competitive Procurement Process shall be as per the
bidding Guidelines. These Guidelines shall be binding on
the procurers [Distribution Licensee(s)].
10.2.4 In case there is any deviation from the bidding
Guidelines, the Distribution licensee(s), shall obtain prior
approval of the Commission and the Commission shall
decide on the modifications to the bid documents within
a reasonable time in accordance with provisions of the
bidding guidelines;
10.2.5 The rate of power purchase in cases of generating
companies, which are not covered under the process of
competitive bidding as per Section 63 of the Act shall be
determined by the Commission under Section 62 of the
Act subject to the provisions in Tariff Policy;
10.2.6 Any long-term power purchase arrangements made
through MOUs and PPAs with the generating companies
by the Distribution Licensee(s) prior to the issue of these
Regulations will not come under the purview of these
Regulations till their validity;
10.2.7 All power purchase for a period of more than one year
and less than 10 years will be treated at par with long-
term power purchase.
10.2.8 Within 15 days from the date of entering into an
agreement or arrangement of long term procurement, the
Distribution Licensee(s) shall submit to the Commission
providing full details of such agreement or arrangement
including quantum, duration, supplier detail, procedure
adopted for supplier selection, reasonability of cost and
any other detail seeking adoption of the tariff under
Section 63 of the Act.
10 BIHAR GAZETTE (EXTRA) 3RD APRIL 2018
10.2.9 The Commission shall adopt the tariff subject to
reasonability or reject the same, after giving ample
opportunity to the Distribution licensees of being heard,
within a reasonable time not exceeding 60 days.
11. Power Purchase Arrangements or Agreements
11.1 Commencement of power under any new long term or short term
power purchase arrangement or agreement and amendments to
existing PPA entered into by Distribution Licensee(s), shall be
subject to prior approval of the Commission under section 86 of
the Act, in respect of:-
(i) Necessity;
(ii) Reasonability of cost;
(iii) Promoting efficiency, economy, equitability and competition ;
(iv) Conformity with regulations for investment approval;
(v) Conformity with requirements of quality, continuity and
reliability of supply;
(vi) onformity with safety and environmental standards;
(vii) Conformity with criterion of power purchase as laid down in
these Regulations;
(viii) Conformity with policy directives of the State Government
and policies issued by the Government of India viz. National
Electricity Policy, Tariff Policy, long term and short term
power procurement bidding guidelines.
12. Intervention in the Procurement Process
12.1 Once the Distribution Licensee(s) have begun to implement a
procurement process in accordance with these Regulations, the
Commission shall not intervene except on the grounds -
a) of mala fide or improper conduct ; and/or
b) the manner in which the Distribution Licensee(s) is
conducting the procurement process differs materially from
its proposal as approved by the Commission; and
c) on other reasonable grounds.
12.2 These provisions are without prejudice to the Commission's right
to investigate and take appropriate action on credible information
of malpractice becoming available to it;
12.3 Any investigation of a procurement process will be initiated by a
notice of inquiry and conducted in accordance with the
Commission's Conduct of Business Regulations. The Distribution
Licensee(s) shall not enter into any commitment to procure power
or act upon such a commitment pending the outcome of such
investigation;
12.4 If the Commission determines that the procurement process was
unsatisfactory and not in line with these Regulations, the
Commission may order the Licensee(s) to take necessary corrective
steps, including requiring it temporarily to suspend the
procurement process, or to cancel it and declare the results null
and void;
12.5 If the results of the procurement process are declared null and
void, the Distribution Licensee(s) shall so notify to the public and
bidders;
11
BIHAR GAZETTE (EXTRA), 3RD APRIL 2018
12.6 Nothing in these Regulations shall prevent the Commission from
investigating or taking such other action, as it deems appropriate,
with respect to a completed power purchase agreement in the
exercise of its responsibilities under the Act.
Previous and next
All provisions of Power Purchase and Procurement Process of Licensee Regulations, 2018
Questions people ask
Is regulation 6 of Power Purchase and Procurement Process of Licensee Regulations, 2018 still in force?
No repeal of Power Purchase and Procurement Process of Licensee Regulations, 2018 is recorded.