LawGrids logoLAWGRIDS.ORG

Section 17, THE SIKKIM GREENFIELD AIRPORT, PAKYONG (SETTLEMENT OF CLAIMS FOR LOSS AND DAMAGES) ACT,2018

THE SIKKIM GREENFIELD AIRPORT, PAKYONG (SETTLEMENT OF CLAIMS FOR LOSS AND DAMAGES) ACT,2018 (14 of 2018) - Section 17

Text of section 17

17. Appeal and Execution - The Award of the Claims Commissioner, both interim and final, shall be deemed to be a decree of a Civil Court for the purposes of appeal and execution, which shall be governed by the provisions of the Code of Civil Procedure, 1908 (5 of 1908).

Previous and next

All sections of THE SIKKIM GREENFIELD AIRPORT, PAKYONG (SETTLEMENT OF CLAIMS FOR LOSS AND DAMAGES) ACT,2018

Questions people ask

Is section 17 of THE SIKKIM GREENFIELD AIRPORT, PAKYONG (SETTLEMENT OF CLAIMS FOR LOSS AND DAMAGES) ACT,2018 still in force?

No repeal of the SIKKIM GREENFIELD AIRPORT, PAKYONG (SETTLEMENT OF CLAIMS FOR LOSS AND DAMAGES) ACT,2018 is recorded.