14. Project identification, prioritization and implementation.
(a) On identifying or conceptualizing a project to be developed, managed and
operated in the State, the Board, on its own accord or based on a study or
survey caused to be conducted or based on inputs received from a third
party, may seek the views of the public agency concerned thereon:
Provided that if the public agency does not furnish its views with in thirty
days from the date of receipt of the said communication from the Board, it
shall be deemed that the public agency has no view to offer.
15
Tripura Gazette, Extraordinary Issue, July 24, 2018 A. D.
(b) Any Government Department may also identify or conceptualize a project to
be developed, managed and operated in the State and send the proposal
thereafter to the Board for its recommendation. The Board shall scrutinize,
evaluate and where more than one such proposal is received, prioritize the
same.
(c) The Board, on receipt of the views of the public agency under sub-section
(a) or proposal from any Government Department under sub-section (b),
shall examine the project proposal with reference to the cost benefit analysis
of the project including the socio-economic ‘cost benefit and shall appraise
the project proposal with sufficient details;
(d) Where the public agency or the Government Department has proposed a
project through Public-Private Partnership, the Board shall further examine
the project with reference to the following factors, namely:-
(i) the cost effectiveness of implementation through public-private
partnership with value for Money test, as may be specified in the
scheme;
(ii) the possibility of specifying project performance parameters and
measuring their outcomes;
(iii) the risk sharing with the participants;
(iv) the technological and managerial advantages due to participation;
(v) the socio-economic factors which may affect investment by the
participant;
(vi) compliance with regulatory norms.
(e) The Board, may cause a feasibility study of the proposed project and after
satisfying itself as to its feasibility, may recommend the same to the
Government, indicating specifically as to whether it may be implemented
through public sector mode or through public private partnership.
(f) The Board shall cause the details of projects recommended under sub-
section (e), to be published on its website and on such other websites, as
may be specified in the Scheme:
16
Tripura Gazette, Extraordinary Issue, July 24, 2018 A. D.
Provided that the Board may, for reasons to be recorded in writing, choose
not to publish the details of a Project.
(g) On receipt of proposal for implementation of the Project under sub-section
(e), the Government shall consider the same and communicate its decision
on the implementation of the Project including the mode of its
implementation, to the Board.
(h) In respect of a Project decided by the Government to be implemented
through public sector mode, the Board shall designate the public agency
which shall implement that Project, give direction for its implementation and
monitor the progress of implementation.
(i) If the public agency does not commence the Project within three months
from the date of receipt of such direction or expresses its inability to
implement the Project, for any reason recorded in writing, the Board with
the approval of the Government may re-examine the Project as in sub-
section (c) and make a fresh recommendation to the Government.
(j) In respect of Project decided by the Government to be implemented through
Public-Private Partnership, the Board shall cause the sponsoring agency to
publish the details of the proposed projects in such form and in such
manner, as may be specified in the Scheme, inviting objections and
suggestions. The sponsoring agency shall, based on the objections and
suggestions, if any, received, prepare and submit a report to the Board
within such period, as may be specified in the Scheme.
(k) The Board, on receipt of the report from the sponsoring agency under sub-
section (j), shall consider the project in consultation with the administrative
department and after causing the detailed project study, if it considers
necessary, finalize the scope and structure of the Project, either in its
original form or with such modification, as it deems fit, also taking into
account, the following aspects, namely:-
(i) whether the Project needs any public financial support, and if so,
the appropriate form of- such support;
17
Tripura Gazette, Extraordinary Issue, July 24, 2018 A. D.
(ii) the tender criteria or variables relevant for evaluation of the tender;
and
(iii) the appropriate concession agreement or a combination thereof,
from out of those listed in Third Schedule.
Previous and next
All sections of The Tripura Infrastructure Investment Fund Act,2018
Questions people ask
Is section 14 of the Tripura Infrastructure Investment Fund Act,2018 still in force?
No repeal of the Tripura Infrastructure Investment Fund Act,2018 is recorded.